Loading...
HomeMy WebLinkAbout#13 CC Report Rieder Preliminary Plat Extension 12 15 15 MAYOR & COUNCIL COMMUNICATION -- page 1 -- DATE: December 15, 2015 CONSENT ITEM # 13 AGENDA ITEM: Rieder Property– Preliminary Plat Extension SUBMITTED BY: Stephen Wensman, City Planner REVIEWED BY: Clark Schroeder SUGGESTED ORDER OF BUSINESS: - Introduction of Item ........................................................................ City Planner - Report/Presentation………………………………………………...City Planner - Questions from Council to Staff ............................................. Mayor Facilitates - Call for Motion ............................................................... Mayor & City Council - Discussion ....................................................................... Mayor & City Council - Action on Motion .................................................................... Mayor Facilitates SUMMARY AND ACTION REQUESTED: The City Council is being asked to consider a request by Mr. Rieder for Preliminary Plat Extension. The City Council approved Resolution 2015-056 granting preliminary plat approval on July 21, 2015. According to Lake Elmo City Ordinance 153.07 a subdivider of land must submit a final plat within 180 days after approval of preliminary plat or the plat will be considered void. Staff is recommending approval of the Preliminary Plat Extension. Staff recommends approval of the request with the following motion: “Move to adopt Resolution No. 2015-086 approving the Rieder (Lennar Diedrich) Townhouses preliminary plat extension for one year.” BACKGROUND AND STAFF REPORT: The City Council approved Resolution 2015-056 granting preliminary plat approval for a 46-unit singled family attached (townhouse) development to be located on slightly over 15 acres of land immediately east of Lake Elmo Avenue and north of the Hunters Crossing development. The applicant, Mr. Rieder is requesting the extension to allow for more time to arrange bank financing and prepare for final plat. City Council Meeting [Regular Agenda Item 13] December 1, 2015 -- page 2 -- As with previous extension considerations, the City Council has the right to reconsider. According to the City Attorney: “The council can reconsider any action …[but the] motion to reconsider must be brought by somebody who voted in the affirmative…. But, there is, however, the matter of what standards are to be applied in considering a reconsideration (must not be arbitrary, must not be capricious, must be fact-based) and the matter of whether intervening rights have accrued in the meantime (ie: whether the applicant has taken steps or materially changed its position after the first vote). Bottom line, absent a showing of materially changed circumstances, reconsideration can be raised, but a vote to effectuate it is likely not recommended”. According to MN State Statutes, the applicant must have filed the approved plat or followed through with conditions, so even if the Council wishes to see something different happen on this land, it cannot compel such changes within a period of two years after the original plat approval. If the Council elects to not approve the extension, the developer can reapply for preliminary and final plat, and Council will have to approve the requests (as it would be very difficult to arrive at findings for denial when the subdivision has already been approved under existing regulations). For reference, the relevant statute reads as follows: Statute 462.358 Subd. 3c. Effect of subdivision approval. For one year following preliminary approval and for two years following final approval, unless the subdivider and the municipality agree otherwise, no amendment to a comprehensive plan or official control shall apply to or affect the use, development density, lot size, lot layout, or dedication or platting required or permitted by the approved application. Thereafter, pursuant to its regulations, the municipality may extend the period by agreement with the subdivider and subject to all applicable performance conditions and requirements, or it may require submission of a new application unless substantial physical activity and investment has occurred in reasonable reliance on the approved application and the subdivider will suffer substantial financial damage as a consequence of a requirement to submit a new application. In connection with a subdivision involving planned and staged development, a municipality may by resolution or agreement grant the rights referred to herein for such periods of time longer than two years which it determines to be reasonable and appropriate. In summary, in considering the applicants request the City Council should consider whether there has been any intervening area-wide zoning or big land-use changes since the original approval of the plat. To deny, the City Council would