Loading...
HomeMy WebLinkAbout#13 CC 11 4 15 HammesMAYOR AND COUNCIL COMMUNICATION DATE: 11/4/15 CONSENT RESOLUTION # ITEM: #13 AGENDA ITEM: Hammes Plat Extension SUBMITTED BY: Clark Schroeder, Interim City Administrator THROUGH: Clark Schroeder, Interim City Administrator REVIEWED BY: Clark Schroeder, Interim City Administrator SUGGESTED ORDER OF BUSINESS: - Introduction of Item .................................................... Interim City Administrator - Report/Presentation ..................................................... Interim City Administrator - Questions from Council to Staff ................................................ Mayor Facilitates - Public Input, if Appropriate ....................................................... Mayor Facilitates - Call for Motion .................................................................. Mayor & City Council - Discussion .......................................................................... Mayor & City Council - Action on Motion ....................................................................... Mayor Facilitates FINANCIAL IMPACT: Delayed/Lost revenue related to 163 units; General fund impact of approximately $100k per year, Utility fund access and connection fees of $1.2M, Utility fund usage revenue of $150k per year and parkland dedication fees of $107k. Risk related to recovery of utility fund special assessments of $580k. BACKGROUND AND STAFF REPORT: On October 7, 2014, the City Council approved the Hammes Estates final plat. At that same meeting, a draft developer agreement was proposed and approved as well. However, the developer agreement was never executed due to various issues. The issues which previously prevented the execution of the developer agreement and the plat from being recorded have since been mitigated and they would now like to move forward. However, since plat approval is good for one year, an extension is being sought from the City Council to allow them to do so. Opinion from Mr. Snyder. Setting aside the financial inquiries, my recommendation would be to grant an extension here-as requested to October. A decision on this subject would be evaluated by the arbitrary and capricious standard-basically an inquiry into the reasonableness of the council’s decisionmaking. Since there have been no intervening area-wide zoning changes, no big land-use changes, since the plat is not proposed to be materially modified and since the extension is, practically speaking, that of a couple of months, I think an extension would customarily be granted and that a reviewer would conclude that it should be granted. I do not recommend an extension longer than that at this time-any subsequent extension should be sought from and considered by Council at the end of any extension given into next year. Turning to financial inquiries then, I would defer to Clark and Cathy. As for the specific question, No, the petition and waiver agreement does not require the city to allow plats or plat extensions. The financial aspects of this should, however, be a central area of the council’s understanding of the implications of an approval or denial of the extension request. Needless to say, if the plat is allowed to expire and no extension is granted then receipt of infrastructure funding from this development and any that might rely on it for their own utilities will certainly be delayed, likely indefinitely and likely for a long time. S.W.O.T Analysis: Strengths: Recovery of infrastructure investment via access and connection fees, ability to collect of special assessments assessed as part of the section 34 project and generation of on-going utility usage revenue to strengthen the utility fund balances. Weaknesses: None identified Opportunities: Ability to move forward with a previously approved plat. Threats: Potential for prior developer to place lien on property preventing build out activity. . RECOMMENDATIONS: “Motion to extend the final plat approval and development contract for two years through Oct 7th 2016 with the condition that all special assessments be paid at plat, that the developer’s agreement be signed within 60 days of November 4th 2015, that the agreement and resolution be reassigned to Hammes Estates from Hammes West, LLC.” ATTACHMENTS: 1. Request from Eleanor Hammes for an extension 2. Developer Agreement 3. City council packet 10-7-14 (reserved for recording information) DEVELOPMENT CONTRACT (Public sewer and water) Hammes Estates 1st Addition AGREEMENT dated_________________, 2015, by and between the CITY OF LAKE ELMO a Minnesota municipal corporation (“City”), and The Ryland Group, Inc. a Maryland Corporation (the “Developer”). 1. REQUEST FOR PLAT APPROVAL. The Developer has asked the City to approve t he plat for Hammes Estates 1st Addition (referred to in this this Contract as the "plat"). The land is situated in the County of Washington, State of Minnesota, and is legally described as: That part of the South Half of the Northeast Quarter of Section 34, Township 29 North, Range 21 West, Washington County, Minnesota, EXCEPT the East 60.00 feet of the North 967 feet of said South Half of the Northeast Quarter thereof. AND EXCEPT Parcel 3 of Washington County Highway Right of Way Plat 49-19B, recorded September 18, 1985 as Document Number 492530. 2. CONDITIONS OF PLAT APPROVAL. The City hereby approves the plat on condition that the Developer enter into this Contract, furnish the security required by it, and record the plat with the County Recorder or Registrar of Titles within (180) days after the City Council approves the final plat. 1 3. RIGHT TO PROCEED. Unless separate written approval has been given by the City, within the plat or land to be platted, the Developer may not grade or otherwise disturb the earth, remove trees, construct sewer lines, water lines, streets, utilities, public or private improvements, or any buildings until all the following conditions have been satisfied: 1) this agreement has been fully executed by both parties and filed with the City Clerk, 2) the necessary security has been received by the City, 3) the plat has been recorded with the Washington County Recorder's Office, and 4) the City’s Community Development Director has issued a letter that all conditions have been satisfied, a preconstruction conference has been held, and that the Developer may proceed. 4. HOA DOCUMENTS. The required HOA documents shall be recorded with the Washington County Recorder’s Office within thirty (30) days of the plat being recorded with the County. 5. PHASED DEVELOPMENT. This plat is a phase of a multi-phased preliminary plat, the City may refuse to approve final plats of subsequent phases if the Developer has breached this Contract and the breach has not been remedied. Development of subsequent phases may not proceed until Development Contracts for such phases are approved by the City. Park charges and area charges for sewer and water referred to in this Contract are not being imposed on outlots, if any, in the plat that are designated in an approved preliminary plat for future subdivision into lots and blocks. Such charges will be calculated and imposed when the outlots are final platted into lots and blocks. 6. PRELIMINARY PLAT STATUS. The plat is a phase of a multi-phased preliminary plat, the preliminary plat approval for all phases not final platted shall lapse and be void unless final platted into lots and blocks, not outlots, within five (5) years after preliminary plat approval. 7. CHANGES IN OFFICIAL CONTROLS. For two (2) years from the date of this Contract, no amendments to the City's Comprehensive Plan or official controls shall apply to or affect the residential use, development density, lot size, lot layout or dedications of the approved final plat unless required by state or federal law or agreed to in writing by the City and the Developer. Thereafter, notwithstanding anything in this Contract to the contrary, to the full extent permitted by state law, the City may require compliance with any amendments to the City's Comprehensive Plan, official controls, platting or dedication 2 requirements enacted after the date of this Contract. 