HomeMy WebLinkAboutItem 8 Lake Elmo Avenue Sewer Project Schedule 3-12-2013PROJECT SCHEDULE
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283 DATE: March 12, 2013
City of Lake Elmo, Minnesota
Project No. 2013.123
Lake Elmo Avenue Sewer Infrastructure Improvements: I-94 to 30th Street
March 19, 2013 Council Workshop – Address Scope of Improvements/Project Schedule
March 19, 2013 Council orders preparation of Plans and Specifications/approves Engineering Contract
March 26, 2013 Project kick-off meeting [8 Weeks for Design]
June 18, 2013 City Engineer presents Plans and Specifications for Council approval
June 21, 2013 Placement of Ad for Bids
July 23, 2013 Receive Contractor Bids
August 6, 2013 City Council accepts bids and awards Contract
September 9, 2013 Issue Notice to Proceed. Contractor begins Work
December 20, 2013 Substantial Completion [includes all pipe installation, Lift Station start-up, paving]
15 Weeks [8-12 week pump & control panel lead time]
June 1, 2014 Final Completion [includes restoration, and punch list items]