HomeMy WebLinkAboutBoulder Ponds 2nd Add Dev Agreement 5.9.16REV2: 04/18/2016 1
(reserved for recording information)
DEVELOPMENT CONTRACT
(Public sewer and water) Boulder Ponds 2nd Addition
AGREEMENT dated , 2016, by and between the CITY OF LAKE
ELMO a Minnesota municipal corporation (“City”), and OP4 Boulder Ponds (the “Developer”).
1. REQUEST FOR PLAT APPROVAL. The Developer has asked the City to approve a
plat for Boulder Ponds 2nd Addition (referred to in this Contract as the “plat”). The land is situated in the
County of Washington, State of Minnesota, and is legally described on Exhibit A
2. CONDITIONS OF PLAT APPROVAL. The City hereby approves the plat on condition
that the Developer enter into this Contract, furnish the security required by it, and record the plat with the
County Recorder or Registrar of Titles within (180) days after the City Council approves the final plat.
3. RIGHT TO PROCEED. Unless separate written approval has been given by the City,
within the plat or land to be platted, the Developer may not grade or otherwise disturb the earth, remove
trees, construct sewer lines, water lines, streets, utilities, public or private improvements, or any buildings
until all the following conditions have been satisfied: 1) this agreement has been fully executed by both
REV2: 04/18/2016 2
parties and filed with the City Clerk, 2) the necessary security has been received by the City, 3) the plat has
been recorded with the Washington County Recorder's Office, and 4) the City’s Planning Director has
issued a letter that all conditions have been satisfied, a preconstruction conference has been held, and that
the Developer may proceed.
4. PHASED DEVELOPMENT. If the plat is a phase of a multi-phased preliminary plat, the
City may refuse to approve final plats of subsequent phases if the Developer has breached this Contract
and the breach has not been remedied. Development of subsequent phases may not proceed until
Development Contracts for such phases are approved by the City. Park charges and availability
charges for sewer and water referred to in this Contract are not being imposed on outlots, if any, in the
plat that are designated in an approved preliminary plat for future subdivision into lots and blocks. Such
charges will be calculated and imposed when the outlots are final platted into lots and blocks.
5. PRELIMINARY PLAT STATUS. If the plat is a phase of a multi-phased preliminary plat,
the preliminary plat approval for all phases not final platted shall lapse and be void unless final platted into
lots and blocks, not outlots, within five (5) years after preliminary plat approval.
6. CHANGES IN OFFICIAL CONTROLS. For two (2) years from the date of this
Contract, no amendments to the City's Comprehensive Plan or official controls shall apply to or affect the
use, development density, lot size, lot layout or dedications of the approved final plat unless required by
state or federal law or agreed to in writing by the City and the Developer. Thereafter, notwithstanding
anything in this Contract to the contrary, to the full extent permitted by state law, the City may require
compliance with any amendments to the City's Comprehensive Plan, official controls, platting or dedication
requirements enacted after the date of this Contract.
7. DEVELOPMENT PLANS. The plat shall be developed in accordance with the following
plans and at the Developer’s sole expense. The plans shall not be attached to this Contract. If the plans
vary from the written terms of this Contract, the written terms shall control. The plans are:
Plan A - Plat Plan B - Final Grading, Drainage, and Erosion Control Plan
REV2: 04/18/2016 3
Plan C - Tree Preservation and Reforestation Plan Plan D - Plans and Specifications for Public Improvements
Plan E - Street Lighting Plan
Plan F - Landscape Plan 8. IMPROVEMENTS. The Developer shall install and pay for the following: A. Streets B. Sanitary Sewer C. Watermain D. Surface Water Facilities (pipe, ponds, rain gardens, etc.) E. Grading and Erosion Control F. Sidewalks/Trails G. Street Lighting H. Underground Utilities I. Street Signs and Traffic Control Signs J. Landscaping
K. Tree Preservation and Reforestation
L. Wetland Mitigation and Buffers
M. Monuments Required by Minnesota Statutes
N. Miscellaneous Facilities The improvements shall be installed in accordance with the City subdivision ordinance and the City’s
Engineering Design and Construction Standards Manual and pursuant to the direction of the City Engineer.
