Project Title: Well No. 4 Connecting Watermain Improvements
Client: City of Lake Elmo
Project No.: 2013.131
Date: REVISED September 24, 2013
August 6, 2013 Council orders preparation of a Feasibility Report and preparation of the Plans and
Specifications.
August 8, 2013 Team kickoff meeting. Schedule resident meeting and send out NOTICES.
August 21, 2013 Conduct resident meeting to present the project (following TH 5 Open House).
September 3, 2013 Presentation of Feasibility Report to Council. Council passes resolution receiving
report and calling for a hearing on improvements to be held October 1, 2013.
September 4, 2013 Send notice of public hearing to residents and post in newspaper.
October 1, 2013 Public Improvement Hearing. Council Orders the Improvement.
January 21, 2014 Council Approve Plans and Specifications and Orders Advertisement for Bids.
February 20, 2014 Receive Contractor bids.
March 4, 2014 City Council accepts bids and awards Contract.
April 1, 2014 Conduct Pre-construction Meeting & Issue Notice to Proceed.
June 20, 2014 Work is substantially complete (estimated 12 weeks).
July 18, 2014 Final Completion Date. Record As-builts; Testing Results; and Final Recommendation
Letter to City Engineer.