HomeMy WebLinkAbout#15 -Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
2016 STREET, DRAINAGE AND UTILITY IMPROVEMENTS
PROJECT NO. 2015.129
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
FEBRUARY 2016
August 4, 2015 Council authorizes Feasibility Report.
October 6, 2015 Presentation of Feasibility Report. Council accepts Report and calls Hearing.
November 4, 2015 Public Improvement Hearing. Council orders preparation of Plans and Specifications.
February 16, 2016 Council approves Plans and Specifications and orders Advertisement for Bids.
March 17, 2016 Receive Contractor Bids.
April 5, 2016 Council accepts Bids and awards Contract.
May 2, 2016 Conduct Pre-Construction Meeting and issue Notice to Proceed.
August 12, 2016 Substantial Completion.
September 30, 2016 Final Completion.