HomeMy WebLinkAbout#13-Inwood Booster Station - Accept Bids Award Contract AGENDA MAYOR & COUNCIL COMMUNICATION -- page 1 -- DATE: April 5, 2016 REGULAR ITEM # 13 AGENDA ITEM: Inwood Water Booster Station Improvements – Accept Bids and Award Contract SUBMITTED BY: Chad Isakson, Project Engineer THROUGH: Kristina Handt, City Administrator REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director Mike Bouthilet, Public Works SUGGESTED ORDER OF BUSINESS: - Introduction of Item .................................................................................. City Engineer - Report/Presentation .................................................................................. City Engineer - Questions from Council to Staff ......................................................... Mayor Facilitates - Public Input, if Appropriate .............................................................. Mayor Facilitates - Call for Motion ............................................................... Mayor & City Council - Discussion ....................................................................... Mayor & City Council - Action on Motion .................................................................... Mayor Facilitates POLICY RECOMMENDER: Engineering. FISCAL IMPACT: $1,308,404. Approval of this resolution commits the council to enter into a construction contract for the project with a construction contract amount of $1,308,404. The improvement will be funded through a combination of the city’s water enterprise fund, bonding, and DEED Grant funds. SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to consider accepting contractor bids and awarding a contract for the Inwood Water Booster Station Improvements. LEGISLATIVE HISTORY/BACKGROUND INFORMATION: The City Council approved the Plans and Specifications for the Inwood Water Booster Station on January 19, 2016 and authorized staff to advertise the Project for bids. The Project was advertised on QuestCDN.com and in the Oakdale-Lake Elmo Review in accordance with the Minnesota Competitive City Council Meeting [Regular Agenda Item 13] April 5, 2016 -- page 2 -- Bidding requirements. The improvements include a building structure approximately 40-feet by 28-feet to house pumps, discharge piping, electrical equipment, and chemical feed equipment. The building environment is humid and corrosive due to chemicals, so the general building structure will be a slab on grade with masonry load bearing walls and a protective/water resistant coated ceiling. Bids were received, publicly opened, and read aloud on March 3, 2016. The City’s design consultant has prepared and attached the letter of recommendation for the award of the contract together with the Tabulation of Bids. The City received 3 bids for this project, with Magney Construction, Inc. providing the lowest base bid in the amount of $1,308,404. Contractor references for Magney Construction, Inc. were reviewed and verified. The City Engineer and the design consultant are therefore recommending that the Council award the contract to the lowest responsible bidder, Magney Construction, Inc., as outlined in the attached letter. An alternate bid was taken to install a smaller standby generator that would only run one of the two pumps in the event of a power outage. Based on the savings offered for the smaller generator, Staff’s recommendation is to award the contract based on the base bid to maintain the ability for the generator to run both pumps and provide additional flow capacity for fire protection services during a power outage. The project construction costs are higher than previously presented to council due to the need to include automated chlorination sampling and feed equipment along with the building addition necessary to house this added equipment. During the design phase of the project, the additional