HomeMy WebLinkAboutItem 9 - 39th St Imp - Pay Request No 4 AGENDA ITEM
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 19, 2015 CONSENT ITEM # 9 AGENDA ITEM: 39th Street North: Street and Sanitary Sewer Improvements – Pay Request No. 4 SUBMITTED BY: Chad Isakson, Project Engineer
THROUGH: Dean A. Zuleger, City Administrator REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering FISCAL IMPACT:
None. Partial payment is proposed in accordance with the approved Contract and change orders for the project. SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider approving Pay Request No. 4 for the 39th Street North: Street and Sanitary Sewer Improvements project. If removed from the consent agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 4 to Geislinger & Sons Inc. in the amount of $526,866.15
for the 39th Street North: Street and Sanitary Sewer Improvements”.
City Council Meeting [Consent Agenda Item 9]
May 19, 2015
-- page 2 --
LEGISLATIVE HISTORY/BACKGROUND INFORMATION: Geislinger & Sons Inc., the Contractor for the project, has submitted Partial Pay Estimate No. 4 in the amount of $526,866.15. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of
the total work completed. The amount retained is $87,184.68.
RECOMMENDATION: Staff is recommending that the City Council consider approving, as part of the Consent Agenda, Pay Request No. 4 for the 39th Street North: Street and Sanitary Sewer Improvements project. If
removed from the consent agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 4 to Geislinger & Sons Inc. in the amount of $526,866.15, for the 39th Street North: Street and Sanitary Sewer Improvements”. ATTACHMENT(S): 1. Partial Pay Estimate No. 4