CITY OF LAKE ELMO
VILLAGE EAST TRUNK SANITARY SEWER IMPROVEMENTS
PROJECT NO. 2014.131
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
JUNE 2014
June 17, 2014 Council Orders Preparation of Feasibiilty Report.
Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
Council approves Plans and Specifications; Orders Advertisement for Bids.
(project is added to the 39th Street: Street and Sanitary Sewer Improvements as an add alternate bid).
July 10, 2014 Receive Contractor Bids
July 15, 2014 Public Improvement Hearing. Council Orders the Improvement, accepts bids and
awards Contract.
July 28, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
November 28, 2014 Substantial completion (estimated 17 weeks).
December 16, 2015 Final Completion.