HomeMy WebLinkAbout5-2016 Street Improvements-Preliminary Project SchedulePRELIMINARY PROJECT SCHEDULE  CITY OF LAKE ELMO    2016 STREET, DRAINAGE AND UTILITY IMPROVEMENTS  PROJECT NO. 2015.129  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.  651.300.4261 Jack Griffin, P.E.               651.300.4264  Ryan Stempski, P.E. 651.300.4267  Chad Isakson, P.E. 651.300.4283  AUGUST 2015                August 4, 2015 Council authorizes Feasibility Report.    October 6, 2015 Presentation of Feasibility Report. Council accepts Report and calls Hearing.    November 3, 2015 Public Improvement Hearing. Council orders preparation of Plans and Specifications.    February 16, 2016 Council approves Plans and Specifications and orders Advertisement for Bids.    March 17, 2016 Receive Contractor Bids.    April 5, 2016  Council accepts Bids and awards Contract.    May 2, 2016  Conduct Pre‐Construction Meeting and issue Notice to Proceed.    August 12, 2016 Substantial Completion.    September 30, 2016 Final Completion.