The Developer shall submit plans and specifications which have been prepared by a competent registered
professional engineer to the City for approval by the City Engineer. The Developer shall instruct its
engineer to provide adequate field inspection personnel to assure an acceptable level of quality control to
the extent that the Developer's engineer will be able to certify that the construction work meets the
approved City standards as a condition of City acceptance. In addition, the City may, at the City's discretion
and at the Developer's expense, have one or more City inspectors and a soil engineer inspect the work on
a full or part-time basis. The Developer's engineer shall provide for on-site project management. The
Developer's engineer is responsible for design changes and contract administration between the Developer
REV2: 04/18/2016 4
and the Developer's contractor. The Developer or his engineer shall schedule a pre-construction meeting
at a mutually agreeable time at the City Hall with all parties concerned, including the City staff, to review the
program for the construction work.
All labor and work shall be done and performed in the best and most workmanlike manner and in
strict conformance with the approved plans and specifications. No deviations from the approved plans and
specifications will be permitted unless approved in writing by the City Engineer. The Developer agrees to
furnish to the City a list of contractors being considered for retention by the Developer for the performance
of the work required by the Contract. The Developer shall not do any work or furnish any materials not
covered by the plans and specifications and special conditions of this Contract, for which reimbursement is
expected from the City, unless such work is first ordered in writing by the City Engineer as provided in the
specifications.
9. CITY ENGINEERING ADMINISTRATION AND CONSTRUCTION OBSERVATION. At the time of Final Plat, the Developer shall submit an escrow for City Engineering
Administration and Construction Observation in an amount provided under paragraph 34. Summary of
Cash Requirements. Thereafter, the Developer shall reimburse the City each month, within 30 days of
receiving an invoice, for all engineering administration and construction observation performed during the
construction of the plat After 30 days of the invoice, the City may draw upon the escrow and stop the work
on site until said escrow has been replenished in its full amount. City engineering administration will include
monitoring of construction progress and construction observation, consultation with the Developer
and his engineer on status or problems regarding the project, coordination for testing, final inspection and
acceptance, project monitoring during the warranty period, and processing of requests for reduction in
security. Construction observation may be performed by the City's in-house staff or consulting engineer.
Construction observation shall include, at the discretion of the city, part or full time inspection of proposed
public utilities and street construction. Services will be billed on an hourly basis.
REV2: 04/18/2016 5
The direction and review provided through the inspection of the improvements should not be
considered a substitute for the Developer required management of the development. The Developer will
cause the contractor(s) to furnish the City with a schedule of proposed operations at least five (5) days prior
to the commencement of construction of each type of Improvement. City shall inspect all Developer
Installed Improvements during and after construction for compliance with approved plans and
specifications. The Developer will notify the City Engineer at such times during construction as the City
Engineer requires for inspection purposes. Such inspection is pursuant to the City’s governmental
authority, and no agency or joint venture relationship between the City and the Developer is thereby
created.
10. CONTRACTORS/SUBCONTRACTORS. City Council members, City employees, and
City Planning Commission members, and corporations, partnerships, and other entities in which such
individuals have greater than a 25% ownership interest or in which they are an officer or director may not
act as contractors or subcontractors for the public improvements identified in Paragraph 8 above.
11. PERMITS. The Developer shall obtain or require its contractors and subcontractors to
obtain all necessary permits, including but not limited to:
A. Right-of-Way Excavations and Obstructions: • City of Lake Elmo, Right-of-Way Utility Installation(s)
• City of Lake Elmo, Right-of-Way Obstruction(s)
• Washington County, Utility Installations(s)
• Washington County, Street or Driveway Access(s)
• Minnesota Department of Transportation, Utility Installation
• Minnesota Department of Transportation, Right-of-Way Permit
B. Watermain Extensions:
• Minnesota Department of Health C. Sanitary Sewer Extensions:
• Minnesota Pollution Control Agency
• Metropolitan Council Environmental Services D. Stormwater Management:
• Valley Branch, Brown’s Creek or South Washington Watershed District Permit E. Erosion, Sedimentation Control:
• Minnesota Pollution Control Agency, General NPDES Stormwater Permit
• SWPPP (Stormwater Pollution Prevention Plan)
REV2: 04/18/2016 6
F. Wetland Mitigation:
• Board of Water and Soil Resources, WCA G. Construction Dewatering:
• Minnesota Department of Natural Resources 12. TIME OF PERFORMANCE. The Developer shall install all required public
improvements by October 31, 2017, with the exception of the final wear course of asphalt on streets.