8. DEVELOPMENT PLANS. The plat shall be developed in accordance with the following plans and at the Developer’s sole expense. The plans shall not be attached to this Contract. If the plans vary from the written terms of this Contract, the written terms shall control. The plans are: Plan A – Final Plat Plan B – Final Grading, Drainage, and Erosion Control Plans Plan C – Final Sanitary Sewer, Water Main, Storm Sewer, and Street Plans Plan D – Final Landscape Plan 9. IMPROVEMENTS. The Developer shall install and pay for the following: A. Streets B. Sanitary Sewer C. Watermain D. Surface Water Facilities (pipe, ponds, rain gardens, etc.) E. Grading and Erosion Control F. Sidewalks/Trails G. Street Lighting H. Underground Utilities I. Street Signs and Traffic Control Signs J. Landscaping and Street Trees K. Tree Preservation and Reforestation L. Wetland Mitigation and Buffers M. Monuments Required by Minnesota Statutes The improvements shall be installed in accordance with the City subdivision ordinance and the City’s Engineering Design and Construction Standards Manual and pursuant to the direction of the City Engineer. The Developer shall submit plans and specifications which have been prepared by a competent registered professional engineer to the City for approval by the City Engineer. The Developer shall instruct its engineer to provide adequate field inspection personnel to assure an acceptable level of quality control to the extent that the Developer's engineer will be able to certify that the construction work meets the approved City standards as a condition of City acceptance. In addition, the City may, at the City's discretion and at the Developer's expense, have one or more City inspectors and a soil engineer inspect the work on 3 a full or part-time basis. The Developer's engineer shall provide for on-site project management. The Developer's engineer is responsible for design changes and contract administration between the Developer and the Developer's contractor. The Developer or his engineer shall schedule a pre-construction meeting at a mutually agreeable time at the City Hall with all parties concerned, including the City staff, to review the program for the construction work. All labor and work shall be done and performed in the best and most workmanlike manner and in strict conformance with the approved plans and specifications. No deviations from the approved plans and specifications will be permitted unless approved in writing by the City Engineer. The Developer agrees to furnish to the City a list of contractors being considered for retention by the Developer for the performance of the work required by the Contract. The Developer shall not do any work or furnish any materials not covered by the plans and specifications and special conditions of this Contract, for which reimbursement is expected from the City, unless such work is first ordered in writing by the City Engineer as provided in the specifications. 10. CITY ENGINEERING ADMINISTRATION AND CONSTRUCTION OBSERVATION. Prior to the commencement of any construction activity authorized under this agreement, the Developer shall submit an escrow for City Engineering Administration and Construction Observation in an amount provided under paragraph 36. Summary of Cash Requirements. Thereafter, the Developer shall reimburse the City each month, within 30 days of receiving an invoice, for all engineering administration and construction observation performed during the construction of the plat at normal City rates for such Services. If the Developer fails to pay the invoiced amount within such 30-day period, and such failure continues for an additional five (5) business days after written notice from the City of such failure, the City may draw upon the escrow and stop the work on site until said escrow has been replenished in its full amount. City engineering administration will include monitoring of construction progress and construction observation, consultation with Developer and his engineer on status or problems regarding the project, coordination for testing, final inspection and acceptance, project monitoring during the warranty period, and processing of requests for reduction in security. Construction observation may be performed by the City's in-house staff or consulting engineer. Construction observation shall include, at the discretion 4 of the city, part or full time inspection of proposed public utilities and street construction. Services will be billed on an hourly basis at normal City rates therefore. The direction and review provided through the inspection of the improvements should not be considered a substitute for the Developer required management of the development. Developer will cause the contractor(s) to furnish the City with a schedule of proposed operations at least five (5) days prior to the commencement of construction of each type of Improvement. City shall inspect all Developer Installed Improvements during and after construction for compliance with approved plans and specifications. Developer will notify the City Engineer at such times during construction as the City Engineer requires for inspection purposes. Such inspection is pursuant to the City’s governmental authority, and no agency or joint venture relationship between the City and Developer is thereby created. 11. CONTRACTORS/SUBCONTRACTORS. City Council members, City employees, and City Planning Commission members, and corporations, partnerships, and other entities in which such individuals have greater than a 25% ownership interest or in which they are an officer or director may not act as contractors or subcontractors for the public improvements identified in Paragraph 8 above. 12. PERMITS. The Developer shall obtain or require its contractors and subcontractors to obtain all necessary permits, including but not limited to: A. Right-of-Way Excavations and Obstructions: • City of Lake Elmo, Right-of-Way Utility Installation(s) • City of Lake Elmo, Right-of-Way Obstruction(s) • Washington County, Utility Installations(s) • Washington County, Street or Driveway Access(s) • Minnesota Department of Transportation, Utility Installation • Minnesota Department of Transportation, Right-of-Way Permit B. Watermain Extensions: • Minnesota Department of Health C. Sanitary Sewer Extensions: • Minnesota Pollution Control Agency • Metropolitan Council Environmental Services D. Stormwater Management: • Valley Branch Watershed District Permit E. Erosion, Sedimentation Control: • Minnesota Pollution Control Agency, General NPDES Stormwater Permit 5 • SW PPP (Stormwater Pollution Prevention Plan) F. Wetland Mitigation: • Board of Water and Soil Resources, W CA G. Construction Dewatering: • Minnesota Department of Natural Resources 13. TIME OF PERFORMANCE. The Developer shall install all required public improvements by October 31, 2015, with the exception of the final wear course of asphalt on streets. The Developer shall have the option of installing the wearing course of streets within one (1) year following initial commencement of work on the required basic improvements or installing it after the first course has weathered a winter season, consistent with warranty requirements, however final acceptance of the improvements will not be granted until all work is completed including the final wear course. The Developer may, however, request an extension of time from the City. If an extension is granted, it shall be conditioned upon updating the security posted by the Developer to reflect cost increases and amending this agreement to reflect the extended completion date. Final wear course placement outside of this time frame must have the written approval of the City Engineer. 14. LICENSE. The Developer hereby grants the City, its agents, employees, officers and contractors a license to enter the plat to perform all work and inspections deemed appropriate by the City in conjunction with plat development. 15. CONSTRUCTION ACCESS. Construction traffic access and egress for grading, public utility construction, and street construction is restricted to access the subdivision via the planned construction access off of Keats Avenue. No construction traffic is permitted on other adjacent local streets. 16. CONSTRUCTION SEQUENCE AND COMPLIANCE. The City will require the Developer to construct the improvements in a sequence which will allow progress and compliance points to be measured and evaluated. The Developer and/or their representatives are required to supervise and coordinate all construction activities for all improvements and must notify the City in writing stating 6 when the work is ready for the inspection at each of the measurable points defined in the following paragraphs 16., 17. and 18. For the purpose of this paragraph, Electronic message (email) shall be deemed an acceptable method of notification provided it is captioned “Notice pursuant to Development Agreement”. 17. EROSION CONTROL. Prior to initiating site grading, the erosion control plan, Plan B, shall be implemented by the Developer and inspected and approved by the City. Erosion control practices must comply with the approved plans and specifications for the plat, with all watershed district permits and with Minnesota Pollution Control Agency’s Best Management Practices. The City may impose additional erosion control requirements as deemed necessary. The parties recognize that time is of the essence in controlling erosion. If the Developer does not comply with the erosion control plan and schedule or supplementary instructions received from the City, the City may take such action as it deems appropriate to control erosion. The City will endeavor to notify the Developer in advance of any proposed action, but failure of the City to do so will not affect the Developer's and City's rights or obligations hereunder. If the Developer does not reimburse the City for any cost the City incurred for such work within ten (10) days, the City may draw down the security to pay any costs. No development, utility or street construction will be allowed and no building permits will be issued unless the plat is in full compliance with the approved erosion control plan. If building permits are issued prior to the acceptance of public improvements, the Developer assumes all responsibility for erosion control compliance throughout the plat and the City may take such action as allowed by this agreement against the Developer for any noncompliant issue as stated above. Erosion control plans for individual lots will be required in accordance with the City’s building permit requirements, or as required by the City or City Engineer. 