HomeMy WebLinkAboutItem 9 - Change Order No 1CHANGE ORDER NO. 1
LAKE ELMO AVE TRUNK WATERMAIN IMP.
CITY OF LAKE ELMO, MINNESOTA
PROJECT NO. 2013.133
QUANTITY UNIT PRICE AMOUNT
CO1‐1 LS 1.0 $3,810.00 $3,810.00
CO1‐2 LS 1.0 ‐$1,130.46 ‐$1,130.46
CO1‐3 EA ‐1.0 $1,657.77 ‐$1,657.77
CO1‐4 EA ‐2.0 $322.24 ‐$644.48
CO1‐5 EA ‐2.0 $3,489.56 ‐$6,979.12
CO1‐6 EA 1.0 $852.25 $852.25
CO1‐7 EA 16.0 $200.00 $3,200.00
CO1‐8 EA 18.0 $832.08 $14,977.44
TOTALS ‐ CHANGE ORDER NO. 1 $12,427.86
DESCRIPTION / JUSTIFICATIONITEM DESCRIPTION OF PAY ITEM UNIT
CHANGE ORDER
This change order is being processed at the request of the City for
improvements completed with the project. The County required
special traffic control signs that were necessary to improve safety
along their road corridor. The signs were not included in the original
scope of improvements. This change order also accounts for the
elimination of a future connection point 10th Street and removes
costs associated with restoration, valves, and fittings needed for the
work from the Contract. Finally the original contract did not include
pipe fittings required to complete the work. This change order adds
these payable items into the scope of the work.
TRAFFIC CONTROL ‐ TEMPORARY SIGNAGE
RESTORATION ‐ ELIMINATE CROSS AT 10TH STREET
FOSTOR ADAPTORS
16‐INCH SLEEVE
18‐INCH HYDRANT EXTENSION
REMOVE 16"X12" CROSS
REMOVE 12" PLUG
REMOVE 16" BUTTERFLY VALVE & BOX