HomeMy WebLinkAboutItem 12 - 6-Village East Trunk Sanitary Sewer-Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
VILLAGE EAST TRUNK SANITARY SEWER IMPROVEMENTS
PROJECT NO. 2014.131
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
JULY 2014
June 17, 2014 Council Orders Preparation of Feasibiilty Report.
Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
Council approves Plans and Specifications; Orders Advertisement for Bids.
(project is added to the 39th Street: Street and Sanitary Sewer Improvements as an add alternate bid).
July 10, 2014 Receive Contractor Bids
August 5, 2014 Public Improvement Hearing. Council Orders the Improvement, accepts bids and
awards Contract.
Augut 12, 2014 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
November 28, 2014 Substantial completion (estimated 15 weeks).
June 5, 2015 Final Completion.