18. GRADING PLAN. The plat shall be graded in accordance with the approved grading drainage and erosion control plan, Plan "B". The plan shall conform to Engineering Design and Construction Standards Manual. All grading shall be completed within the Subdivision prior to the preparation and submittal of the as-constructed grading plan. 7 Within thirty (30) days after completion of the grading, the Developer shall provide the City with a "record" grading plan certified by a registered land surveyor or engineer that all trails, ponds, swales, and ditches have been constructed on public easements or land owned by the City. The "record" plan shall contain site grades and field verified elevations of the following: a) cross sections of ponds; b) location and elevations along all swales, emergency overflows, wetlands, wetland mitigation areas if any, ditches, locations and dimensions of borrow areas/stockpiles; c) lot corner elevations and house pads; and d) top and bottom of retaining walls. The City will not issue any building permits until the approved certified record grading plan is on file with the City. 19. STREET AND UTILITY IMPROVEMENTS. All storm sewers, sanitary sewers, watermain, and streets shall be installed in accordance with the approved Plans and Specifications for Public Improvements, Plan "C". The plan shall conform to the City’s Engineering Design and Construction Standards Manual. Curb and gutter and the first lift of the bituminous streets, sidewalks, the boulevards graded, street signs installed, and all restoration work on the site shall be completed in accordance with the approved plans. Once the work is completed, the Developer or its representative shall submit a written request to the City asking for an inspection of the initial improvements. The City will then schedule a walk- through to create a punch list of outstanding items to be completed. Upon receipt of the written punch list provided by the City, the punch list items must be completed by the Developer and the City notified to re- inspect the improvements. The final bituminous wear course may be installed in accordance with paragraph 12. above. 20. STREET MAINTENANCE DURING CONSTRUCTION. The Developer shall be responsible for all street maintenance until the streets are accepted by the City in writing. W arning signs shall be placed when hazards develop in streets to prevent the public from traveling on same and to direct attention to detours. If and when streets become impassable, such streets shall be barricaded and closed. In the event residences are occupied prior to completing streets, the Developer shall maintain a smooth surface and provide proper surface drainage to insure that the streets are passable to traffic and emergency vehicles. The Developer shall be responsible for keeping streets within and without the 8 subdivision clean of dirt and debris that may spill, track, or wash onto the street from Developer’s operation. The Developer may request, in writing, that the City keep the streets open during the winter months by plowing snow from the streets prior to final acceptance of said streets. The City shall not be responsible for repairing the streets because of snow plowing operations. Providing snow plowing service does not constitute final acceptance of the streets by the City. The Developer shall contract for street cleaning within and immediately adjacent to the development. At a minimum, scraping and sweeping shall take place on a weekly basis. A copy of this contract shall be approved by the City before grading is started. The contract shall provide that the City may direct the contractor to clean the streets and the contractor will bill the Developer. 21. OWNERSHIP OF IMPROVEMENTS. Upon completion of the work and construction required by this Contract, the improvements lying within public easements shall become City property. Prior to acceptance of the improvements by the City, the Developer must furnish the City with a complete set of reproducible "record" plans, an electronic file of the "record" plans in accordance with the City’s Engineering Design and Construction Standards Manual together with the following affidavits: - Developer/Developer Engineer’s Certificate - Land Surveyor’s Certificate certifying that all construction has been completed in accordance with the terms of this Contract. All necessary forms will be furnished by the City. Upon receipt of “record plans” and affidavits, and upon review and verification by the City Engineer, the City Engineer will accept the completed public improvements. 22. PARK DEDICATION. The Developer shall pay a cash contribution of $ 10 7, 55 4 in satisfaction of the City's park dedication requirements. This charge is based on the park dedication requirement for all the areas to be platted within the Hammes Estates Preliminary Plat. No additional fees in lieu of land dedication will be charged for future developments within the preliminary plat area. The charge was calculated as follows: 2.1 acres (5.7 acres of park land provided subtracted from 7.8 acres of park land required) at $51,216 per acre per the submitted appraisal for the property. The Developer shall 9 receive a credit from the cash amount due for the actual costs of the North East Park Plan Improvements depicted in the Final Landscape Plans Dated September 22, 2014. These improvement shall include: 16- feet by 24-feet shelter, picnic table, bike rack, grill station, retaining wall, fishing pier, canoe rack, concrete hardsurface, woodland seed mix restoration, landscaping, and parking lot improvements. The Developer shall deposit $107,554 with the City at time of final plat to be held by the City in escrow until such time as park improvements have been installed. Upon installation of park improvements, the City shall release the credited amount to the Developer. 23. SANITARY SEWER AND WATER UTILITY AVAILABILITY CHARGES (SAC AND WAC). The Developer shall be responsible for the payment of all sewer availability charges (SAC) and all water availability charges (WAC) with respect to the Improvements required by the City and any state or metropolitan government agency. The sewer availability charge (SAC) in the amount of $3,000.00 per REU shall be paid by the Developer prior to the City recording the final plat. The total amount to be paid by the Developer is $171,000.00. The water availability charge (WAC) in the amount of $3,000.00 per REU shall be paid by the Developer prior to the City recording the final plat. The total amount to be paid by the Developer is $171,000.00. In addition, a sewer connection charge in the current amount of $1,000.00 per REU, a Met Council sewer availability charge in the current amount of $2,435.00 per REU, and a water connection charge in the current amount of $1,000.00 per REU will be collected by the City at the time the building permit is issued for each lot. These amounts are charged at the time of building permit in accordance with the latest city fee schedule. 24. TRAFFIC CONTROL SIGNS. Traffic control signs shall be included as part of the public street improvements, and the installation costs shall be included in the street construction calculations. 25. STREET LIGHTS. The Developer is responsible for the installation of street lights 10 consistent with a street lighting plan approved by the City. The Developer shall coordinate the installation of street lights with Xcel Energy in conjunction with the other improvements, and agrees to pay Xcel Energy for all upfront costs associated with the street lighting system, including underground cables, posts, lamps, ballasts, starters, photocells, and glassware. All street lights will be leased by the City upon final acceptance of the system. The Developer shall also pay $499.68 in payment for the first year operating costs for street lights. 26. WETLAND MITIGATION. The Developer shall complete wetland mitigation/restoration in accordance with the approved Plans and Specifications and in accordance with any applicable Watershed or agency Permits. If the mitigation work is found to be incomplete or restoration is unsuccessful the City may draw down the security at any time during the warranty period if the Developer fails to take corrective measures to be used by the City to perform the work. Prior to the acceptance of the public improvements for the Hammes Estates plat, all wetland buffers shall be delineated and identified via staking and signage that is acceptable to the City. 27. BUILDING PERMITS/CERTIFICATES OF OCCUPANCY. A. Public sewer and water, curbing, and one lift of asphalt shall be installed on all public and private streets prior to issuance of any building permits, except five model homes on lots acceptable to the Community Development Director. B. Prior to issuance of building permits, wetland buffer monuments shall be placed in accordance with the City’s zoning ordinance. The monument design shall be approved by the Community Development Department. C. Written certification of the as-constructed grading must be on file at the City for the block where the building is to be located. D. Breach of the terms of this Contract by the Developer, including nonpayment of billings from the City, shall be grounds for denial of building permits and/or withholding of other permits, inspection or actions, including lots sold to third parties, and the halting of all work in the plat. E. If building permits are issued prior to the acceptance of public improvements, the 11 Developer assumes all liability and costs resulting in delays in completion of public improvements and damage to public improvements caused by the City, Developer, their contractors, subcontractors, materialmen, employees, agents, or third parties. F. No sewer and water connection permits may be issued until the streets needed for access have been paved with a bituminous surface and the utilities are tested and approved by the City Engineer. G. The City will not issue a certificate of occupancy for any building constructed on any lot or parcel in the Plat, including any model homes authorized under this agreement, until Public sewer and water, curbing, and one lift of asphalt is installed on all public and private streets; all utilities are tested and approved by the City Engineer; and the as- constructed grading must be on file at the City for the block where the building is to be located. 