HomeMy WebLinkAboutItem 11 - 5-39th St Street and Sewer-Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
39th Street North Street and Sanitary Sewer Schedule
PROJECT NO. 2014.131
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
AUGUST 2014
March 18, 2014 Council Declares Adequacy of Petition and Orders Preparation of Feasibiilty Report.
April 15, 2014 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
April 29, 2014 Property owner meeting. Presentation of Report findings and recommendations.
May 6, 2014 Public Improvement Hearing. Council orders Preparation of plans and specifications.
July 1, 2014 Council approves Plans and Specifications; Orders Advertisement for Bids.
July 31, 2014 Receive Contractor Bids.
August 19, 2014 Council accepts bids and awards Contract.
September 2, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
October 31, 2014 Substantial completion (estimated 8 weeks).
Summer, 2015 Final Completion.