HomeMy WebLinkAbout2016 Street Improvements-Preliminary Project Schedule (2)PRELIMINARY PROJECT SCHEDULE CITY OF LAKE ELMO 2016 STREET IMPROVEMENTS PROJECT NO. 2015.XXX FOCUS ENGINEERING, inc. Cara Geheren, P.E. 651.300.4261 Jack Griffin, P.E. 651.300.4264 Ryan Stempski, P.E. 651.300.4267 Chad Isakson, P.E. 651.300.4283 AUGUST 2015 August 4, 2015 Council authorizes Feasibility Report. October 6, 2015 Presentation of Feasibility Report. Council accepts Report and calls Hearing. November 3, 2015 Public Improvement Hearing. Council orders preparation of Plans and Specifications. February 16, 2016 Council approves Plans and Specifications and orders Advertisement for Bids. March 17, 2016 Receive Contractor Bids. April 5, 2016 Council accepts Bids and awards Contract. May 2, 2016 Conduct Pre-Construction Meeting and issue Notice to Proceed. August 12, 2016 Substantial Completion. September 30, 2016 Final Completion.