HomeMy WebLinkAboutItem 9 - Signed Change Order 5 XNTRACT CHANGE ORDER FORM
CITY OF LAKE ELMO, MINNESOTA FOCUS ENGINEERING, inc.
LAKE ELMO AVE SEWER INFRASTRUCTURE IMPROVEMENTS
2013.123
CHANGE ORDER NO. 5 DATE: June 17, 2014
TO: Minger Construction, Inc. 2471 Galpin Court,Suite 110, Chanhassen, MN 55317
This Document will become a supplement to the Contract and all provisions will apply hereto.The Contract Documents are modified
as follows upon execution of this Change Order,
CHANGE ORDER DESCRIPTION/JUSTIFICATION:
This change order is being issued to(1)Provide a locking enclosure to cover the key pad and switch on the front of the automatic transfer switch
located at the Lisbon Avenue Lift Station,(2)Mill and re-pave the intersection of 30th Street and Lake Elmo Avenue to to improve rideabilAy and
facilitate drainage,and(3)Install a permanent riprap channel along the Lisbon Avenue Lift Station driveway to correct repeat erosion issues.
Attachments (list documents supporting change):
ITEM DESCRIPTION OF PAY ITEM UNIT CITY UNIT PRICE INCREASE/(DECREASE)
C05-1 LOCKING COVER FOR AUTOMATIC TRANSFER SWITCH LS 1 $1,050.00 S1,050.00
C05-2 MILL AND REPAVE LE AVE AND 30TH ST INTERSECTION LS 1 $3,000.00 $3,000.00
C05-3 GRADING FOR RIPRAP CHANNEL ALONG LS DRIVEWAY LS 1 $1,400.00 $1,400.00
C05-4 INSTALL RIPRAP CHANNEL ALONG LS DRIVEWAY TN 70 $72.25 $5,057.50
NET CONTRACT CHANGE $10,507.50
Amount of Original Contract $ 3,463,201.60
Sum of Additions/Deductions approved to date(CO#1-4) $ (4,480.36)
Contract Amount to date $ 3,458,721.24
Amount of this Change Order (ADD) (DEDUCT-) {P O GHAP}6€) $ 10,507.50
Revised Contract Amount $ 3,469,228.74
The Contract Period for Completion will be (UNCHANGED) (INGR,�r.cASEEP) (DEGREASED) 0 days
APPROVED BYE EER: FOCU ngineering,inc. APPROVED BY CONTRACTOR
ENGINEER BY
O - Z-0Iy - ID- ZDIZ/
DATE DATE
APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA
BY BY
DATE DATE
FOCUS Engineering,inc. CHANGE ORDER FORM