HomeMy WebLinkAboutItem 17 - Pumphouse#4 Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
PUMPHOUSE NO. 4
PROJECT NO. 2013.132
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
REVISED DECEMBER 2013
August 6, 2013 Council authorizes preparation of Pland and Specifications. Approves Engineering
Services contract.
January 6, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.
February 5, 2014 Receive Contractor Bids.
February 18, 2014 Council accepts bids and awards Contract.
March 11, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
October 10, 2014 Substantial completion (estimated 26 weeks).
November 21, 2014 Final Completion (estimated 7 weeks).