HomeMy WebLinkAboutItem 8 - Engineer's Post-design Estimate of Construction CostsLake Elmo Wellhouse No. 4
Item Cost
Divisions 0 and 1 - General Conditions, building permits, bonds,
insurance, mobilization, construction allowances, project
management, and site supervision 60,000$
Division 2 - Site Work 35,000$
Division 3 - Concrete 123,500$
Division 4 - Masonry 60,000$
Division 5 - Metals 10,000$
Division 6 - Carpentry 5,000$
Division 7 - Thermal and Moisture Protection 20,000$
Division 8 - Doors and Windows 8,000$
Division 9 - Finishes 30,000$
Division 10 - Specialties 3,000$
Division 11 - Equipment 40,000$
Division 15 - Mechanical 85,000$
Division 16 - Electrical 154,000$
Total Opinion of Probable Construction Cost $633,500
Estimated 3 Ph Electric Service from Xcel Energy 97,000$
Estimated Natural Gas Service from Xcel Energy (Gas in ROW)-$
Subtotal 730,500$
5% Contingency 36,525
Subtotal Project Cost 767,025$
Engineer's Preliminary Opinion of Probable Construction Cost
November 21, 2013