HomeMy WebLinkAboutItem 5 - 6-39th St Street and Sewer-Project SchedulePROJECT SCHEDULE CITY OF LAKE ELMO 39th Street North Street and Sanitary Sewer Schedule PROJECT NO. 2014.131 FOCUS ENGINEERING, inc. Cara Geheren, P.E. 651.300.4261 Jack Griffin, P.E. 651.300.4264 Ryan Stempski, P.E. 651.300.4267 Chad Isakson, P.E. 651.300.4283 MARCH 2014 March 18, 2014 Council Declares Adequacy of Petition and Orders Preparation of Feasibiilty Report. April 15, 2014 Presentation of Feasibility Report. Council accepts Report and Calls Hearing. April 29, 2014 Property owner meeting. Presentation of Report findings and recommendations. May 6, 2014 Public Improvement Hearing. Council orders Preparation of plans and specifications. July 1, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids. July 31, 2014 Receive Contractor Bids. August 5, 2014 Council accepts bids and awards Contract. August 25, 2014 Conduct Pre-construction Meeting and Issue Notice to Proceed. November 28, 2014 Substantial completion (estimated 12 weeks). Summer, 2015 Final Completion.