28. RESPONSIBILITY FOR COSTS. A. In the event that the City receives claims from labor, materialmen, or others that work required by this Contract has been performed, the sums due them have not been paid, and the laborers, materialmen, or others are seeking payment from the City, and in t he f ut ure event that such claims have not been resolved by t he Developer wit hin t hirt y (30) days af ter writt en not ice from the City, the Developer hereby authorizes the City to commence an Interpleader action pursuant to Rule 22, Minnesota Rules of Civil Procedure for the District Courts, to draw upon the letters of credit in an amount up to 125 percent of the claim(s) and deposit the funds in compliance with the Rule, and upon such deposit, the Developer shall release, discharge, and dismiss the City from any further proceedings as it pertains to the letters of credit deposited with the District Court, except that the Court shall retain jurisdiction to determine payment of attorneys' fees pursuant to this Contract. B. Except as otherwise specified herein, the Developer shall pay all costs incurred by it or the City in conjunction with the development of the plat, including but not limited to legal, planning, engineering and inspection expenses incurred in connection with approval and acceptance of the plat, the preparation of this Contract, review of construction plans and documents, and all costs and expenses 12 incurred by the City in monitoring and inspecting development of the plat. All amounts incurred and due at the time, must be fully paid prior to execution and release of the final plat for recording. C. The Developer shall hold the City and its officers, employees, and agents harmless from claims made by itself and third parties for damages sustained or costs incurred resulting from plat approval and development. The Developer shall indemnify the City and its officers, employees, and agents for all costs, damages, or expenses which the City may pay or incur in consequence of such claims, including attorneys' fees. D. The Developer shall reimburse the City for costs incurred in the enforcement of this Contract, including reasonable engineering and attorneys' fees. E. The Developer shall pay in full all bills submitted to it by the City for obligations incurred under this Contract within thirty (30) days after receipt. Bills not paid within thirty (30) days shall be assessed a late fee per the City of Lake Elmo adopted Fee Schedule. Upon request, the City will provide copies of detailed invoices of the work performed. 29. City Payments. In the event city payments are required by Section 29.A below, within thirty (30) days of the City's final acceptance of the Improvements, pursuant to Section 21 of this Agreement, but only if the Developer is not in default under this Agreement, the City shall pay to the Developer the sums set forth in the attachment to this Agreement as Exhibit B. The actual amount of the reimbursement shall be based on actual construction costs which will be verified by the Developer to the City in the Plans submitted to the City as required in Section 21. This payment by the City shall be the City's only responsibility with regard to construction of the Improvements and in no case shall act as a waiver of any other right of the City under this Agreement or under applicable laws, ordinances, or rules. A. City payments pursuant to this Agreement shall be: $50,045.00 30. SPECIAL PROVISIONS. The following special provisions shall apply to plat development: A. Implementation of the recommendations listed in the September 18, 2014 Engineering memorandum is required along with all conditions of approval listed in any City Council resolution approving the plat. 13 B. Within thirty (30) days of the plat being recorded at the County, the Developer shall convey Outlot A and C to the City by warranty deed, free and clear of any and all encumbrances. C. The Developer shall install a temporary turnaround at the southern end of June Avenue North until it is extended as part of future phases of the Hammes Estates development. D. The Developer must obtain a sign permit from the City Building Official prior to installation of any permanent subdivision identification signs. F. The Developer shall provide for a minimum green belt/buffer of 100 feet around all of the adjacent Stonegate subdivision. This buffer shall be secured by a covenant running in favor of the City and a title commitment issued therefore. G. All trails shall be located within the easements and dedicated to the City of Lake Elmo. Title commitments from a regional title company shall be provided for all land so dedicated. H. The Developer shall be responsible for the construction of all improvements within the Keats Avenue (CSAH 19) right-of-way as required by Washington County and further described in the review letter received from the County dated May 6, 2014. The required improvements shall include, but not be limited to: modifications to the median crossing in this area, continuation of a bituminous trail through the median, turn lanes, and other improvements as required by the County. I. The Developer shall observe all other County requirements as specified in the Washington County review letter dated May 6, 2014. J. The Developer shall enter into a maintenance agreement with and satisfactory to the City that clarifies the individuals or entities responsible for any landscaping installed in areas outside of land dedicated as public park and open space on the final plat. K. Any land under which public trails are located will be accepted as park land provided the Developer constructs said trails within the dedicated areas as part of the public improvements for the subdivision and easements are provided where required by the City. L. No more than one hundred units depicted on the preliminary plat (100) may be 14 approved as part of a final plat until a second access is provided to the subdivision via a connection through the property to the south of the Hammes Estates. M. The Developer shall be responsible to monitor the restored southern shoreline of Goose Lake for invasive species for a period of 5 years as specified in the MN DNR Public Waters Work Permit. N. The Developer shall submit all documentation of remediation activities related to a recorded soil contamination on the site to the Minnesota Pollution Control Agency for review and approval. The Developer shall submit the acknowledgment of approval from the Minnesota Pollution Control Agency to the City prior to the issuance of building permits for all lots in the recorded plat affected by the soil contamination event. The Developer must submit the acknowledgement of successful remediation from the MPCA prior to the City’s consideration of subsequent phases of the Hammes Estates development. 31. MISCELLANEOUS. A. The Developer may not assign this Contract without the written permission of the City Council. The Developer's obligation hereunder shall continue in full force and effect even if the Developer sells one or more lots, the entire plat, or any part of it. B. Retaining walls that require a building permit shall be constructed in accordance with plans and specifications prepared by a structural or geotechnical engineer licensed by the State of Minnesota. Following construction, a certification signed by the design engineer shall be filed with the City Engineer evidencing that the retaining wall was constructed in accordance with the approved plans and specifications. All retaining walls identified on the development plans or by special conditions referred to in this Contract shall be constructed before any other building permit is issued for a lot on which a retaining wall is required to be built. C. Appropriate legal documents including Homeowner Association documents, covenants and restrictions relating to the plat approval and outlots and conveyances, as approved by the City Attorney, shall be filed within thirty (30) days of the recording of the plat. No third- party beneficiary status is hereby conferred. All outlots and common areas, including Outlot D, shall be maintained in good order and repair by a homeowner’s association, and, if it does not do so, then the City may perform the work 15 and assess the costs against the individual lots within the plat of Hammes Estates and without regard to the formalities or requirements of Minn. Stat. § 429. D. Developer shall take out and maintain or cause to be taken out and maintained until six (6) months after the City has accepted the public improvements, public liability and property damage insurance covering personal injury, including death, and claims for property damage which may arise out of Developer's