HomeMy WebLinkAboutItem 13 - Inwood Watermain Ext-Project SchedulePROJECT SCHEDULE FOCUS ENGINEERING, inc. Cara Geheren, P.E. 651.300.4261 Jack Griffin, P.E. 651.300.4264 Ryan Stempski, P.E. 651.300.4267 Chad Isakson, P.E. 651.300.4283 Project Title: Inwood Booster Station and Trunk Watermain Extension – Feasibility Report Client: City of Lake Elmo Project No.: 2013.1xx Date: July 26, 2013 August 6, 2013 Council orders preparation of a Feasibility Report. August 8, 2013 Team kickoff meeting. Schedule resident meeting and send out NOTICES. TBD, 2013 Resident meeting to present the project. September 3, 2013 Presentation of Feasibility Report to Council. Council passes resolution receiving report and calling for a hearing on improvements to be held October 1, 2013. September 4, 2013 Send notice of public hearing to residents and post in newspaper. October 1, 2013 Public Improvement Hearing. Council passes resolution ordering Improvement and preparation of Plans. February 4, 2014 Approve Plans and Specifications and authorize advertisement for bids. March 6, 2014 Accept Contractor Bids March 18, 2014 Award Contract. March 21, 2014 Process and send out Contract Documents. April 11, 2014 Receipt of Contractor’s Bonds / Legal Review. April 15, 2014 Conduct Pre-construction Meeting & Issue Notice to Proceed. September, 2014 Substantial completion. October, 2014 Final Completion Date. Record As-builts; Testing Results; and Final Recommendation Letter to City Engineer.