HomeMy WebLinkAboutItem 13 - 2015 Street Improvements-Preliminary Project Schedule_REVISEDPRELIMINARY PROJECT SCHEDULE CITY OF LAKE ELMO 2015 STREET, DRAINAGE & WATERMAIN PROJECT NO. 2014.136 FOCUS ENGINEERING, inc. Cara Geheren, P.E. 651.300.4261 Jack Griffin, P.E. 651.300.4264 Ryan Stempski, P.E. 651.300.4267 Chad Isakson, P.E. 651.300.4283 SEPTEMBER 2014 July 1, 2014 Council authorizes Feasibility Report. September 2, 2014 Presentation of Feasibility Report. Council accepts Report and Calls Hearing. October 7, 2014 October 7, 2014 Public Improvement Hearing. Council orders Preparation of plans and specifications. November 5, 2014 February 17, 2015 Council approves Plans and Specifications; Orders Advertisement for Bids. March 24, 2015 Receive Contractor Bids. April 7, 2015 Council accepts bids and awards Contract. May 1, 2015 Conduct Pre-construction Meeting and Issue Notice to Proceed. August 28, 2015 Substantial completion. October 16, 2015 Final completion.