HomeMy WebLinkAboutItem 17 - Old Village Ph1 Street and Utility Improvements-Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
OLD VILLAGE PHASE 1 STREET & UTILITY IMPROVEMENTS
PROJECT NO. 2014.137
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
JUNE 2014
July 1, 2014 Council authorizes Feasibility Report.
September 16, 2014 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
October, 2014 Property owner meeting. Presentation of Report findings and recommendations.
October 21, 2014 Public Improvement Hearing. Council orders Preparation of plans and specifications.
*PLANS AND SPECIFICATIONS WILL BE PREPARED IN CONJUNCTION WITH THE CSAH 17 (LAKE ELMO
AVENUE) CORRIDOR IMPROVEMENT PROJECT – A COUNTY‐CITY JOINT PROJECT.
*PROJECT IS BEING IMPLEMENTED FOR CONSTRUCTION IN 2015.