DATE: October 20, 2015
CONSENT
ITEM # 5
AGENDA ITEM: Eagle Point Blvd Street and Utility Improvements – Pay Request No. 2
SUBMITTED BY: Ryan Stempski, Project Engineer
THROUGH: Clark Schroeder, Interim City Administrator
REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT:
None. Partial payment is proposed in accordance with the Contract for the project. Payment
remains within the authorized scope and budget.
SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to consider approving Pay Request No. 2 for the
Eagle Point Boulevard Street and Utility Improvements project. If removed from the consent
agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 2 to Miller Excavating, Inc. in the amount of $268,768.06 for the Eagle Point Boulevard Street and Utility Improvements”.
City Council Meeting [Consent Agenda Item 5]
October 20, 2015
-- page 2 --
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
Miller Excavating, Inc., the Contractor for the project, has submitted Partial Pay Estimate No. 2
in the amount of $268,768.06. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of
the total work completed. The amount retained is $19,544.78.
RECOMMENDATION:
Staff is recommending that the City Council consider approving, as part of the Consent Agenda, Pay Request No. 2 for the Eagle Point Boulevard Street and Utility Improvements project. If
removed from the consent agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 2 to Miller Excavating, Inc. in the amount of $268,768.06 for the Eagle Point Boulevard Street and Utility Improvements”. ATTACHMENT(S):
1. Partial Pay Estimate No. 2
PROJECT PAY FORM
PARTIAL PAY ESTIMATE NO.
PERIOD OF ESTIMATE
TO
PROJECT OWNER: CONTRACTOR:
1. Original Contract Amount
2. Net Change Order Sum
3. Revised Contract (1+2)
4. *Work Completed
5. *Stored Materials
6. Subtotal (4+5)
7. Retainage*
8. Previous Payments
9. Amount Due (6‐7‐8)
*Detailed Breakdown Attached
START DATE:ON SCHEDULE
SUBSTANTIAL COMPLETION:
FINAL COMPLETION:X
ENGINEER'S CERTIFICATION: FOCUS Engineering, inc.
DATE
CONTRACTOR'S CERTIFICATION: CONTRACTOR
DATE
APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA
DATE DATE
No.Approval
Date
Amount $1,249,494.09
Additions Deductions ‐$28,500.00
$390,895.65
1 8/4/2015 $28,500.00 $1,220,994.09
$390,895.65
$0.00
$102,582.81
$19,544.785.0%
CONTRACT TIME
TOTALS $0.00 $28,500.00 $268,768.06
NET CHANGE ($28,500.00)
CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY
2
9/30/20159/1/2015FROM
EAGLE POINT BLVD STREET & UTILITY IMPROVEMENTS
PROJECT NO. 2015.120
CITY OF LAKE ELMO
3800 LAVERNE AVENUE NORTH
LAKE ELMO, MN 55042
ATTN: JACK GRIFFIN, CITY ENGINEER
MILLER EXCAVATING, INC.
3636 STAGECOACH TRAIL NORTH
STILLWATER, MN 55082
ATTN: STEVE ST. CLAIRE, PROJECT MANAGER
7/31/2015
6/15/2016
REVISED DAYS
REMAINING
320
0
259
10/15/2015
ORIGINAL DAYS
BY
BY
YES
NO
The undersigned Contractor certifies that to the best of their
knowledge, information and belief the work covered by this payment
estimate has been completed in accordance with the contract
documents, that all amounts have been paid by the contractor for
work for which previous payment estimates was issued and payments
received from the owner, and that current payment shown herein is
now due.
The undersigned certifies that the work has been reviewed and to the
best of their knowledge and belief, the quantities shown in this
estimate are correct and the work has been performed in accordance
with the contract documents.
