HomeMy WebLinkAboutItem 8 - Pumphouse#4 Project SchedulePROJECT SCHEDULE  CITY OF LAKE ELMO    PUMPHOUSE NO. 4  PROJECT NO. 2013.132  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.  651.300.4261 Jack Griffin, P.E.               651.300.4264  Ryan Stempski, P.E. 651.300.4267  Chad Isakson, P.E. 651.300.4283  REVISED DECEMBER 2013               August 6, 2013 Council authorizes preparation of Pland and Specifications. Approves Engineering  Services contract.    January 6, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.    February 5, 2014 Receive Contractor Bids.    February 18, 2014 Council accepts bids and awards Contract.    March 11, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.    October 10, 2014 Substantial completion (estimated 26 weeks).    November 21, 2014 Final Completion (estimated 7 weeks).