The Developer shall install the bituminous wearing course of streets after the first course has weathered a
winter season, consistent with warranty requirements, however final acceptance of the improvements
will not be granted until all work is completed including the final wear course. The Developer may,
however, request an extension of time from the City. If an extension is granted, it shall be conditioned upon
updating the security posted by the Developer to reflect cost increases and amending this agreement to
reflect the extended completion date. Final wear course placement outside of this time frame must have
the written approval of the City Engineer.
13. LICENSE. The Developer hereby grants the City, its agents, employees, officers and
contractors a license to enter the plat to perform all work and inspections deemed appropriate by the City in
conjunction with plat development.
14. CONSTRUCTION ACCESS. Construction traffic access and egress for grading, public
utility construction, and street construction is restricted to access the subdivision via
Hudson Boulevard and Jade Trail North. No construction traffic is permitted on other adjacent local
streets.
15. CONSTRUCTION SEQUENCE AND COMPLIANCE. The City will require the
Developer to construct the improvements in a sequence which will allow progress and compliance points
to be measured and evaluated. The Developer and/or their representatives are required to supervise
and coordinate all construction activities for all improvements and must notify the City in writing stating
when the work is ready for the inspection at each of the measurable points defined in the following
paragraphs 16, 17 and 18.
16. EROSION CONTROL. Prior to initiating site grading, the erosion control plan, Plan B,
REV2: 04/18/2016 7
shall be implemented by the Developer and inspected and approved by the City. Erosion control practices
must comply with the approved plans and specifications for the plat, with all watershed district permits and
with Minnesota Pollution Control Agency’s Best Management Practices. The City may impose additional
erosion control requirements as deemed necessary. The parties recognize that time is of the essence in
controlling erosion. If the Developer does not comply with the erosion control plan and schedule or
supplementary instructions received from the City, the City may take such action as it deems appropriate to
control erosion. The City will endeavor to notify the Developer in advance of any proposed action, but
failure of the City to do so will not affect the Developer's and City's rights or obligations hereunder. If the
Developer does not reimburse the City for any cost the City incurred for such work within ten (10) days
after submitting an invoice for such costs, the City may draw down the security to pay any costs. No
development, utility or street construction will be allowed and no building permits will be issued unless
the plat is in full compliance with the approved erosion control plan.
If building permits are issued prior to the acceptance of public improvements, the Developer
assumes all responsibility for erosion control compliance throughout the plat and the City may take such
action as allowed by this agreement against the Developer for any noncompliant issue as stated above.
Erosion control plans for individual lots will be required in accordance with the City’s building permit
requirements, or as required by the City or City Engineer.
17. GRADING PLAN. The plat shall be graded in accordance with the approved grading
drainage and erosion control plan, Plan "B". The plan shall conform to the Engineering Design and
Construction Standards Manual. All grading shall be completed within the Subdivision prior to the
preparation and submittal of the as-constructed grading plan.
A. Within thirty (30) days after completion of the grading, the Developer shall provide
the City with a "record" grading plan certified by a registered land surveyor or engineer that all ponds,
swales, and ditches have been constructed on public easements or land owned by the City. The "record"
plan shall contain site grades and field verified elevations of the following: a) cross sections of ponds; b)
location and elevations along all swales, emergency overflows, wetlands, wetland mitigation areas if any,
REV2: 04/18/2016 8
ditches, locations and dimensions of borrow areas/stockpiles; c) lot corner elevations and house pads;
and d) top and bottom of retaining walls.
B. The City will not issue any building permits until the approved certified record
grading plan is on file with the City.
18. STREET AND UTILITY IMPROVEMENTS. All storm sewers, sanitary sewers, watermain,
and streets shall be installed in accordance with the approved Plans and Specifications for Public
Improvements, Plan "D". The plan shall conform to the City’s Engineering Design and Construction
Standards Manual. Curb and gutter and the first lift of the bituminous streets, sidewalks, boulevards
graded, street signs installed, and all restoration work on the site shall be completed in accordance with the
approved plans. Once the work is completed, the developer or its representative shall submit a written
request to the City asking for an inspection of the initial improvements. The City will then schedule a walk-
through to create a punch list of outstanding items to be completed. Upon receipt of the written punch list
provided by the City, the punch list items must be completed by the Developer and the City notified to re-
inspect the improvements. The final bituminous wear course shall be installed in accordance with
paragraph 12 above.
