Loading...
HomeMy WebLinkAboutItem 18 - 4-Project SchedulePROJECT SCHEDULE OLD VILLAGE PHASE 1: STREET AND UTILITY IMPROVEMENTS FOCUS ENGINEERING, inc. Cara Geheren, P.E. 651.300.4261 Jack Griffin, P.E. 651.300.4264 Ryan Stempski, P.E. 651.300.4267 Chad Isakson, P.E. 651.300.4283 MAY, 2015 FEBRUARY 5, 2015 Council approves Municipal Consent. County proceeds with Final Design. FEBRUARY 24, 2015 Council authorizes the preparation of a Feasibility Report. MAY 1, 2015 County posts advertisement for bid. MAY 19, 2015 Council accepts Report; and adopts project assessment policy. Calls Public Improvement Hearing. Submit Notice of Public Hearing for Publication. MAY 27, 2015 Notice of Public Hearing Published (2nd Notice on June 3rd). JUNE 2, 2015 Accept Contractor Bids. Finalize Cooperative Agreement. JUNE 16, 2015 County Board Meeting. County accepts bids and awards Contract contingent up City award. JUNE 16, 2015 Public Improvement Hearing. Council approves “Concurrence” to award contract. Council Orders the Improvement for the 2015 IMPROVEMENTS (Requires 4/5th vote). OCTOBER 15, 2015 Substantial Completion. JUNE 15, 2016 Final Completion.