need to cite some material fact. The Council’s decision cannot be arbitrary or capricious. If denied, the Reider’s and/or their developer could go through the approval process again spending time and money (which would then restart their two-year protection clock). Staff’s valuable time would be taken to again review and provide reports, and the public hearings would be held for an item that essentially has a predetermined outcome. Accordingly, it is strongly recommended that City Council approve this item on the consent agenda and grant the requested one-year extension to file the approved final plat. City Council Meeting [Regular Agenda Item 13] December 1, 2015 -- page 3 -- MORITORIUM: This development is not affected by the City’s moratorium since it received preliminary plat approval prior to July 22, 2015. FISCAL IMPACT: • 5th Street: The City will require that the applicant enter into a developer’s agreement with the City to specify the financial responsibilities for various aspects of the subdivision and related public improvements. It is expected that the project will include the construction of the northern half of the segment of 5th Street to the east of Lake Elmo. • Municipal services and property taxes: The developer is expected to pay the Water Availability Charge for the entire development at the time a final plat ($138,000 per unit) and Sewer Accessibility Charge ($138,000) similar to other developments that are connecting to the Municipal services. In addition, at the time of building permit issuance, water and sewer connection charges will be collected in the amount of $2,000/unit ($92,000).When fully developed, the property taxes will produce roughly ($350,000x46).002=$32,200) in increased revenue per year. SUMMARY AND ACTION REQUESTED: The City Council is being asked to consider a request for approval of a Preliminary Plat Extension for a 46-unit singled family attached (townhouse) development to be located on slightly over 15 acres of land immediately east of Lake Elmo Avenue and north of the Hunters Crossing development. “Move to adopt Resolution No. 2015-086 approving the Rieder (Lennar Diedrich) Townhouses preliminary plat extension for one year.” ATTACHMENTS: 1. Resolution No. 2015-086 approving the Rieder Preliminary extension for one year. 2. Resolution No. 2015-056 approving the preliminary plat 3. Lennar Diedrich Townhouses Preliminary Plat 4. City Council Packet 7-21-15 1 Resolution 2015-__ CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2015-86 A RESOLUTION APPROVING WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing under the laws of the State of Minnesota; and WHEREAS, Gerhart Rieder, property owner, 7401 Wyndham Way, Woodbury, MN 55125, submitted an application to the City of Lake Elmo (City) for a preliminary plat for a 46- unit singled family attached (townhouse) development on approximately 15 acres in the RT- Rural Development Transitional Zoning District (PID: 36.029.21.32.0002) referred to as Lennar Diedrich Property Preliminary Plat, a copy of which is on file in the City of Lake Elmo Community Development Department; and WHEREAS, on July 7, 2015, the Lake Elmo Planning Commission reviewed and recommended approval of the Lennar Diedrich Preliminary Plat; and WHEREAS, on July 21, 2015, the Lake Elmo City Council adopted Resolution 2015- 056 granting preliminary plat approval for a 46-unit singled family attached (townhouse) development WHEREAS, Gerhart Reider has requested a 12-month extension to the Final Plat submittal deadline of the approved plat to allow for additional time to prepare for financing and other planning activities; NOW, THEREFORE, BE IT RESOLVED THAT the City Council does hereby approve a 12-month extension to the Final Plat deadline for the Lennar Diedrich property residential subdivision, thereby extending the final plat application deadline to December 1, 2016. Passed and duly adopted this 15th day of December, 2015 by the City Council of the City of Lake Elmo, Minnesota. ___________________________________ Mike Pearson, Mayor ATTEST: ____________________________________ Julie Johnson, City Clerk MAYOR & COUNCIL COMMUNICATION -- page 1 -- DATE: July 21, 2015 REGULAR ITEM # 14 RESOLUTION 2015-056 AGENDA ITEM: Diedrich Property Townhouses (Lennar) – Preliminary Plat SUBMITTED BY: Kyle Klatt, Community Development Director THROUGH: Julie Johnson, City Clerk REVIEWED BY: Planning Commission Nick Johnson, City Planner Jack Griffin, City Engineer SUGGESTED ORDER OF BUSINESS: - Introduction of Item .....................................Community Development Director - Report/Presentation………………………...Community Development Director - Questions from Council to Staff ............................................. Mayor Facilitates - Call for Motion ............................................................... Mayor & City Council - Discussion ....................................................................... Mayor & City Council - Action on Motion .................................................................... Mayor Facilitates POLICY RECCOMENDER: The Planning Commission is recommending approval of a preliminary plat for a new subdivision as requested by Lennar Corporation. The Subdivision Ordinance requires that the City Council review and approval a preliminary plat before an applicant may proceed with the preparation and recording of a final plat. The subdivision request is being made by Lennar for property presently owned by Tammy Diedrich and Gerhard Rieder within the I-94 Corridor planning area. FISCAL IMPACT: TBD – The City will require that the applicant enter into a developer’s agreement with the City to specify the financial responsibilities for various aspects of the subdivision and related public improvements. The developer is expected to pay the Water Availability Charge for the entire development at the time a final plat is approved (currently $3,000 per unit) similar to other developments that are connecting to the Lake Elmo Avenue water main. SUMMARY AND ACTION REQUESTED: The City Council is being asked to consider a request for approval of a Preliminary Plat from Lennar Corporation for a 46-unit singled family City Council Meeting [Regular Agenda Item 14] July 21, 2015 -- page 2 -- attached (townhouse) development to be located on slightly over 15 acres of land immediately east of Lake Elmo Avenue and north of the Hunters Crossing development. The proposed development site is located within the City’s I-94 corridor planning area, and is in an area guided for public sewer and water services. The preliminary plat has been prepared in response to the City’s Comprehensive Plan for the corridor, which guides this site for medium density urban residential development. The Staff report to the Planning Commission concerning this request is attached to this memorandum, and includes a detailed summary of the request in addition to the detailed Staff review and recommendation. The City Council was scheduled to review this request at the 7/7/15 meeting, but consideration was postponed at request of the applicant. The applicant has now requested that consideration be placed back on the agenda The Planning Commission is recommending approval of the preliminary plat with several conditions of approval. The suggested motion to adopt the Planning Commission recommendation is as follows: “Move to adopt Resolution No. 2015-056 approving the Lennar Diedrich Townhouses preliminary plat with 16 conditions of approval.” LEGISLATIVE HISTORY/PLANNING COMMISSION REPORT: The attached staff report to the Planning Commission provides an overview of the request and a list of comments and recommendations from Staff. In order to address the initial set of comments from the City, the developer prepared an updated site plan prior to the Planning Commission meeting that reduced the overall number of units by two and that changed the originally planned private street to a public street meeting City specifications. Although the construction plans have not yet been updated, the Planning Commission’s review focused on the updated site plan. The City will still need to review updated construction plans, and all previous review comments from the City Engineer and County Engineer will need to be addressed by the applicant. Since the Planning Commission meeting the developer has updated the landscape plan to provide a better overview of how the site will look when completed. The Planning Commission considered the preliminary plat at its June 22, 2015 meeting and conducted a public hearing on the applicant’s request at this time. No one spoke at the public hearing. The Planning Commission discussed the request and specifically issues associated with the timing of improvements to 5th Street, the updated site plan, and potential issues associated with the new configuration of lots. The Commission also noted that the developer would need to address an ownership issue in the extreme southwestern portion of the plat. Specifically, Ryland Homes owns a small remnant of land that is sandwiched between 5th Street and the Lennar property. This property is shown as part of the Lennar plat, but it may be excluded from the subdivision based on the developers’ comments at the meeting. If this is the case, four of the lots need be adjusted in order to provide adequate rear yard setbacks. This is not a major plat concern, but will need to be addressed as part of a final plat submission. The Commission adopted a finding of fact to document their concerns over this issue. City Council Meeting [Regular Agenda Item 14] July 21, 2015 -- page 3 -- The Commission further discussed the status of parks in this area and the