19. STREET MAINTENANCE DURING CONSTRUCTION. The Developer shall be
responsible for all street maintenance until the streets are accepted by the City in writing. Warning signs
shall be placed when hazards develop in streets to prevent the public from traveling on same and to direct
attention to detours. If and when streets become impassable, such streets shall be barricaded and closed.
In the event residences are occupied prior to completing streets, the Developer shall maintain a smooth
surface and provide proper surface drainage to insure that the streets are passable to traffic and emergency
vehicles. The Developer shall be responsible for keeping streets within and without the subdivision clean of
dirt and debris that may spill, track, or wash onto the street from the Developer’s operation. The Developer
may request, in writing, that the City keep the streets open during the winter months by plowing snow from
the streets prior to final acceptance of said streets. The City shall not be responsible for repairing the streets
because of snow plowing operations. Providing snow plowing service does not constitute final acceptance of
REV2: 04/18/2016 9
the streets by the City. The Developer shall contract for street cleaning within and immediately adjacent to
the development. At a minimum, scraping and sweeping shall take place on a weekly basis. A copy of this
contract shall be approved by the City before grading is started. The contract shall provide that the City may
direct the contractor to clean the streets and the contractor will bill the Developer.
20. OWNERSHIP OF IMPROVEMENTS. Upon completion of the work and construction
required by this Contract, the improvements lying within public easements shall become City property.
Prior to acceptance of the improvements by the City, the Developer must furnish the City with a complete
set of reproducible "record" plans, an electronic file of the "record" plans in accordance with the City’s
Engineering Design and Construction Standards Manual together with the following affidavits:
- Developer/Developer Engineer’s Certificate - Land Surveyor’s Certificate certifying that all construction has been completed in accordance with the terms of this Contract. All
necessary forms will be furnished by the City. Upon receipt of “record plans” and affidavits, and upon
review and verification by the City Engineer, the City Engineer will accept the completed public
improvements.
21. PARK DEDICATION. The Developer shall dedicate 1.77 acres of park land
comprised of that the portion of the northern greenbelt park not within the Xcel Energy easement with the
third phase of the development. Fees in lieu of land dedication was paid as part of the Boulder Ponds
Development Contract.
22. SANITARY SEWER AND WATER UTILITY AVAILABILITY CHARGES (SAC AND WAC). The Developer shall be responsible for the payment of all sewer availability charges (SAC)
and all water availability charges (WAC) with respect to the Improvements required by the City and any
state or metropolitan government agency.
The sewer availability charge (SAC) in the amount of $3,000.00 per REU shall be paid by the
Developer prior to the City recording the final plat. The total amount to be paid by the Developer is
$54,000.00.
REV2: 04/18/2016 10
The water availability charge (WAC) in the amount of $3,000.00 per REU shall be paid by the
Developer prior to the City recording the final plat. The total amount to be paid by the Developer is
$54,000.00.
In addition, a sewer connection charge in the amount of $1,000.00 per REU, a Met Council sewer
availability charge in the amount of $2,485.00 per REU, and a water connection charge in the amount of
$1,000.00 per REU will be collected by the City at the time the building permit is issued for each lot. 23. TRAFFIC CONTROL SIGNS. The Developer is responsible for the cost of for
the installation of traffic control signs. The traffic control signs shall be installed in accordance with the City
subdivision ordinance and the City’s Engineering Design and Construction Standards Manual and pursuant
to the direction of the City Engineer.
24. STREET LIGHTS. The Developer is responsible for the cost of street light installation
consistent with a street lighting plan approved by the City. Before the City signs the final plat, the
Developer shall post a security for street light installation consistent with the approved plan. The
required security is $12,000 and consist of one (2) decorative lights at $6000 each. The Developer shall
also pay $258 in payment of the first year operating costs for street lights.
25. WETLAND MITIGATION. The Developer shall complete wetland mitigation/restoration
in accordance with the approved Plans and Specifications and in accordance with any applicable
Watershed or agency Permits. If the mitigation work is found to be incomplete or restoration is
unsuccessful the City may draw down the security at any time during the warranty period if the Developer
fails to take corrective measures to be used by the City to perform the work.
26. BUILDING PERMITS/CERTIFICATES OF OCCUPANCY.
A. Public sewer and water, curbing, and one lift of asphalt shall be installed on all
public and private streets prior to issuance of any building permits, except one model home on a lot
acceptable to the Planning Director.
