HomeMy WebLinkAboutItem 3 - 2014 Seal Coat Project ScheduleCITY OF LAKE ELMO 2014 SEAL COAT PROJECT PROJECT NO. 2014.118 PROJECT SCHEDULE February 18, 2014 Council orders preparation of Plans and Specifications. April 1, 2014 Presentation of Plans and Specifications. Council Approves Plans and Specifications and Orders Advertisement for Bids. April 5, 2014 Placement of Advertisement for Bids. –Oakdale-Lake Elmo Review. Publication on April 9 – Quest CDN. Publication on April 2 May 1, 2014 Receive Contractor bids. May 20, 2014 City Council accepts bids and awards Contract. May 23, 2014 Process and send out Contract Documents. June 6, 2014 Receipt of Contractor’s Bonds/Legal Review. June 10, 2014 Conduct Pre-Construction Meeting and Issue Notice to Proceed. June 11, 2014 Contractor begins Work. July 18, 2014 Substantial Completion of Work (including sweeping of excess aggregate). August 22, 2014 Final Completion of Work (including Punchlist and final documentation).