HomeMy WebLinkAboutItem 10 - Lake Elmo Ave Sewer CO #3 CONTRACT CHANGE ORDER FORM CITY OF LAKE ELMO, MINNESOTA FOCUS ENGINEERING, inc. LAKE ELMO AVE SEWER INFRASTRUCTURE IMPROVEMENTS 2013.123 CHANGE ORDER NO. 3 DATE: January 6, 2014 TO: Minger Construction, Inc. 2471 Galpin Court,Suite 110,Chanhassen, MN 55317 This Document will become a supplement to the Contract and all provisions will apply hereto.The Contract Documents are modified as follows upon execution of this Change Order. CHANGE ORDER DESCRIPTION/JUSTIFICATION: This change order extends the contract times for Substantial Completion date by 56 days(from December 20,2013 to February 14,2014). This extension request is early frost conditions in December and a delay in the lift station start-up based on the delivery date of the chemical feed system. The Final Completion Date of June 1,2014 remains unchanged. Attachments (list documents supporting change): ITEM DESCRIPTION OF PAY ITEM UNIT CITY UNITE PRICE INCREASE/(DECREASE) CO3-1 REVISE SUBSTANTIAL COMPLETION DATE N/A N/A $0.00 $0.00 NET CONTRACT CHANGE $0.00 Amount of Original Contract $ 3,463,201.60 Sum of Additions/Deductions approved to date (CO#1 and#2) $ (10,533.70) Contract Amount to date $ 3,452,667.90 Amount of this Change Order (AD-D) (DE (NO CHANGE) $ 0.00 Revised Contract Amount $ 3,452,667.90 The Contract Period for Completion will be (UNCHANGED) (INCREASED) (DEED;) 56 days APPROVED BY ENGINEER: FOCUS Engineering, inc. APPROVED BY CONTRACTOR ENGINEER BY J DATE DATE APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA BY BY DATE DATE FOCUS Engineering,inc. CHANGE ORDER FORM