equipment was found to be required to maintain proper residual chlorine within the system. Following the receipt of bids on March 3rd, staff delayed the project award recommendation to review the project with public works, the design consultant and the Minnesota Department of Health to verify the operational needs, design assumptions and to review opportunities to reduce costs. With the operational needs verified through the MDH and Public Works the project is being recommended to be awarded per the Base Bid. RECOMMENDATION: Staff is recommending that the City Council approve Resolution No. 2016-23, thereby accepting bids and awarding a contract to Magney Construction, Inc., for the Base Bid in the amount of $1,308,404 for the Inwood Water Booster Station Improvements. The recommended motion for this action is as follows: “Move to approve Resolution No. 2016-23, Accepting Bids and Awarding a Contract to Magney Construction, Inc. for the Base Bid in the amount of $1,308,404 for the Inwood Water Booster Station Improvements.” ATTACHMENT(S): 1. Resolution 2016-23 Accepting Bids and Awarding a Contract. 2. Engineer’s Letter of Award Recommendation and Tabulation of Bids. 3. Project Schedule. Resolution No. 2016-23 1 CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2016-23 A RESOLUTION ACCEPTING BIDS AND AWARDING A CONTRACT FOR THE INWOOD WATER BOOSTER STATION IMPROVEMENTS WHEREAS, pursuant to an advertisement for bids for the Inwood Water Booster Station, bids were received, opened, and tabulated according to law, and bids were received complying with the advertisement; and WHEREAS, bids were tabulated, checked and summarized to verify that all requirements of the submittals were met; and WHEREAS, the project engineer reviewed the bids and has provided a letter recommending the award of the contract to the lowest responsible bidder, Magney Construction, Inc. in the amount of $1,308,404. NOW, THEREFORE, IT IS HEREBY RESOLVED, 1. The Mayor and City Clerk are hereby authorized and directed to enter into a Contract in accordance with the above ordered Project, in the amount of the Contractor’s lowest responsible bid, and according to the plans and specifications thereof approved by the City Council. 2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits made with their bids, except that the deposits of the successful bidder and the next two lowest bidders shall be retained until a contract has been signed. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE FIFTH DAY OF APRIL 2016. CITY OF LAKE ELMO By: __________________________ Mike Pearson Mayor (Seal) ATTEST: ________________________________ Julie Johnson City Clerk BID TABULATIONPROJECT: Inwood Water Booster StationPROJECT NUMBER: 09880003OWNER: City of Lake ElmoBID DATE: March 3, 2016ITEM ITEM ESTIMATED UNIT TOTAL UNIT TOTAL UNIT TOTALNO. DESCRIPTION QUANTITY UNITS PRICE PRICE PRICE PRICE PRICE PRICEBASE BIDDIVISION 1 - GENERAL1. MOBILIZATION 1 LS 55,000.00$ 55,000.00$ 65,000.00$ 65,000.00$ 45,000.00$ 45,000.00$ 2. TRAFFIC CONTROL 1 LS 700.00$ 700.00$ 1,500.00$ 1,500.00$ 1,000.00$ 1,000.00$ 3. SILT FENCE 240 LF 3.00$ 720.00$ 5.00$ 1,200.00$ 3.00$ 720.00$ 4. CLEARING AND GRUBBING 1 LS 2,000.00$ 2,000.00$ 2,000.00$ 2,000.00$ 2,500.00$ 2,500.00$ 5. TEMPORARY ROCK CONSTRUCTION ENTRANCE 1 EA 1,000.00$ 1,000.00$ 2,000.00$ 2,000.00$ 900.00$ 900.00$ 6. STREET SWEEPING 10 HR105.00$ 1,050.00$ 150.00$ 1,500.00$ 115.00$ 1,150.00$ 7. SITE RESTORATION 1 LS 4,800.00$ 4,800.00$ 2,500.00$ 2,500.00$ 6,750.00$ 6,750.00$ DIVISION 2 - WATER MAIN8. CONNECT TO EXISTING WATERMAIN AND SERVICE 3 EA 1,500.00$ 4,500.00$ 1,200.00$ 3,600.00$ 1,450.00$ 4,350.00$ 9. 1.5" COPPER WATER SERVICE PIPE 65 LF 50.00$ 3,250.00$ 48.00$ 3,120.00$ 45.75$ 2,973.75$ 10. 12" DUCTILE IRON WATERMAIN PIPE, CLASS 52 100 LF 120.00$ 12,000.00$ 86.00$ 8,600.00$ 107.25$ 10,725.00$ 11. DUCTILE IRON FITTINGS 344 LB 16.00$ 5,504.00$ 6.00$ 2,064.00$ 15.00$ 5,160.00$ DIVISION 3 - STORM SEWER12. 