developer’s request to pay a fee in lieu of land dedication. Commissioners adopted a motion to include a finding that there are no City parks within ½ mile of the subdivision site. The Commission also requested one additional condition of approval to clarify that the developer must secure a written agreement from Xcel Energy to perform the planned grading work within the existing power line easement. The conditions of approval as amended by the Planning Commission are incorporated into the draft resolution. The Planning Commission adopted a motion to recommend approval of the Preliminary Plat with the findings and conditions as noted in the attached Resolution 2015-056. The motion passed unanimously (7-0). BACKGROUND INFORMATION (SWOT): Strengths • The preliminary plat is consistent with the Comprehensive Plan and specifically the Urban Medium Density Residential land use classification. • The project will connect to the Cottage Grove sewer interceptor via a connection to the gravity line constructed across the project site late last year. • The project will connect to the Lake Elmo Avenue water main recently installed in this area. Weaknesses • The two developers adjacent to 5th Street have not yet agreed to build this road as a joint project. Opportunities • The development will include 46 REC units and will pay connection fees for sewer and water service. The developer has committed to paying the water availably charge for the entire development ($138,000 based on the current fee schedule) with the first phase of the final plat. • The project will include the construction of the initial segment of 5th Street to the east of Lake Elmo (which must either be constructed as a public project or privately by the developer). Threats • None identified. RECOMMENDATION: Based upon the above background information, Staff report and Planning Commission recommendation, it is recommended that the City Council approve the Lennar Diedrich Townhouses preliminary plat with the 16 conditions of approval as documented in the resolution of approval by taking the following action / with the following motion: “Move to adopt Resolution No. 2015-056 approving the Lennar Diedrich Townhouses preliminary plat with 16 conditions of approval.” City Council Meeting [Regular Agenda Item 14] July 21, 2015 -- page 4 -- ATTACHMENTS: 1. Resolution No. 2015-056 2. Planning Commission Report (6/22/15) 3. Application Forms 4. Application Narrative and Information 5. Location Map 6. Tree Inventory 7. Review Comments: a. City Engineer b. Washington County 8. Preliminary Plat and Plans (20 sheets) a. Revised Site Plan (Dated 6/19/15) b. Revised Landscape Plan (Dated 6/25/15) c. Cover Sheet d. Legend Sheet e. Existing Conditions f. Preliminary Plat g. Preliminary Site Plan h. Preliminary Utility Plan i. Preliminary Grading Plan j. Erosion Control Plan k. Preliminary Seeding Plan l. Preliminary Street Profiles m. Details n. Landscape Plan o. Tree Preservation Plan CITY OF LAKE ELMO WASHINGTON COUNTY, MINNESOTA RESOLUTION NO. 2015-056 A RESOLUTION APPROVING A PRELIMINARY PLAT FOR THE LENNAR DIEDRICH TOWNHOUSES WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing under the laws of the State of Minnesota; and WHEREAS, Lennar Corporation, 16305 36th Avenue North, Plymouth, MN (Applicant) has submitted an application to the City of Lake Elmo (City) for a Preliminary Plat for the Lennar Diedrich Townhouses subdivision, a copy of which is on file in the City of Lake Elmo Community Development Department; and WHEREAS, the Lake Elmo Planning Commission held public hearing on June 22, 2015 to consider the Preliminary Plat request; and WHEREAS, the Lake Elmo Planning Commission has submitted its report and recommendation concerning the Preliminary Plat as part of a memorandum to the City Council from Community Development Director Kyle Klatt for the July 7, 2015 Council Meeting; and WHEREAS, the Lake Elmo Planning Commission adopted a motion recommending approval of the Preliminary Plat; and WHEREAS, the City Council reviewed the Preliminary Plat at its meeting held on July 7, 2014 and made the following findings of fact: 1) That the preliminary plat is consistent with the Lake Elmo Comprehensive Plan and the Future Land Use Map for this area. 2) That the preliminary plat complies with the City’s Urban Medium Density Residential zoning district regulations. 3) That the preliminary plat complies with all other applicable zoning requirements, including the City’s landscaping, storm water, sediment and erosion control and other ordinances with the plan revisions as requested by City Staff and consultants. 4) That the preliminary plat complies with the City’s subdivision ordinance. 5) That the preliminary plat is consistent with the City’s engineering standards provided the plans are updated to address the City Engineer’s comments documented in a letter dated June 17, 2014. 