B. Prior to issuance of building permits, wetland buffer monuments shall be placed in
accordance with the City’s zoning ordinance. The monument design shall be approved by the
REV2: 04/18/2016 11
Community Development Department.
C. Written certification of the as-constructed grading must be on file at the City for the
phase of the development.
D. Breach of the terms of this Contract by the Developer, including nonpayment of
billings from the City, shall be grounds for denial of building permits and/or withholding of other permits,
inspection or actions, including lots sold to third parties, and the halting of all work in the plat.
E. If building permits are issued prior to the acceptance of public improvements, the
Developer assumes all liability and costs resulting in delays in completion of public improvements and
damage to public improvements caused by the City, Developer, its contractors, subcontractors,
materialmen, employees, agents, or third parties.
F. No sewer and water connection permits may be issued until the streets needed for
access have been paved with a bituminous surface and the utilities are tested and approved by the City
Engineer.
G. The City will not issue a certificate of occupancy for any building constructed on
any lot or parcel in the Plat until Public sewer and water, curbing, and one lift of asphalt is installed on all
public and private streets; all utilities are tested and approved by the City Engineer; and the as-
constructed grading must be on file at the City for the phase of the development. This requirement does
not allow for the development to be phased for some lots.
27. RESPONSIBILITY FOR COSTS.
A. In the event that the City receives claims from labor, materialmen, or others that
work required by this Contract has been performed, the sums due them have not been paid, and the
laborers, materialmen, or others are seeking payment from the City, the Developer hereby authorizes the
City to commence an Interpleader action pursuant to Rule 22, Minnesota Rules of Civil Procedure for the
District Courts, to draw upon the letters of credit in an amount up to 125 percent of the claim(s) and deposit
the funds in compliance with the Rule, and upon such deposit, the Developer shall release, discharge, and
dismiss the City from any further proceedings as it pertains to the letters of credit deposited with the District
REV2: 04/18/2016 12
Court, except that the Court shall retain jurisdiction to determine attorneys' fees pursuant to this Contract.
B. Except as otherwise specified herein, the Developer shall pay all costs incurred by it
or the City in conjunction with the development of the plat, including but not limited to legal, planning,
engineering and inspection expenses incurred in connection with approval and acceptance of the plat, the
preparation of this Contract, review of construction plans and documents, and all costs and expenses
incurred by the City in monitoring and inspecting development of the plat. All amounts incurred and due at
the time, must be fully paid prior to execution and release of the final plat for recording.
C. The Developer shall hold the City and its officers, employees, and agents harmless
from claims made by itself and third parties for damages sustained or costs incurred resulting from plat
approval and development. The Developer shall indemnify the City and its officers, employees, and agents
for all costs, damages, or expenses which the City may pay or incur in consequence of such claims,
including attorneys' fees.
D. The Developer shall reimburse the City for costs incurred in the enforcement of this
Contract, including reasonable engineering and attorneys' fees.
E. The Developer shall pay, or cause to be paid when due, and in any event before any
penalty is attached, all special assessments referred to in this Contract. This is a personal obligation of the
Developer and shall continue in full force and effect even if the Developer sells one or more lots, the entire
plat, or any part of it.
F. The Developer shall pay in full all bills submitted to it by the City for obligations
incurred under this Contract within thirty (30) days after receipt. Bills not paid within thirty (30) days shall
be assessed a late fee per the City of Lake Elmo adopted Fee Schedule. Upon request, the City will
provide copies of detailed invoices of the work performed.
28. SPECIAL PROVISIONS. The following special provisions shall apply to
plat development:
A. Implementation of the recommendations listed in the April 21, 2016
Engineering memorandum.
REV2: 04/18/2016 13
B. The Developer must obtain a sign permit from the City Building Official prior to
installation of any subdivision identification signs.
C. The Developer shall enter into a landscape license agreement that identifies
required management of landscaping and individuals or entities responsible for any landscaping installed
in areas outside of land dedicated as public park and open space on the final plat.
29. MISCELLANEOUS. A. The Developer may not assign this Contract without the written permission of the
City Council. The Developer's obligation hereunder shall continue in full force and effect even if the
Developer sells one or more lots, the entire plat, or any part of it.