work or the work of its subcontractors or by one directly or indirectly employed by any of them. Limits for bodily injury and death shall be not less than $500,000 for one person and $1,000,000 for each occurrence; limits for property damage shall be not less than $200,000 for each occurrence; or a combination single limit policy of $1,000,000 or more. The City shall be named as an additional insured on the policy, and the Developer shall file with the City a certificate evidencing coverage prior to the City signing the plat. The certificate shall provide that the City must be given thirty (30) days advance written notice of the cancellation of the insurance. E. Third parties shall have no recourse against the City under this Contract. F. If any portion, section, subsection, sentence, clause, paragraph, or phrase of this Contract is for any reason held invalid, such decision shall not affect the validity of the remaining portion of this Contract. G. The action or inaction of the City shall not constitute a waiver or amendment to the provisions of this Contract. To be binding, amendments or waivers shall be in writing, signed by the parties and approved by written resolution of the City Council. The City's failure to promptly take legal action to enforce this Contract shall not be a waiver or release. H. This Contract shall run with the land and may be recorded against the title to the property. The Developer covenants with the City, its successors and assigns, that the Developer has fee title to the property being final platted and/or has obtained consents to this Contract, in the form attached hereto, from all parties who have an interest in the property; that there are no unrecorded interests in the property being final platted; and that the Developer will indemnify and hold the City harmless for any breach of the foregoing covenants. I. Each right, power or remedy herein conferred upon the City is cumulative and in 16 addition to every other right, power or remedy, express or implied, now or hereafter arising, available to City, at law or in equity, or under any other agreement, and each and every right, power and remedy herein set forth or otherwise so existing may be exercised from time to time as often and in such order as may be deemed expedient by the City and shall not be a waiver of the right to exercise at any time thereafter any other right, power or remedy. J. The Developer represents to the City that the plat complies with all city, county, metropolitan, state, and federal laws and regulations, including but not limited to: subdivision ordinances, zoning ordinances, and environmental regulations. If the City determines that the plat does not comply, the City may, at its option, refuse to allow construction or development work in the plat until the Developer does comply. Upon the City’s demand, the Developer shall cease work until there is compliance. 32. EVENTS OF DEFAULT. The following shall be "Events of Default" under this Agreement and the term "Event of Default" shall mean, whenever it is used in this Agreement, any one or more of the following events: A. Subject to unavoidable delays, failure by Developers to commence and complete construction of the Public Improvements pursuant to the terms, conditions and limitations of this Agreement and the continuance of such failure for a period of thirty (30) days after written notice thereof (provided, however, that in the event of a bona fide emergency, the City shall only be required to give such notice as is practicable under the circumstances). B. Failure by Developers to substantially observe or perform any material covenant, condition, obligation or agreement on their part to be observed or performed under this Agreement and the continuance of such failure for a period of thirty (30) days after written notice thereof (provided, however, that in the event of a bona fide emergency, the City shall only be required to give such notice as is practicable under the circumstances). 33. REMEDIES ON DEFAULT. Whenever any Event of Default occurs, the City, subject to any rights of third parties agreed to by the City pursuant to this Agreement, or otherwise by written, executed instrument of the City, may take any one or more of the following: A. The City may suspend its performance under the Agreement until it receives 17 assurances from Developers, deemed adequate by the City, that Developers will cure their default and continue their performance under the Agreement. Suspension of performance includes the right of the City to withhold permits including, but not limited to, building permits. B. The City may initiate such action, including legal or administrative action, as is necessary for the City to secure performance of any provision of this agreement or recover any amounts due under this Agreement from Developers, or immediately draw on the Letter of Credit, as set forth in this Agreement. In the event of any uncorrected failure to maintain any common area or landscape areas, the City may undertake to do the work and assess the costs to the individual lots within the plat without regard to the formalities or requirements of Minn. Stat. § 429.. 18 34. ENFORCEMENT BY CITY; DAMAGES. The Developer acknowledges the right of the City to enforce the terms of this Agreement against the Developer, by action for specific performance or damages, or both, or by any other legally authorized means. The Developer also acknowledges that its failure to perform any or all of its obligations under this Agreement may result in substantial damages to the City; that in the event of default by the Developer, the City may commence legal action to recover all damages, losses and expenses sustained by the City; and that such expenses may include, but are not limited to, the reasonable fees of legal counsel employed with respect to the enforcement of this Agreement. 35. WARRANTY. The Developer warrants all improvements required to be constructed by it pursuant to this Contract against poor material and faulty workmanship. The Developer shall submit either cash or a letter of credit for twenty-five percent (25%) of the amount of the original cost of the improvements. A. The required warranty period for materials and workmanship for the utility contractor installing public sewer and water mains shall be two (2) years from the date of final written City acceptance of the work. B. The required warranty period for all work relating to street construction, including concrete curb and gutter, sidewalks and trails, materials and equipment shall be one (1) year from the date of final written acceptance, unless the wearing course is placed during the same construction season as the bituminous base course. In those instances, the Developer shall guarantee all work, including street construction, concrete curb and gutter, sidewalks and trails, material and equipment for a period of two (2) years from the date of final written City acceptance of the work. C. The required warranty period for sod, trees, and landscaping is two growing seasons following installation. D. The required warranty for landscaping within storm water infiltration areas (Outlot A) shall be three (3) years following installation. The Developer shall also enter into a funded maintenance agreement with the City for a period of three (3) years prior to acceptance of the landscaping for within these storm water infiltration areas. Said maintenance agreement shall include requirements for the proper care of native plantings and the elimination of weeds and invasive species. 19 36. SUMMARY OF SECURITY REQUIREMENTS. To guarantee compliance with the terms of this agreement, payment of special assessments, payment of the costs of all public improvements, and construction of all public improvements, the Developer shall furnish the City with an irrevocable letter of credit, in the form attached hereto, from a bank, cash escrow or a combination cash escrow and Letter of Credit ("security") for $2,880,829.56. The amount of the security was calculated as follows: CONSTRUCTION COSTS: Streets $489,243.50 Sanitary Sewer $569,227.75 Watermain $359,915.00 Surface Water Facilities (pipe, ponds, rain gardens, etc.) $479,785.50 Grading $25,000.00 Erosion Control $25,801.90 Sidewalks/Trails $117,684.00 Street Lighting Xcel to Install, to be pre-paid directly by Developer Street Signs and Traffic Control Signs $3,550.00 Landscaping $222,656.00 Tree Preservation and Restoration $3,600.00 Wetland Mitigation and Buffers Separate letter of credit through Watershed District Monuments $5,700.00 Miscellaneous Facilities N/A Developer’s Record Drawings $2,500.00 Construction Sub-Total $2,304,663.65 Total Project Securities (at 125% Construction Costs) $2,880,829.56 20 This breakdown is for historical reference; it is not a restriction on the use of the security. The bank shall be subject to the approval of the City Administrator. The City may draw down the security, without notice, for any violation of the terms of this Contract or if the security is allowed to lapse prior to the end of the required term. If the required public improvements are not completed at least thirty (30) days prior to the expiration of the security, the City may also draw it down. If the security is drawn down, the proceeds shall be used to cure the default. 