Loading...
HomeMy WebLinkAboutItem 12 - Lake Elmo Avenue Trunk Watermain-Project Schedule PROJECT SCHEDULE FOCUSENGINEERINGY inc. Cara Geheren, P.E. 651.300.4261 Jack Griffin,P.E. 651.300.4264 Ryan Stempski,P.E. 651.300.4267 Chad Isakson,P.E. 651.300.4283 Project Title: Lake Elmo Avenue Trunk Watermain Improvements Client: City of Lake Elmo Project No.: 2013.1xx Date: September 17, 2013 September 17, 2013 Council orders preparation of a Feasibility Report. November 5, 2013 Presentation of Feasibility Report to Council. Council passes resolution receiving report and calling for a hearing on improvements to be held December 3, 2013. November 21, 2013 Property owner meeting. Presentation of Report findings and recommendations. December 3, 2013 Public Improvement Hearing. Council passes resolution ordering Improvement and preparation of Plans. March 4, 2014 Approve Plans and Specifications and authorize advertisement for bids. April 8, 2014 Accept Contractor Bids April 15, 2014 Award Contract. May 12, 2014 Conduct Pre-construction Meeting & Issue Notice to Proceed. September, 2014 Substantial completion. October, 2014 Final Completion Date. Record As-builts; Testing Results; and Final Recommendation Letter to City Engineer.