HomeMy WebLinkAboutItem 7 CERTIFICATE_OF_COMPLETION
CITY OF LAKE ELMO, MN 2013 SEAL COAT PROJECT PROJECT NO. 2013.118
CERTIFICATE OF COMPLETION
DATE OF ISSUANCE: August 20, 2013
OWNER: CITY OF LAKE ELMO, MN
CONTRACTOR: PEARSON BROTHERS, INC.
PROJECT NAME: 2013 SEAL COAT PROJECT
PROJECT NO.: 2013.118
This Certification of Completion applies to all work under the Contract Documents
This Certification of Completion applies to the following specified parts of the Contract Documents
I do hereby certify that the work to which this Certificate applies has been constructed in
accordance with the Contract dated May 21, 2013. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: August 20, 2013 Ryan W. Stempski Reg. No. 45395
FOCUS Engineering, inc.
THE WARRANTY PERIOD BEGINS August 20, 2013 AND ENDS August 20, 2015