Loading...
HomeMy WebLinkAbout#4 Test Well No. 4 - Approve Quote AGENDA ITEM MAYOR & COUNCIL COMMUNICATION -- page 1 -- DATE: October 20, 2015 CONSENT ITEM # 4 AGENDA ITEM: Test Well No. 4 – Approve Quote to Seal and Abandon Test Well SUBMITTED BY: Chad Isakson, Project Engineer THROUGH: Clark Schroeder, Interim City Administrator REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director Mike Bouthilet, Public Works SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda): - Questions from Council to Staff ............................................. Mayor Facilitates - Public Input, if Appropriate………………………………….Mayor Facilitates - Call for Motion ............................................................... Mayor & City Council - Discussion ....................................................................... Mayor & City Council - Action on Motion .................................................................... Mayor Facilitates POLICY RECOMMENDER: Engineering. FISCAL IMPACT: $2,515.00. The estimated amount of $2,515 to be paid from the Water Enterprise Fund. SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to consider approving a contract with Kimmes-Bauer Well Drilling, Inc. to seal Test Well No. 4. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve the quote provided by Kimmes-Bauer Well Drilling, Inc. to permanently seal Test Well No. 4 for $2,515.00”. City Council Meeting [Consent Agenda Item 4] October 20, 2015 -- page 2 -- LEGISLATIVE HISTORY/BACKGROUND INFORMATION: Test Well No. 4 was constructed in 2012 as part of the site planning and acquisition process for the City’s municipal Well No. 4. A smaller test well was constructed to verify the aquifer water quality and capacity in the location of Well No. 4 prior to purchasing the site and proceeding with the construction of the much more expensive well construction. With Well No. 4 completed and in service the test well is no longer in use and must be sealed and abandoned per the Minnesota Department of Health Well Code. Staff recently obtained a quote from Kimmes-Bauer Well Drilling, Inc. in the estimated amount of $2,515.00 to seal Test Well No. 4. Kimmes Bauer Well Drilling is a licensed well contractor and was the contractor that constructed the test well in 2012. The quote is based on the unit price per cubic yard of grout required to successfully seal the well. Payment will be made for the actual quantities of grout installed. RECOMMENDATION: Staff is recommending that the City Council consider approving, as part of the Consent Agenda, a contract with Kimmes-Bauer Well Drilling, Inc. to seal Test Well No. 4. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve the quote provided by Kimmes-Bauer Well Drilling, Inc. to permanently seal Test Well No. 4 for $2,515.00”. ATTACHMENT(S): 1. Kimmes-Bauer Well Drilling, Inc. Quote.