HomeMy WebLinkAboutItem 7 - 2013-08-16 Change Order No 3 CONTRACT CHANGE ORDER FORM
CITY OF LAKE ELMO, MINNESOTA FOCUS ENGINEERING, inc.
KEATS MSA STREET AND TRUNK WATERMAIN IMP
PROJECT NO.2012.129
CHANGE ORDER NO. 3 DATE: August 16, 2013
TO: T.A.SCHIFSKY&SONS, INC.,2370 E HIGHWAY 36,NORTH ST. PAUL, MN 55109
This Document will become a supplement to the Contract and all provisions will apply hereto.The Contract Documents are
modified as follows upon execution of this Change Order.
CHANGE ORDER DESCRIPTION/JUSTIFICATION:
This change order provides compensation to the contractor to install concrete curb and gutter in two pours(instead of one
pour)across 2 residential driveways.The change was made at the direction of the engineer to allow property owners access to
their properties during the curb and gutter placement and curing periods.These properties had homes with substantial setbacks
from the roadway.This required the Contractor to re-mobilize crews to complete the work,which was not included in their
original contract. This change order also extends the contract times for project completion by 26 days;revising the Substantial
Completion date from August 30,2013 to September 25,2013,and the Final Completion date from October 4,2013 to October
30,2013.This extension accounts for all delays to the contractor expreienced to date on the project that were beyond the
control of the contractor,including delays from private utility conflicts,abnormal weather conditions,and all other unforeseen
conditions and job site changes.
Attachments (list documents supporting change): N/A
ITEM DESCRIPTION OF PAY ITEM UNIT CITY UNITE PRICE INCREASE/(DECREASE)
CO3-1 Remobilize Concrete Crew for half pours EA 2 $1,650.00 $3,300.00
CO3-2 Revise Substantial Completion Date N/A N/a $0.00 $0.00
NET CONTRACT CHANGE $3,300.00
Amount of Original Contract $ 1,606,833.47
Sum of Additions/Deductions approved to date(CO Nos. 1,2) $ 3,960.00
Contract Amount to date $ 1,610,793.47
Amount of this Change Order (ADD) (DEDUCT-) (^.o��.,^^���) $ 3,300.00
Revised Contract Amount $ 1,614,093.47
The Contract Periods for Completion will be (UNCHANGED) (INCREASED) (DECREASED) 26 days
APPROVED BY ENGINEER: FOCUS Engineering,inc. APPROVED BY CON T OR
di
ENGINEER BY
8/16/2013
DATE DATE
APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA
BY BY
DATE DATE
FOCUS Engineering,inc. CHANGE ORDER FORM