37. REDUCTION OF SECURITY. Upon written request by the Developer and upon receipt of proof satisfactory to the City Engineer that work has been completed and financial obligations to the City have been satisfied, with City Engineer approval the security may be reduced as follows: A. Up to 50%, or $1,440,414.78 of the security provided in accordance with paragraph 32. above may be released when: (1) Developer’s obligations under this Agreement have been completed and the Public Improvements have been found to be complete to the satisfaction of the City including all corrective work for any identified punch list items, but not including the final wear course; and (2) completion of the Improvements is done to the satisfaction of the City and evidence of such is provided by the City in writing and satisfactory evidence of payment, such as lien waivers are provided. B. Up to an additional 25%, or $720,207.39 of the security provided in accordance with paragraph 32. above may be released when: (1) Developer’s obligations under this Agreement have been completed and the Improvements have been found to be complete to the satisfaction of the City including all corrective work for any identified punch list items and including the final wear course; and (2) Improvements are accepted by the City in writing and satisfactory evidence of payment, such as lien waivers, are provided. C. Twenty percent (25%) of the amounts certified by the Developer's engineer shall be retained as security until: (1) all improvements have been completed, (2) iron monuments for lot corners have been installed, (3) all financial obligations to the City satisfied, (4) the required "record" plans have been received and approved by the City, (5) a warranty security is provided, and (6) the public improvements are accepted by the City. 38. SUMMARY OF CASH REQUIREMENTS. The following is a summary of the cash 21 Sewer Availability Charge (SAC) Water Availability Charge (WAC) Park Dedication Street Light Operating Fee City Base Map Upgrading City Engineering Administration Escrow Total Cash Requirements requirements under this Contract which must be furnished to the City at the time of final plat approval: $171,000.00 $171,000.00 $107,554.00 $499.68 $1,425.00 $50,000.00 (Based on two months of administration/observation) $501,478.68 39. NOTICES. Required notices to the Developer shall be in writing, and shall be either hand delivered to the Developer, its employees or agents, or mailed to the Developer by certified mail at the following address: 36 Moonlight Bay, Stillwater, MN 55082. Notices to the City shall be in writing and shall be either hand delivered to the City Administrator, or mailed to the City by certified mail in care of the City Administrator at the following address: Lake Elmo City Hall, 3800 Laverne Avenue N. Lake Elmo, Minnesota 55042. 40. EVIDENCE OF TITLE. Developer shall furnish the City with evidence of its fee ownership of the property being platted by way of an attorney’s title opinion or title insurance policy dated not earlier than thirty (30) days prior to the execution of the plat. CITY OF LAKE ELMO (SEAL) BY: , Mayor AND , City Clerk 22 DEVELOPER: THE RYLAND GROUP, INC. BY: Its STATE OF MINNESOTA ) ( ss. COUNTY OF WASHINGTON ) The foregoing instrument was acknowledged before me this day of , 2 , by and by , the Mayor and City Clerk of the City of Lake Elmo, a Minnesota municipal corporation, on behalf of the corporation and pursuant to the authority granted by its City Council. NOTARY PUBLIC STATE OF MINNESOTA ) ( ss. COUNTY OF ) The foregoing instrument was acknowledged before me this_____day of________________, 2015, by The Ryland Group, Inc., a Maryland corporation, for and on behalf of the corporation. NOTARY PUBLIC DRAFTED BY: City of Lake Elmo 3800 Laverne Avenue North Lake Elmo, MN 55042 (651) 747-3901 23 FEE OWNER CONSENT TO DEVELOPMENT CONTRACT , fee owners of all or part of the subject property, the development of which is governed by the foregoing Development Contract, affirm and consent to the provisions thereof and agree to be bound by the provisions as the same may apply to that portion of the subject property owned by them. Dated this day of , 2 . STATE OF MINNESOTA ) ( ss. COUNTY OF ) The foregoing instrument was acknowledged before me this day of , 2 , by . NOTARY PUBLIC DRAFTED BY: City of Lake Elmo 3800 Laverne Avenue North Lake Elmo, MN 55042 (651) 747-3901 24 MORTGAGE CONSENT TO DEVELOPMENT CONTRACT , which holds a mortgage on the subject property, the development of which is governed by the foregoing Development Contract, agrees that the Development Contract shall remain in full force and effect even if it forecloses on its mortgage. Dated this day of , 2 . STATE OF MINNESOTA ) ( ss. COUNTY OF ) The foregoing instrument was acknowledged before me this day of _, 2 , by . NOTARY PUBLIC DRAFTED BY: City of Lake Elmo 3800 Laverne Avenue North Lake Elmo, MN 55042 (651) 747-3901 25 EXHIBIT “A” TO DEVELOPMENT CONTRACT Legal Description of Property Being Final Platted as Hammes Estates 1st Addition That part of the South Half of the Northeast Quarter of Section 34, Township 29 North, Range 21 West, Washington County, Minnesota, EXCEPT the East 60.00 feet of the North 967 feet of said South Half of the Northeast Quarter thereof. AND EXCEPT Parcel 3 of Washington County Highway Right of Way Plat 49-19B, recorded September 18, 1985 as Document Number 492530. 26 EXHIBIT “B” TO DEVELOPMENT CONTRACT City Oversizing Payment Calculation Contract Item Unit Cost/ Cost Increase (8” to 12” WM) Quantity Amount Watermain LF $12.50 3,104 $38,800.00 Gate Valves EA $1,225.00 4 $4,900.00 Plugs EA $345.00 2 $690.00 Fittings Lbs $5.00 1,131 $5,655.00 Total Oversizing Estimate $50,045.00 27 IRREVOCABLE LETTER OF CREDIT No. Date: TO: City of Lake Elmo Dear Sir or Madam: We hereby issue, for the account of (Name of Developer) and in your favor, our Irrevocable Letter of Credit in the amount of $_ , available to you by your draft drawn on sight on the undersigned bank at its offices in Minnesota. The draft must: a) Bear the clause, "Drawn under Letter of Credit No. , dated , 2 , of (Name of Bank) "; b) Be signed by the Mayor or City Administrator of the City of Lake Elmo. c) Be presented for payment at (Address of Bank) , on or before 4:00 p.m. on November 30, 2_ _. This Letter of Credit shall automatically renew for successive one-year terms unless, at least forty-five (45) days prior to the next annual renewal date (which shall be November 30 of each year), the Bank delivers written notice to the Lake Elmo City Administrator that it intends to modify the terms of, or cancel, this Letter of Credit. Written notice is effective if sent by certified mail, postage prepaid, and deposited in the U.S. Mail, at least forty-five (45) days prior to the next annual renewal date addressed as follows: City Administrator, City Hall, 3800 Laverne Ave. N. Lake Elmo Minnesota 55042 and is actually received by the City Administrator at least thirty (30) days prior to the renewal date. This Letter of Credit sets forth in full our understanding which shall not in any way be modified, amended, amplified, or limited by reference to any document, instrument, or agreement, whether or not referred to herein. This Letter of Credit is not assignable. This is not a Notation Letter of Credit. More than one draw may be made under this Letter of Credit. This Letter of Credit shall be governed by the most recent revision of the Uniform Customs and Practice for Documentary Credits, International Chamber of Commerce Publication No. 500. We hereby agree that a draft drawn under and in compliance with this Letter of Credit shall be duly honored upon presentation. BY: Its 28 MAYOR & COUNCIL COMMUNICATION DATE: October 7, 2014 REGULAR ITEM # 14 AGENDA ITEM: Hammes Estates Residential Subdivision - Final Plat (Phase 1) SUBMITTED BY: Nick M. Johnson, City Planner THROUGH: Dean Zuleger, City Administrator REVIEWED BY: Planning Commission Kyle Klatt, Community Development Director Jack Griffin, City Engineer Greg Malmquist, Fire Chief Stephen Mastey, City’s Landscape Consultant SUGGESTED ORDER OF BUSINESS: - Introduction of Item .....................................Community Development Director - Report/Presentation………………………...Community Development Director - Questions from Council to Staff ............................................. Mayor Facilitates - Call for Motion ............................................................... Mayor & City Council - Discussion ....................................................................... Mayor & City Council - Action on Motion .................................................................... Mayor Facilitates POLICY RECCOMENDER: The Planning Commission is unanimously recommending that the City Council approve a final plat request from Hammes West, LLC for the first phase of a 163 unit residential development to be located on 78 acres of land west of Keats Avenue and within the City’s I-94 Corridor Planning Area. The final plat will include 57 single-family lots, all of which will be accessed off of Keats Avenue (CSAH 19). FISCAL IMPACT: TBD – the City will be asked to review a developer’s agreement concerning the final plat at its October 7, 2014 meeting. The agreement will include a detailed accounting of any development costs that will be the responsibility of the City. The subdivision is included in the Section 34 utility project area, and therefore the developer is being assessed for the costs of the project to bring sewer and water to the site. SUMMARY AND ACTION REQUESTED: The City Council