ENGINEER
BY
FOCUS Engineering, inc.PROJECT PAYMENT FORM
PARTIAL PAY ESTIMATE NO. 2
EAGLE POINT BLVD STREET & UTILITY IMPROVEMENTS
CITY OF LAKE ELMO, MINNESOTA
PROJECT NO. 2015.120
QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
1 LS 1 $29,900.00 $29,900.00 0.00 $0.00 0.50 $14,950.00
2 LS 1 $6,850.00 $6,850.00 0.00 $0.00 0.50 $3,425.00
3 LF 3,100 $2.00 $6,200.00 0.00 $0.00 1,550.00 $3,100.00
4 EA 17 $200.00 $3,400.00 0.00 $0.00 8.00 $1,600.00
5 EA 2 $1,000.00 $2,000.00 1.00 $1,000.00 1.00 $1,000.00
6 HR 20 $100.00 $2,000.00 4.00 $400.00 4.00 $400.00
7 SY 5,145 $10.50 $54,022.50 0.00 $0.00 0.00 $0.00
8 SY 2,575 $1.15 $2,961.25 0.00 $0.00 0.00 $0.00
$107,333.75 $1,400.00 $24,475.00
9 EA 2 $2,800.00 $5,600.00 0.00 $0.00 2 $5,600.00
10 LF 764 $33.60 $25,670.40 0.00 $0.00 764 $25,670.40
11 EA 3 $3,400.00 $10,200.00 0.00 $0.00 3 $10,200.00
12 LF 12 $240.00 $2,880.00 0.00 $0.00 12 $2,880.00
13 CY 42 $52.00 $2,184.00 0.00 $0.00 0 $0.00
14 CY 42 $68.00 $2,856.00 0.00 $0.00 0 $0.00
15 LF 764 $3.50 $2,674.00 0.00 $0.00 0 $0.00
$52,064.40 $0.00 $44,350.40
16 EA 1 $2,650.00 $2,650.00 1.00 $2,650.00 1 $2,650.00
17 EA 1 $1,990.00 $1,990.00 0.00 $0.00 0 $0.00
18 EA 2 $4,770.00 $9,540.00 2.00 $9,540.00 2 $9,540.00
19 EA 1 $4,990.00 $4,990.00 1.00 $4,990.00 1 $4,990.00
20 EA 1 $4,560.00 $4,560.00 0.00 $0.00 0 $0.00
21 LF 209 $108.00 $22,572.00 31.00 $3,348.00 31 $3,348.00
22 EA 2 $985.00 $1,970.00 1.00 $985.00 1 $985.00
23 EA 1 $1,560.00 $1,560.00 0.00 $0.00 0 $0.00
24 EA 1 $2,190.00 $2,190.00 1.00 $2,190.00 1 $2,190.00
25 EA 2 $1,380.00 $2,760.00 2.00 $2,760.00 2 $2,760.00
26 EA 1 $1,270.00 $1,270.00 0.00 $0.00 0 $0.00
27 SF 32 $10.00 $320.00 32.00 $320.00 32 $320.00
$56,372.00 $26,783.00 $26,783.00
28 EA 2 $400.00 $800.00 2.00 $800.00 2 $800.00
29 LF 65 $15.00
$975.00 65.00 $975.00 65.00 $975.00
30 EA 2 $890.00
$1,780.00 1.00 $890.00 1.00 $890.00
31 LF 117 $33.00 $3,861.00 39.00 $1,287.00 39.00 $1,287.00
32 LF 971 $34.50 $33,499.50 584.00 $20,148.00 584.00 $20,148.00
33 EA 3 $1,695.00
$5,085.00 1.00 $1,695.00 1.00 $1,695.00
34 EA 7 $2,665.00 $18,655.00 5.00 $13,325.00 5.00 $13,325.00
35 EA 2 $475.00 $950.00 0.00 $0.00 0.00 $0.00
36 SF 27 $36.00
$972.00 0.00 $0.00 0.00 $0.00
$66,577.50 $39,120.00 $39,120.00
37 EA 11.00 $60.00 $660.00 0.00 $0.00 0 $0.00
