HomeMy WebLinkAboutItem 8 - Project Schedule PROJECT SCHEDULE FOCUSENGINEERING1 inc.
CITY OF LAKE ELMO Cara Geheren, P.E. 651.300.4261
Jack Griffin,P.E. 651.300.4264
INWOOD BOOSTER STATION AND Ryan Stempski,P.E. 651.300.4267
TRUNK WATERMAIN IMPROVEMENTS Chad Isakson,P.E. 651.300.4283
PROJECT NO. 2012.126
NOVEMBER 2013
August 6, 2013 Council authorizes Feasibility Report.
December 3, 2013 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
January, 2014 Property owner meeting. Presentation of Report findings and recommendations.
January 21, 2014 Public Improvement Hearing. Council Orders Improvement and Preparation of plans
and specifications.
April 15, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.
May 13, 2014 Receive Contractor Bids.
May 20, 2014 Council accepts bids and awards Contract.
June 9, 2014 Conduct Pre-construction Meeting and Issue Notice to Proceed.
September, 2014 Substantial completion.
October, 2014 Final completion.