HomeMy WebLinkAboutItem 10 - 4-Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
INWOOD BOOSTER STATION AND
TRUNK WATERMAIN IMPROVEMENTS
PROJECT NO. 2012.126
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
JANUARY 2014
TRUNK WATERMAIN PROJECT SCHEDULE
January 21, 2014 Public Improvement Hearing. Council Orders Improvement and Preparation of plans
and specifications.
April 15, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.
May 13, 2014 Receive Contractor Bids.
May 20, 2014 Council accepts bids and awards Contract.
June 9, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
September, 2014 Substantial completion.
October, 2014 Final completion.
BOOSTER STATION PROJECT SCHEDULE
January 21, 2014 Public Improvement Hearing. Council Orders Improvement and Preparation of plans
and specifications.
May 20, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.
June 12, 2014 Receive Contractor Bids.
June 17, 2014 Council accepts bids and awards Contract.
June 30, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
Engineer Recommendation ‐ Substantial and Final completion.