HomeMy WebLinkAboutItem 12 - 2014 Street Improvements-Project SchedulePROJECT SCHEDULE
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283 Project Title: 2014 Street Improvements
Client: City of Lake Elmo
Project No.: 2013.135
Date: September 26, 2013
October 1, 2013 Council orders preparation of a Feasibility Report.
December 3, 2013 Presentation of Feasibility Report to Council. Council passes resolution receiving
report and calling for a hearing on improvements to be held January 7, 2013.
January 16, 2013 Property owner meeting. Presentation of Report findings and recommendations.
January 21, 2013 Public Improvement Hearing. Council passes resolution ordering Improvement and
preparation of Plans.
April 15, 2014 Approve Plans and Specifications and authorize advertisement for bids.
May 15, 2014 Accept Contractor Bids
June 3, 2014 Award Contract.
June 24, 2014 Conduct Pre-construction Meeting & Issue Notice to Proceed.
September, 2014 Substantial completion.
October, 2014 Final completion.