10" PVC DRAIN 15 LF 50.00$ 750.00$ 32.00$ 480.00$ 45.50$ 682.50$ 13. 18" RCP STORM SEWER PIPE, CLASS 5 130 LF 50.00$ 6,500.00$ 49.00$ 6,370.00$ 44.50$ 5,785.00$ 14. 18" RCP FLARED END SECTION 1 EA 1,500.00$ 1,500.00$ 1,250.00$ 1,250.00$ 1,060.00$ 1,060.00$ 15. CATCH BASIN/MANHOLE 2 EA 3,000.00$ 6,000.00$ 2,800.00$ 5,600.00$ 2,900.00$ 5,800.00$ 16. RANDOM RIPRAP CLASS III (CV) 10 CY160.00$ 1,600.00$ 90.00$ 900.00$ 155.00$ 1,550.00$ DIVISION 4 - DRIVEWAY CONSTRUCTION17. COMMON EXCAVATION (P) 690 CY 20.00$ 13,800.00$ 6.00$ 4,140.00$ 26.55$ 18,319.50$ 18. SELECT GRANULAR BORROW (P) 110 CY 25.00$ 2,750.00$ 15.00$ 1,650.00$ 25.00$ 2,750.00$ 19. SUBGRADE PREPARATION 1 LS 1,400.00$ 1,400.00$ 500.00$ 500.00$ 1,255.00$ 1,255.00$ 20. AGGREGATE BASE CLASS 5 140 TON 22.00$ 3,080.00$ 32.00$ 4,480.00$ 19.20$ 2,688.00$ 21. TYPE SP 9.5 WEAR COURSE MIX (2,B) 50 TON 95.00$ 4,750.00$ 100.00$ 5,000.00$ 87.00$ 4,350.00$ 22. 4" CONCRETE SIDEWALK 41 SY 70.00$ 2,870.00$ 55.00$ 2,255.00$ 31.00$ 1,271.00$ 23. SEGMENTAL RETAINING WALL 480 FF 23.00$ 11,040.00$ 20.00$ 9,600.00$ 27.00$ 12,960.00$ 24. SPLIT RAIL FENCE 120 LF 17.00$ 2,040.00$ 15.00$ 1,800.00$ 14.00$ 1,680.00$ 25. GUARD POST 3 EA 350.00$ 1,050.00$ 300.00$ 900.00$ 450.00$ 1,350.00$ 26. 6" PERFORATED PVC DRAIN 140 LF 40.00$ 5,600.00$ 20.00$ 2,800.00$ 35.40$ 4,956.00$ 27. 8" INLINE DRAIN 5 EA 900.00$ 4,500.00$ 560.00$ 2,800.00$ 750.00$ 3,750.00$ 28. ROOF DRAIN CONNECTION 5 EA 900.00$ 4,500.00$ 525.00$ 2,625.00$ 750.00$ 3,750.00$ 29. DRAINTILE CLEANOUT 1 EA 900.00$ 900.00$ 450.00$ 450.00$ 775.00$ 775.00$ DIVISION 5 - BOOSTER FACILITY30. BOOSTER FACILITY (COMPLETE) 1 LS762,000.00$ 762,000.00$ 860,541.00$ 860,541.00$ 908,534.25$ 908,534.25$ 31. SCADA INTEGRATION AND SYSTEM IMPROVEMENTS (SCADA CONTRACTOR) ALLOWANCE1 LS 30,000.00$ 30,000.00$ 30,000.00$ 30,000.00$ 30,000.00$ 30,000.00$ 32.PROCESS INSTRUMENTATION AND CONTROL (SYSTEM INTEGRATOR)1 LS 215,000.00$ 215,000.00$ 210,000.00$ 210,000.00$ 209,817.00$ 209,817.00$ 33. 230 KW GENERATOR SET 1 LS 105,000.00$ 105,000.00$ 101,000.00$ 101,000.00$ 100,248.00$ 100,248.00$ 34. UTILITY ALLOWANCE (ELECTRIC, NATURAL GAS, TELECOMMUNICATION/DATA)1 LS 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 35. HOLDING TANK AND ASSOCIATED PIPING 1 LS 20,000.00$ 20,000.00$ 23,000.00$ 23,000.00$ 15,860.00$ 15,860.00$ 36. EROSION CONTROL BLANKET 625 SY 2.00$ 1,250.00$ 3.00$ 1,875.00$ 1.00$ 625.00$ TOTAL ESTIMATED CONSTRUCTION COST 1,308,404.00$ 1,383,100.00$ 1,431,045.00$ ALTERNATE A - 150 KW PORTABLE GENERATOR33A.150 KW GENERATOR SET (DEDUCT)1 LS (30,000.00)$ (30,000.00)$ (28,000.00)$ (28,000.00)$ (29,286.00)$ (29,286.00)$ Municipal Builders, Inc.Andover, MNMagney Construction, Inc. Rice Lake Construction GroupChanhassen, MN Deerwood, MNFor updated bidding information visit us at www.msa-ps.com1 of 109880003 Bid Form 022616TABULATION PROJECT SCHEDULE  CITY OF LAKE ELMO    INWOOD BOOSTER STATION  PROJECT NO. 2014.129  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.  651.300.4261 Jack Griffin, P.E.               651.300.4264  Ryan Stempski, P.E. 651.300.4267  Chad Isakson, P.E. 651.300.4283  MARCH 2016                January 21, 2014 Council Orders the Improvement for the Inwood Booster Station and the preparation  of Plans and Specifications.     Project was delayed due to delay in receipt of MN‐DEED Water System Grant.     February 2, 2016 Council approves Plans and Specifications and orders Advertisement for Bids.    March 3, 2016  Receive Contractor Bids.    April 5, 2016  Council accepts Bids and awards Contract.    April 24, 2016  Conduct Pre‐construction meeting and issue Notice to Proceed.    October 31, 2016 Substantial Completion (booster station online and operational).    January 15, 2017 Final Completion (punch list and final paperwork).