6) That there are no City parks located within ½ mile of the proposed subdivision. 7) That the updated development plans indicate that proposed structures on Lots 29-32 are located too close to the property line and that the development plans must be updated to move these structures to the required setbacks prior to the submission of a final plat. NOW, THEREFORE, BE IT RESOLVED THAT the City Council does hereby approve the preliminary plat for the Lennar Diedrich Townhouses subdivision subject to the following conditions: 1) The landscape plan and tree preservation plan shall be reviewed and approved by an independent forester or landscape architect in advance of the approval of a final plat and final construction plans. 2) The final landscape plan shall incorporate additional plantings where feasible adjacent to the shared property lines with parcel at 11490 Hudson Boulevard. 3) The applicant shall be responsible for updating the final construction plans to include the construction of all improvements within the Lake Elmo Avenue (CSAH 17) right-of-way as required by Washington County and further described in the review letter received from the County dated March 3, 2015. The required improvements shall include, but not be limited to the construction of a northbound right turn lane and southbound center turn lane. 4) The developer shall follow all of the rules and regulations spelled out in the Wetland Conservation Act, and shall acquire the needed permits from the Valley Branch Watershed District prior to the commencement of any grading or development activity on the site. 5) The applicant shall enter into a maintenance agreement with the City that clarifies the individuals or entities responsible for any landscaping installed in areas outside of land dedicated as public park and open space on the final plat. 6) The developer shall be required to pay a fee in lieu of park land dedication equivalent to the fair market value for the amount of land that is required to be dedicated for such purposes in the City’s Subdivision Ordinance. A cash payment in lieu of land dedication shall be paid by the applicant prior to the release of the final plat for recording. 7) The applicant must enter into a separate grading agreement with the City prior to the commencement of any grading activity in advance of final plat and plan approval. The City Engineer shall review any grading plan that is submitted in advance of a final plat, and said plan shall document extent of any proposed grading on the site. 8) All required modifications to the plans as requested by the City Engineer in a review letter dated June 17, 2015 shall be incorporated into the plans prior to consideration of a final plat. 9) The applicant shall update all of the landscaping and construction plans to reflect the updated site plan that includes a public right-of-way within the project area. These updated plan shall be subject to review and approval by the City Engineer. 10) Although the updated site plan does not incorporate a private street, any request for flexibility from City regulations and standards must be considered and addressed as part of the final plat submission. 11) The final construction plans for the Diedrich Townhouses subdivision shall include, at a minimum, the northern portion of 5th Street if a joint construction project between the applicant and Ryland Homes does not proceed in advance of a final plat submission for the applicant’s site. 12) The architectural covenants for the homeowner’s association shall include provisions that discourage blank garage doors. All garage doors shall incorporate windows or decorative trim to minimize the visual impact of the garage-forward home design. 13) Prior to recording the Final Plat for any portion of the area shown in the Preliminary Plat, the Developer shall enter into a Developers Agreement acceptable to the City Attorney that delineates who is responsible for the design, construction, and payment of public improvements. 14) The site plan and construction plans shall be revised to include a sidewalk along at least one side of all streets within the subdivision. 15) The applicant shall pay a Water Availability Charge consistent with the Lake Elmo Fee Schedule for the entire development prior to the release of the final plat for recording, regardless of project phasing. 16) The developer shall secure a written grading agreement from Excel Energy concerning the proposed grading activity underneath an existing power line easement across the property prior to submission of a final plat. Passed and duly adopted this 21st day of July 2015 by the City Council of the City of Lake Elmo, Minnesota. ___________________________________ Mike Pearson, Mayor ATTEST: ____________________________________ Julie Johnson, City Clerk