B. Retaining walls that require a building permit shall be constructed in accordance with
plans and specifications prepared by a structural or geotechnical engineer licensed by the State of
Minnesota. Following construction, a certification signed by the design engineer shall be filed with the City
Engineer evidencing that the retaining wall was constructed in accordance with the approved plans and
specifications. All retaining walls identified on the development plans or by special conditions referred to in
this Contract shall be constructed before any other building permit is issued for a lot on which a retaining
wall is required to be built.
C. Appropriate legal documents regarding Homeowner Association documents,
covenants and restrictions, as approved by the City Attorney, shall be filed with the final plat. No third-
party beneficiary is hereby conferred.
D. Developer shall take out and maintain or cause to be taken out and maintained until
six (6) months after the City has accepted the public improvements, public liability and property damage
insurance covering personal injury, including death, and claims for property damage which may arise out of
Developer's work or the work of its subcontractors or by one directly or indirectly employed by any of them.
Limits for bodily injury and death shall be not less than $500,000 for one person and $1,000,000 for each
occurrence; limits for property damage shall be not less than $200,000 for each occurrence; or a
combination single limit policy of $1,000,000 or more. The City shall be named as an additional insured on
REV2: 04/18/2016 14
the policy, and the Developer shall file with the City a certificate evidencing coverage prior to the City
signing the plat. The certificate shall provide that the City must be given thirty (30) days advance written
notice of the cancellation of the insurance.
E. Third parties shall have no recourse against the City under this Contract.
F. If any portion, section, subsection, sentence, clause, paragraph, or phrase of this
Contract is for any reason held invalid, such decision shall not affect the validity of the remaining portion of
this Contract.
G. The action or inaction of the City shall not constitute a waiver or amendment to the
provisions of this Contract. To be binding, amendments or waivers shall be in writing, signed by the parties
and approved by written resolution of the City Council. The City's failure to promptly take legal action to
enforce this Contract shall not be a waiver or release.
H. This Contract shall run with the land and may be recorded against the title to the
property. The Developer covenants with the City, its successors and assigns, that the Developer has fee
title to the property being final platted and/or has obtained consents to this Contract, in the form attached
hereto, from all parties who have an interest in the property; that there are no unrecorded interests in the
property being final platted; and that the Developer will indemnify and hold the City harmless for any
breach of the foregoing covenants.
I. Each right, power or remedy herein conferred upon the City is cumulative and in
addition to every other right, power or remedy, express or implied, now or hereafter arising, available to
City, at law or in equity, or under any other agreement, and each and every right, power and remedy herein
set forth or otherwise so existing may be exercised from time to time as often and in such order as may be
deemed expedient by the City and shall not be a waiver of the right to exercise at any time thereafter any
other right, power or remedy.
J. The Developer represents to the City that the plat complies with all city, county,
metropolitan, state, and federal laws and regulations, including but not limited to: subdivision ordinances,
zoning ordinances, and environmental regulations. If the City determines that the plat does not comply, the
City may, at its option, refuse to allow construction or development work in the plat until the Developer does
REV2: 04/18/2016 15
comply. Upon the City’s demand, the Developer shall cease work until there is compliance.
30. EVENTS OF DEFAULT. The following shall be "Events of Default" under this Agreement
and the term "Event of Default" shall mean, whenever it is used in this Agreement, any one or more of the
following events:
A. Subject to unavoidable delays, failure by the Developer to commence and
complete construction of the Public Improvements pursuant to the terms, conditions and limitations of this
Agreement.
B. Failure by the Developer to substantially observe or perform any material
covenant, condition, obligation or agreement on its part to be observed or performed under this Agreement.
31. REMEDIES ON DEFAULT. Whenever any Event of Default occurs, the City, subject to
any rights of third parties agreed to by the City pursuant to this Agreement, or otherwise by written, executed
instrument of the City, may take any one or more of the following:
A. The City may suspend its performance under the Agreement until it receives
assurances from the Developer, deemed adequate by the City, that Developer will cure its default and
continue their performance under the Agreement. Suspension of performance includes the right of the City
to withhold permits including, but not limited to, building permits.
B. The City may initiate such action, including legal or administrative action, as is
necessary for the City to secure performance of any provision of this agreement or recover any amounts
due under this Agreement from the Developer, or immediately draw on the Letter of Credit, as set forth in
this Agreement.
