Loading...
HomeMy WebLinkAboutItem 7 - Project Schedule PROJECT SCHEDULE FOCUSENGINEERING1 inc. CITY OF LAKE ELMO Cara Geheren, P.E. 651.300.4261 Jack Griffin,P.E. 651.300.4264 LAKE ELMO AVENUE TRUNK WATERMAIN IMPROVEMENTS Ryan Stempski,P.E. 651.300.4267 PROJECT NO. 2013.133 Chad Isakson,P.E. 651.300.4283 SEPTEMBER 2013 September 17, 2013 Council authorizes Feasibility Report. November 6, 2013 Presentation of Feasibility Report. Council accepts Report and Calls Hearing. November, 2013 Property owner meeting. Presentation of Report findings and recommendations. December 3, 2013 Public Improvement Hearing. Council orders Preparation of plans and specifications. March 4, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids. April 8, 2014 Receive Contractor Bids. April 15, 2014 Council accepts bids and awards Contract. May 12, 2014 Conduct Pre-construction Meeting and Issue Notice to Proceed. September, 2014 Substantial completion (estimated 10-13 weeks). October, 2014 Final Completion.