38 EA 1.00 $60.00 $60.00 0.00 $0.00 0 $0.00
39 LF 553.00 $3.00 $1,659.00 0.00 $0.00 0 $0.00
40 SY 266.00 $5.00 $1,330.00 0.00 $0.00 0 $0.00
41 SY 380.00 $6.00 $2,280.00 0.00 $0.00 0 $0.00
42 LF 7,036.00 $2.00 $14,072.00 1,520.00 $3,040.00 3,570 $7,140.00
43 LS 1.00 $214,450.00 $214,450.00 0.31 $66,479.50 0.48 $102,936.00
44 CY 12,000.00 $11.95 $143,400.00 5,760.00 $68,832.00 5,760 $68,832.00
45 SY 2,700.00 $9.00 $24,300.00 350.00 $3,150.00 350 $3,150.00
46 RS 34.00 $150.00 $5,100.00 17.00 $2,550.00 17 $2,550.00
47 TN 9,850.00 $12.65 $124,602.50 3,625.00 $45,856.25 3,625 $45,856.25
48 TN 9.00 $80.00 $720.00 0.00 $0.00 0 $0.00
49 TN 1,825.00 $62.00 $113,150.00 0.00 $0.00 0 $0.00
16"X6" REDUCER MJ DUCTILE IRON COMPACT FITTING
4" POLYSTYRENE INSULATION
16" DIP CL. 52 WATERMAIN
SUBTOTAL ‐ DIVISION 2
DIVISION 3 ‐ WATERMAIN
16" BUTTERFLY VALVE & BOX
16"X45° BEND MJ DUCTILE IRON COMPACT FITTING
16"x16" TEE MJ DUCTILE IRON COMPACT FITTING
CONNECT TO EXISITING WATERMAIN
12" GATE VALVE
REMOVE AND REPLACE VALVE BOX
HYDRANT
TEMPORARY ROCK CONSTRUCTION ENTRANCE
STREET SWEEPING
6" TOPSOIL AND SOD
HYDRAULIC MULCH (TEMPORARY)
16"X12" REDUCER MJ DUCTILE IRON COMPACT FITTING
SANITARY SEWER PIPE ‐ 8"
SANITARY SEWER MANHOLE ‐ TYPE 301
SUBTOTAL ‐ DIVISION 1
EXCESS MANHOLE DEPTH
REMOVAL OF UNSTABLE FOUNDATION MATERIAL
DIVISION 2 ‐ SANITARY SEWER
CONNECT TO EXISTING SANITARY SEWER MANHOLE
STABILIZING AGGREGATE BORROW
TELEVISING
6" GATE VALVE & BOX
DIVISION 1 ‐ GENERAL
MOBILIZATION
TRAFFIC CONTROL
SILT FENCE
INLET PROTECTION
ITEM DESCRIPTION OF PAY ITEM UNIT
CONTRACT AMOUNT THIS PERIOD TOTAL TO DATE
SUBTOTAL ‐ DIVISION 3
DIVISION 4 ‐ STORM SEWER
REMOVE EXISTING STORM SEWER STRUCTURE
CATCH BASIN/MANHOLE ‐ TYPE 406
RESET EXISTING CATCH BASIN CASTING
REPAIR EXISTING CATCH BASIN CONCRETE
REMOVE EXISTING STORM SEWER (ALL TYPES AND SIZES)
CONNECT TO EXISTING STORM SEWER STRUCTURE
STORM SEWER PIPE ‐ 12" RCP
STORM SEWER PIPE ‐ 15" RCP
CATCH BASIN ‐ TYPE 404
AGGREGATE TRAIL RESTORATION
BITUMINOUS NON‐WEAR COURSE
CLASS 6 AGGREGATE BASE
SUBTOTAL ‐ DIVISION 4
REMOVE AND DISPOSE OF EXISTING CONCRETE PAVEMENT (DRIVEWAY)
REMOVE AND DISPOSE OF EXISTING CONCRETE CURB
COMMON EXCAVATION
SELECT GRANULAR BORROW (CV) (P)
SUBGRADE CORRECTION
SUBGRADE PREPARATION
