HomeMy WebLinkAboutItem 16 - 2015 Street Improvements-Preliminary Project SchedulePRELIMINARY PROJECT SCHEDULE
CITY OF LAKE ELMO
2015 STREET & UTILITY IMPROVEMENTS
PROJECT NO. 2014.136
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
JUNE 2014
July 1, 2014 Council authorizes Feasibility Report.
September 2, 2014 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
September, 2014 Property owner meeting. Presentation of Report findings and recommendations.
October 7, 2014 Public Improvement Hearing. Council orders Preparation of plans and specifications.
January 20, 2015 Council approves Plans and Specifications; Orders Advertisement for Bids.
February 19, 2015 Receive Contractor Bids.
March 3, 2015 Council accepts bids and awards Contract.
April 15, 2015 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
August 28, 2015 Substantial completion.
October 16, 2015 Final completion.