is being asked to consider a request from Hammes West, LLC for approval of a final plat for the first phase of the Hammes Estates residential development. The final plat includes 57 single-family residential lots, and the -- page 1 -- City Council Meeting [Regular Agenda Item 14] October 7, 2014 related construction plans for the improvements necessary to serve these homes. The City Council approved the Hammes Estates Preliminary Plat on July 1, 2014, which covered approximately 78 acres of land within the I-94 Corridor planning area. There are 163 single family residential lots planned within the entire subdivision, and the final plat covers only a portion of the overall total of units that will eventually be platted. The public improvements associated with the site will be installed by The Ryland Group in conjunction with the applicant. The Planning Commission considered this matter at its September 22, 2014 meeting and unanimously recommended approval of the final plat subject to 16 conditions of approval. The suggested motion to adopt the Planning Commission recommendation is as follows: “Move to adopt Resolution No. 2014-81, approving the final plat for Hammes Estates” BACKGROUND INFORMATION: Attached are the original detailed Staff report that was provided to the Planning Commission regarding the applicant’s request for a final plat, which includes general information about the application, a summary of the relevant planning and zoning issues, a thorough review and analysis of the final plat (including a draft list of recommended conditions of approval), draft findings, and the Staff recommendation to the Planning Commission. In addition to the information provided in the Staff Report, it should be noted that the applicant is requesting to amend Condition #13 related to the Minnesota Pollution Control Agency (MPCA) approval letter of the remediation of the soil contamination event on the Hammes site. As demonstrated in the request letter in Attachment #3, the applicants are requesting that the approval letter from the MPCA be provided prior to the issuance of building permit for affected lots as opposed to prior to the release of the Final Plat. The reason for the request relates to the closing of the property by The Ryland Group. If the Final Plat is delayed due to the MPCA approval process, which is estimated to take 30-60 days, the closing or purchase of a large portion of the property by the Ryland Group will also be delayed. After consulting with the Fire Chief and MPCA on the request, staff determined that the request is reasonable and will not create a negative or dangerous situation in the interim period while the review by MPCA is completed. It should be noted that the applicants have submitted a Phase 1 Environmental Review for the site, as well as substantial information regarding the cleanup and disposal of the contaminated soil. The Fire Chief simply want to close the loop by requesting the applicant enter the Voluntary Brownfield Program to ensure that the remediation work that was completed has properly addressed the contamination. Staff recommends that condition #13 be amended per the suggested language from the applicant (Attachment #3). PLANNING COMMISSION REPORT: The Planning Commission reviewed the final plat application at its September 22, 2014 meeting. During the meeting, the Planning Commission engaged in discussions regarding the design and locations of the trails, the stormwater facilities, the phasing of the proposed subdivision, and other pertinent topics and questions. In reviewing the final plat, the Planning Commission -- page 2 -- City Council Meeting [Regular Agenda Item 14] October 7, 2014 recommended two additional conditions of approval: 1) that any trail segment designed as a boardwalk must be able to safely accommodate bicycle traffic, and 2) that the developer must inventory and replace trees that are removed on the City park land due to the installation of the trail. The Planning Commission recommended that the trees be replaced at the schedule or rate required under the City’s tree preservation ordinance (§154.257). In addition to these added conditions, the Planning Commission wanted to ensure that the MPCA approve the soil remediation work prior to the City releasing final plat for recording. Further detail of the Planning Commission discussion on the Hammes Estates Final Plat can be found in the 9/22/14 draft minutes. The Planning Commission recommended approval of the final plat as submitted with 16 conditions of approval. The vote to recommend approval of the Hammes Estates Final Plat was unanimous (Vote: 7-0). STRENGTHS, WEAKNESSES, OPPORTUNITIES, THREATS: Strengths: The proposed final plat is consistent with the approved preliminary plat subject to the conditions being recommended by Staff and the Planning Commission. Weaknesses: Several conditions of approval must be met by the applicant, including revisions to the final construction plans to address comments from the City Engineer. Opportunities: Approval of the plat application allows the development plans for the Hammes site to proceed as planned in the Comprehensive Plan. Moving forward with sewered single family growth should allow the City to add additional users to the City’s public sanitary sewer system, helping to finance the City’s investments in sanitary sewer. Threats: None RECOMMENDATION: Based on the aforementioned, the Planning Commission and Staff are recommending that the City Council approve the Hammes Estates Final Plat subject to 16 conditions of approval through the following motion: “Move to adopt Resolution No. 2014-81, approving the final plat for Hammes Estates” ATTACHMENTS: 1. Resolution 2014-81 2. Staff Report to the Planning Commission, 9/22/14 3. Hammes West, LLC Request to Amend Condition #13 4. Application Form 5. Preliminary Plat Response Letter (Westwood Engineering) 6. Final Plat (3 sheets) -- page 3 -- City Council Meeting [Regular Agenda Item 14] October 7, 2014 7. Final Construction Plans (Sanitary Sewer, Water Main, Storm Sewer and Streets – 17 sheets) 8. Final Construction Plans (Grading, Drainage and Erosion Control – 14 sheets) 9. Final Landscape Plans (4 sheets) 10. Park Location Plan 11. City Engineer Review Memorandum, dated 9/18/14 12. Fire Chief Review Memorandum, dated 9/18/14 13. Landscape Consultant Review Memorandum, dated 8/25/14 and 9/18/14 14. Valley Branch Watershed District Permit 15. MN DNR Permit to Restore Southern Shore of Goose Lake 16. Excerpt of Park Commission Minutes from 7/21/14 Meeting. 17. Goose Lake Park Area Sketch 18. Soil Contamination Remediation Report -- page 4 -- CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2014-81 A RESOLUTION APPROVING A FINAL PLAT FOR HAMMES ESTATES WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing under the laws of the State of Minnesota; and WHEREAS, Hammes West, LLC, 36 Moonlight Bay, Stillwater, MN (Applicant) has submitted an application to the City of Lake Elmo (City) for a Final Plat for Hammes Estates, a copy of which is on file in the City of Lake Elmo Community Development Department; and WHEREAS, the Lake Elmo Planning Commission held a public hearing on May 12, 2014 to consider the Hammes Estates Preliminary Plat and continued discussion on the Preliminary Plat until its June 23, 2014 meeting; and WHEREAS, the Lake Elmo Planning Commission has submitted its report and recommendation concerning the Preliminary Plat as part of a memorandum to the City Council for the July 1, 2014 City Council Meeting; and WHEREAS, the Lake Elmo Planning Commission adopted a motion recommending approval of the Preliminary Plat; and WHEREAS, the City Council reviewed the Preliminary Plat request at its July 1, 2014 meeting and adopted Resolution No. 2014-55 approving the Preliminary Plat; and WHEREAS, the Lake Elmo Planning Commission met on September 22, 2014 to review the Final Plat for Hammes Estates consisting of 57 single-family residential lots; and WHEREAS, on September 22, 2014 the Lake Elmo Planning Commission adopted a motion to recommend that the City Council approve the Final Plat for Hammes Estates with conditions; and WHEREAS, the City Council reviewed the recommendation of the Planning Commission and the Final Plat for Hammes Estates at a meeting held on October 7, 2014; and NOW, THEREFORE, based upon the testimony elicited and information received, the City Council makes the following: FINDINGS 1) That the procedure for obtaining approval of said Final Plat is found in the Lake Elmo City Code, Section 153.08. 1 Resolution 2014-81 2) That all the requirements of said City Code Section 153.08 related to the Final Plat have been met by the Applicant. 3) That the proposed Final Plat for Hammes Estates consists of the creation of 57 single-family residential lots. 4) That the Hammes Estates Final Plat is consistent with the Preliminary Plat and Plans as approved by the City of Lake Elmo on July 1, 2014 and revised on August 25, 2014. 5) That the Hammes Estates Final Plat is consistent with the Lake Elmo Comprehensive Plan and the Future Land Use Map for this area. 6) That the Hammes Estates Final Plat complies with the City’s Urban Low Density Residential zoning district. 7) That the Hammes Estates Final Plat complies with all other applicable zoning requirements, including the City’s landscaping, storm water, sediment and erosion control and other ordinances, except as noted in this report or attachment thereof. 