HomeMy WebLinkAbout4-Inwood Water Tower 4-Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
INWOOD WATER TOWER (NO. 4)
PROJECT NO. 2015.130
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
JANUARY 2016
October 6, 2015 Council approves consultant selection.
November 17, 2015 Preliminary Design. Council accepts preliminary design recommendations (water
tower style, materials, and site plan).
January 19, 2016 Council approves Plans and Specifications and orders Advertisement for Bids.
February 18, 2016 Receive Contractor Bids.
March 15, 2016 Council accepts Bids and awards Contract.
April 7, 2016 Conduct Pre-construction meeting and issue Notice to Proceed.
October 1, 2017 Substantial Completion (water tower online and operational).
November 3, 2017 Final Completion (punch list and final paperwork).