Loading...
HomeMy WebLinkAboutItem 12 - 6-Village East Trunk Sanitary Sewer-Project SchedulePROJECT SCHEDULE  CITY OF LAKE ELMO    VILLAGE EAST TRUNK SANITARY SEWER IMPROVEMENTS  PROJECT NO. 2014.131  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.  651.300.4261 Jack Griffin, P.E.               651.300.4264  Ryan Stempski, P.E. 651.300.4267  Chad Isakson, P.E. 651.300.4283  JULY 2014                June 17, 2014 Council Orders Preparation of Feasibiilty Report.   Presentation of Feasibility Report. Council accepts Report and Calls Hearing.  Council approves Plans and Specifications; Orders Advertisement for Bids.  (project is added to the 39th Street: Street and Sanitary Sewer Improvements as an add alternate bid).    July 10, 2014 Receive Contractor Bids     August 5, 2014 Public Improvement Hearing. Council Orders the Improvement, accepts bids and  awards Contract.    Augut 12, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.    November 28, 2014 Substantial completion (estimated 15 weeks).    June 5, 2015 Final Completion.