HomeMy WebLinkAboutItem 10 - 3-Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
LAKE ELMO AVENUE TRUNK WATERMAIN IMPROVEMENTS
PROJECT NO. 2013.133
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
APRIL 2014
September 17, 2013 Council authorizes Feasibility Report.
November 6, 2013 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
November 21, 2013 Property owner meeting. Presentation of Report findings and recommendations.
December 3, 2013 Public Improvement Hearing. Council orders Preparation of plans and specifications.
April 15, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.
May 15, 2014 Receive Contractor Bids.
June 3, 2014 Council accepts bids and awards Contract.
June 16, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
October, 2014 Substantial completion (estimated 15 weeks).
November, 2014 Final Completion.