HomeMy WebLinkAboutItem 8 - 4-Eagle Point Blvd Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
EAGLE POINT BLVD STREET AND SANITARY
SEWER IMPROVEMENTS
PROJECT NO. 2015.120
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
FEBRUARY 2015
January 20, 2015 Council authorizes Feasibility Report.
March 3, 2015 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
March, 2015 Property owner meeting. Presentation of Report findings and recommendations.
April 7, 2015 Public Improvement Hearing. Council orders Preparation of plans and specifications.
June 2, 2015 Council approves Plans and Specifications; Orders Advertisement for Bids.
June 30, 2015 Receive Contractor Bids.
July 7, 2015 Council accepts bids and awards Contract.
July 28, 2015 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
October 23, 2015 Substantial completion.
November 27, 2015 Final completion.