DIVISION 5 ‐ STREETS
SALVAGE POST AND SIGN
REMOVE POST AND SIGN
SAWCUT BITUMINOUS OR CONCRETE
REMOVE AND DISPOSE OF EXISTING BITUMINOUS PAVEMENT (DRIVEWAY)
QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
ITEM DESCRIPTION OF PAY ITEM UNIT
CONTRACT AMOUNT THIS PERIOD TOTAL TO DATE
50 TN 1,825.00 $62.00 $113,150.00 0.00 $0.00 0 $0.00
51 GA 842.00 $3.00 $2,526.00 0.00 $0.00 0 $0.00
52 LF 6,596.00 $12.00 $79,152.00 0.00 $0.00 0 $0.00
53 EA 4.00 $2,970.00 $11,880.00 0.00 $0.00 0 $0.00
54 SY 40.00 $55.00 $2,200.00 0.00 $0.00 0 $0.00
55 SY 295.00 $27.00 $7,965.00 0.00 $0.00 0 $0.00
56 LF 6,660.00 $9.00 $59,940.00 2,297.00 $20,673.00 2,297 $20,673.00
57 EA 50.00 $150.00 $7,500.00 16.00 $2,400.00 16 $2,400.00
58 EA 8.00 $400.00 $3,200.00 4.00 $1,600.00 4 $1,600.00
59 EA 6.00 $515.00 $3,090.00 2.00 $1,030.00 2 $1,030.00
60 EA 4.00 $600.00 $2,400.00 0.00 $0.00 0 $0.00
61 EA 18.00 $350.00 $6,300.00 0.00 $0.00 0 $0.00
62 SF 15.00 $45.00 $675.00 0.00 $0.00 0 $0.00
63 EA 2.00 $200.00 $400.00 0.00 $0.00 0 $0.00
64 LF 7,116.00 $0.53 $3,771.48 0.00 $0.00 0 $0.00
65 LF 1,524.00 $0.53 $807.72 0.00 $0.00 0 $0.00
66 LF 2,558.00 $0.53 $1,355.74 0.00 $0.00 0 $0.00
67 EA 2.00 $1,200.00 $2,400.00 0.00 $0.00 0 $0.00
68 LS 1.00 $4,500.00 $4,500.00 0.00 $0.00 0 $0.00
69 EA 10.00 $815.00 $8,150.00 0.00 $0.00 0 $0.00
$967,146.44 $215,610.75 $256,167.25
TOTALS ‐ BASE CONTRACT $1,249,494.09 $282,913.75 $390,895.65
CHANGE ORDER NO. 1
CO1‐1 LF (2,850.00)$9.00 ‐$25,650.00 0.00 $0.00 0 $0.00
CO1‐2 EA (19.00)$150.00 ‐$2,850.00 0.00 $0.00 0 $0.00
TOTALS ‐ CHANGE ORDER NO. 1 ‐$28,500.00 $0.00 $0.00
TOTALS ‐ REVISED CONTRACT $1,220,994.09 $282,913.75 $390,895.65
PERFORATED PVC EDGE DRAIN
DRAINTILE CLEANOUT
PERFORATED PVC EDGE DRAIN
DRAINTILE CLEANOUT
DRAINTILE CONNECTION INTO CATCH BASIN
PRECAST CONCRETE HEADWALL FOR DRAINTILE
BITUMINOUS MATERIAL FOR TACK COAT
CONCRETE CURB AND GUTTER
DRIVEWAY VALLEY GUTTER
6" CONCRETE DRIVEWAY PAVEMENT
BITUMINOUS DRIVEWAY PAVEMENT
BITUMINOUS WEAR COURSE
PAVEMENT MARKINGS ‐ POLY PREFORMED
SUBTOTAL ‐ DIVISION 5
ADJUST MANHOLE CASTING
ADJUST GATE VALVE BOX
FURNISH SIGN PANEL
INSTALL SIGN PANELS
4" SOLID LINE WHITE EPOXY
4" SOLID LINE YELLOW EPOXY
4" BROKEN LINE YELLOW EPOXY
STOP BAR ‐ POLY PREFORMED
TEMPORARY PAVEMENT STRIPING