October 1, 2013 Council authorizes Feasibility Report.
January 6, 2014 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
January 23, 2014 Property owner meeting. Presentation of Report findings and recommendations.
February 5, 2014 Public Improvement Hearing. Council orders Preparation of plans and specifications.
May 6, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.
June 5, 2014 Receive Contractor Bids.
June 17, 2014 Council accepts bids and awards Contract.
July 8, 2014 Conduct Pre-construction Meeting and Issue Notice to Proceed.
October 10, 2014 Substantial completion (estimated 12-15 weeks).