HomeMy WebLinkAboutItem 9 - Eagle Point Blvd Project Schedule May 2015PROJECT SCHEDULE
CITY OF LAKE ELMO
EAGLE POINT BLVD STREET AND
UTILITY IMPROVEMENTS
PROJECT NO. 2015.120
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
MAY 2015
January 20, 2015 Council authorizes Feasibility Report.
February 19, 2015 Property owner meeting. Present scope of impovements and discuss alternative
assessment methodologies.
March 3, 2015 Presentation of Feasibility Report. Council accepts Report and Calls Hearing.
April 7, 2015 Public Improvement Hearing. Council orders Preparation of plans and specifications.
June 2, 2015 Council approves Plans and Specifications; Orders Advertisement for Bids.
June 30, 2015 Receive Contractor Bids.
July 7, 2015 Council accepts bids and awards Contract.
July 28, 2015 Conduct Pre‐construction Meeting and Issue Notice to Proceed.
October 16, 2015 Substantial completion.
June 15, 2016 Final completion.