8) That the Hammes Estates Final Plat complies with the City’s subdivision ordinance. 9) That the Hammes Estates Final Plat is consistent with the City’s engineering standards with the exceptions noted by the City Engineer in his review comments to the City dated September 18, 2014. CONCLUSIONS AND DECISION NOW, THEREFORE, BE IT RESOLVED THAT the City Council does hereby approve the Final Plat for Hammes Estates subject to the following conditions: 1) Final grading, drainage, and erosion control plans, utility plans, sanitary and storm water management plans, and street and utility construction plans shall be reviewed and approved by the City Engineer prior to the recording of the Final Plat. All changes and modifications to the plans requested by the City Engineer in a memo dated 9/18/14 shall be incorporated into these documents before they are approved. 2) The developer shall provide evidence in a form satisfactory to the City Attorney that warrants it has fee interest in area included in the Hammes Estates Final Plat. 3) Prior to the execution of the Final Plat by City officials, the Developer shall enter into a Developer’s Agreement acceptable to the City Attorney and approved by the City Council that delineates who is responsible for the design, construction, and payment of the required improvements with financial guarantees therefore. 2 Resolution 2014-81 4) All easements as requested by the City Engineer and Public Works Department shall be documented on the Final Plat prior to the release of the Final Plat for recording. 5) A Common Interest Agreement concerning management of the common areas of Hammes Estates and establishing a homeowner’s association shall be submitted in final form to the Community Development Director before a building permit may be issued for any structure within this subdivision. Said agreement shall comply with Minnesota Statues 515B.3-103, and specifically the provisions concerning the transfer of control to the future property owners. The applicant shall also enter into a maintenance agreement with the City that clarifies the individuals or entities responsible for any landscaping installed in areas outside of land dedicated as public park and open space on the Final Plat. 6) The applicant shall provide fees in lieu of land dedication for 2.1 acres of land to fulfill the City’s parkland dedication requirements in a pro-rated amount for the Phase 1 Area or in an amount addressing the total site. 7) The Final Landscape Plan shall be revised per the requested modifications of the City Landscape Consultant, documented in a memo dated 9/18/14. Final Landscape Plans shall be approved prior to the release of Final Plat for recording. 8) The applicant shall provide evidence that all conditions attached to the Valley Branch Watershed District permit for the Final Plat and associated grading work have been met prior to the commencement of any final grading activity. 9) The applicant must provide written authorization to perform any work in the Electrical Transmission easement areas prior to the release of the Final Plat for recording. 10) The applicant shall provide evidence that Washington County has approved final construction plans for all required work within the Keats Avenue right-of-way as described in a letter from the County dated May 6, 2013. Final Construction Plans provided to the City shall be updated to include the improvements approved by Washington County 11) The applicant shall abide by all conditions of the MN DNR Public Waters Work Permit dated 8/27/14. 12) The applicant must revise the Goose Lake Park Plan to provide greater separation between the public use area and the lift station maintenance area. The applicant will be responsible for all necessary watershed district permitting requirements related to the Goose Lake Park improvements. 13) Per the recommendation of the Fire Chief, the applicant must submit all documentation related to the mitigation of the soil contamination to the Minnesota Pollution Control Agency’s Voluntary Brownfield Program for review and approval prior to the release of Final Plat for recording. 14) Prior to the acceptance of the public improvements for the 1st Phase of the Hammes Estates subdivision, all wetland buffers shall be delineated and identified via staking or signage that is acceptable to the City. 3 Resolution 2014-81 15) Any boardwalk trail segments included in the Hammes Estates subdivision must be designed to accommodate bicycle traffic. 16) All trees impacted by the northern buffer trail must be inventoried and replaced at the schedule or rate specified in the City’s tree preservation ordinance (§154.257). Passed and duly adopted this 7th day of October 2014 by the City Council of the City of Lake Elmo, Minnesota. __________________________________ Mike Pearson, Mayor ATTEST: ________________________________ Adam Bell, City Clerk 4 Resolution 2014-81 7 Ilumms Wpsr, LLC 36 Moom,rcut Blv Sru,r,warrn, MN 55082 Septembdr 30,2014 Mr. NickJohnson City of Lake Elmo qi ohnson@l akeelmo. org Re: City of Lake Etno Requirements DearNick: We are requesting that Condition No. 13 of the Plarning Commission recommendation be amended to state the following: o?er the recommendation of the Fire Chief, the applicant must submit all documentation related to the mitigation of the soil contamination to ttre Minnesota Pollution Control Agency's Voluntary Brownfield Program for review and approval pnor to the issuance of building permits for lots affected by the soil contasrination, if any." Thank you. Sincerely, Hem,msWnsr,LLC / t I /*#*'//*\- Managing Member a. Park Sign Update (Macleod) Macleod shared that two signs were finished (Reid and Pebble) and picked up earlier that day. The rest of the signs are anticipated to be completed by the first week of August, with Sunfish Lake Park being the next in line for completion. An amenity panel for one of the signs was in the council chambers for the commission to view. b. LERT Update (Weis) Weis stated that city planner Johnson has continued to talk to Washington County and that they are working on the west side access plan. Zuleger added that the LERT is currently on hold but the city has been talking with the county about being incorporated into the master plan to be considered by the Met Council. Zuleger added that Met Council Park and Open Space Chair, former Mayor Johnston, recently dropped off a copy of the master plan, which has been serving as a guide for next steps. Hietpas referenced the search corridor and stated that the LERT was not currently part of that plan. She commented that regionally, there are a lot of trails going on in other areas, but hardly anything in Washington County and she would like to see more priority placed on Lake Elmo trails at a county level. Weis commented on other communities coming forward and that trail plan requests are becoming more prevalent in the county. Ames asked what the next steps are. Zuleger responded that the city has been requesting that the search corridor be included as a key corridor in the county's trail plan between Oakdale and Stillwater, connecting to a regional park. The City is continuing to have conversations with the county about the best way to access the Lake Elmo Park Reserve. Weis has offered to present the LERT presentation to the County to keep the ball rolling. He emphasized that it is important to get included in the plan because it will open up a lot of funding opportunities. c. Hammes Park Space (Zuleger) Zuleger stated that there was an item not on the agenda that needed to be addressed: The Hammes subdivision park space. To recap, Zuleger shared that per previous discussion and in response to the commission's request, the Hammes developers had placed the park in the northwest corner of the development near Keats Avenue and Goose Lake. The proposed park space includes a fish ing pier, shelter, grill, parking lot and is also where the lift station is located. Currently the plan does not include a play structure, which was initially requested by the park commission as a condition of approval. The Hammes developers are seeking input from the commission as to what type of play structure to include, and if they could receive credit for parkland dedication if the structure was included. Zuleger continued to point out additional green/meeting spaces within the development and the 100' buffer perimeter per the comp plan (including a trail). Ames thought he remembered a small park internally in the neighborhood that would have a play structure. He is not sure that a play structure near a 55 mph roadway is a good place for a play structure. Ames also questioned where neighborhood children would play, as lot sizes looked small to consider private play sets. Zuleger pointed out that the Lake Elmo Park Reserve was located a mile north of the development, with a phenomenal play set. Ames stated that he didn't feel current playgrounds were within reasonable walking distance for residents. Hietpas shared that she didn't feel that the green spaces included throughout the development were large enough for community meeting spaces. Zuleger pointed out the location of neighboring parks in Stonegate and Lennar neighborhoods. The commission requested that a location central in the neighborhood be considered for play structure placement. Zuleger said that he would forward their comments to the developers. Meeting adjourned at 9:54 PM Respectfully Submitted, Alyssa Macleod, Recording Secretary