HomeMy WebLinkAboutItem 6 - Well No 4 Connecting WM - CCO 2 AGENDA ITEM MAYOR & COUNCIL COMMUNICATION -- page 1 -- DATE: December 2, 2014 CONSENT ITEM # 6 AGENDA ITEM: Well No. 4 Connecting Watermain Improvements –Compensating Change Order No. 2 SUBMITTED BY: Chad Isakson, Project Engineer THROUGH: Dean A. Zuleger, City Administrator REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director Mike Bouthilet, Public Works SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda): - Questions from Council to Staff ............................................. Mayor Facilitates - Public Input, if Appropriate………………………………….Mayor Facilitates - Call for Motion ............................................................... Mayor & City Council - Discussion ....................................................................... Mayor & City Council - Action on Motion .................................................................... Mayor Facilitates POLICY RECOMMENDER: Engineering FISCAL IMPACT: $4,537.47. This change order reconciles the estimated and actual quantities installed on the project and increases the contract amount by $4,537.47. With this change order and previous change orders on the project the final contract amount is $448,422.01, or 1.3% over the original construction contract award. The total project costs remain within the original project budget as authorized on March 4, 2014. SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to consider approving, as part of the consent agenda, Compensating Change Order No. 2 for the Well No. 4 Connecting Watermain Improvements to reconcile the estimated and actual quantities installed on the project. If removed from the consent agenda, the recommended motion for the action is as follows: City Council Meeting [Consent Agenda Item 6] December 2, 2014 -- page 2 -- “Move to approve Compensating Change Order No. 2 for the Well No. 4 Connecting Watermain Improvements thereby increasing the final contract amount by $4,537.47.” LEGISLATIVE HISTORY/BACKGROUND INFORMATION: Northdale Construction Company was awarded a construction contract on March 4, 2014 to construct the Well No. 4 Connecting Watermain Improvements. The contractor has completed the work in accordance with the contract and with approval of this change order the contract amount will be adjusted to reflect quantities actually installed as a part of the project. Added project costs relate primarily to additional quantities of service pipe and fittings needed to locate each service stub in the appropriate location for the property. The overall increase in the contract amount for this change order is $4,537.47 as detailed on the attached itemization. The final contract amount is $448,422.01, or 1.3% over the original construction contract award. The total project costs remain within the original project budget authorized on March 4, 2014. RECOMMENDATION: Staff is recommending that the City Council consider, as part of the Consent Agenda, approving Compensating Change Order No. 2 for the Well No. 4 Connecting Watermain Improvements thereby increasing the final contract amount by $4,537.47. If removed from the consent agenda, the recommended motion for this action is as follows: “Move to approve Compensating Change Order No. 2 for the Well No. 4 Connecting Watermain Improvements thereby increasing the final contract amount by $4,537.47.” ATTACHMENT(S): 1. Compensating Change Order No. 2