32. ENFORCEMENT BY CITY; DAMAGES. The Developer acknowledges the right of the
City to enforce the terms of this Agreement against the Developer, by action for specific performance or
damages, or both, or by any other legally authorized means. The Developer also acknowledges that its
failure to perform any or all of their obligations under this Agreement may result in substantial damages to
the City; that in the event of default by the Developer, the City may commence legal action to recover all
damages, losses and expenses sustained by the City; and that such expenses may include, but are not
REV2: 04/18/2016 16
limited to, the reasonable fees of legal counsel employed with respect to the enforcement of this Agreement.
33. WARRANTY. The Developer warrants all improvements required to be constructed by it
pursuant to this Contract against poor material and faulty workmanship. The Developer shall submit a
letter of credit for twenty-five percent (25%) of the amount of the original cost of the improvements.
A. The required warranty period for materials and workmanship for the utility contractor
installing public sewer and water mains shall be two (2) years from the date of final written City acceptance
of the work.
B. The required warranty period for all work relating to street construction, including
concrete curb and gutter, sidewalks and trails, materials and equipment shall be subject to one (1) year
from the date of final written acceptance, unless the wearing course is placed during the same construction
season as the bituminous base course. In those instances, the Developer shall guarantee all work,
including street construction, concrete curb and gutter, sidewalks and trails, material and equipment for a
period of two (2) years from the date of final written City acceptance of the work.
C. The required warranty period for sod, trees, and landscaping is two growing seasons
following installation.
34. SUMMARY OF SECURITY REQUIREMENTS. To guarantee compliance with the
terms of this agreement, payment of special assessments, payment of the costs of all public improvements,
and construction of all public improvements, the Developer shall furnish the City with an irrevocable letter of
credit, in the form attached hereto, from a bank, cash escrow or a combination cash escrow and Letter of
Credit ("security") for $533,844. The amount of the security was calculated as follows:
CONSTRUCTION CATEGORY: COST 125%
1. Grading N/A
2. Sanitary Sewer $73,000 $91,250
3. Watermain $67,000 $83,750
4. Storm Sewer (includes pond structures and outfall pipes) $39,500 $49,375
5. Streets $84,175 $105,219
6. Trails and Sidewalks
REV2: 04/18/2016 17
7. Surface Water Facilities (infiltration basins, bio retention basins, rain gardens,
etc.)
$13,000 $16,250
8. Street Lighting $12,000 $15,000
9. Street Signs and Traffic Control Signs $1,600 $2000
10. Private Utilities (electricity, natural gas, telephone, and cable) (To be coordinated by the Developer)
11. Landscaping $75,000 $93,750
12. Tree Preservation and Restoration N/A
13. Wetland Mitigation and Buffers $1,000 $1,250
14. Monuments $1,800 $2,250
15. Erosion and Sedimentation Control $36,650 $45,813
16. Miscellaneous Facilities N/A
17. Developer’s Record Drawings $2,500 3,125
CONSTRUCTION SUBTOTAL $427,075 N/A
TOTAL PROJECT SECURITIES (at 125% Construction Costs) N/A $533,844
This breakdown is for historical reference; it is not a restriction on the use of the security. The bank shall be
subject to the approval of the City Administrator. The City may draw down the security, without notice, for
any violation of the terms of this Contract or if the security is allowed to lapse prior to the end of the
required term. If the required public improvements are not completed at least thirty (30) days prior to the
expiration of the security, the City may also draw it down. If the security is drawn down, the proceeds shall
be used to cure the default.
35. REDUCTION OF SECURITY. Upon written request by the Developer to the City
Engineer and upon receipt of proof satisfactory to the City Engineer that work has been completed in
accordance with the approved plans and specifications, and terms of this Agreement, and
that all financial obligations to the City have been satisfied, the City Engineer may approve reductions in
the security as follows:
a. Upon completion of grading operations, including temporary site restoration,
Developer shall submit an as-built grading survey to the City that at a minimum establishes the as-built
REV2: 04/18/2016 18
grades at all lot corners and downstream drainage conveyance systems and storm water ponds. Upon
inspection of the site and approval of the as-built survey, 100%, or $0.00, of the grading security may be
released. This security reduction does not include amounts related to erosion and sedimentation control.
b. Up to 75% of the security provided in accordance with paragraph 34 may be
released upon completion of the following key milestones of the project as determined by the City
Engineer.
c. Construction Categories 2 and 3: The amount of $131,250 may be released when
all sanitary sewer and watermain utilities have been installed, all testing and televising has been
successfully completed, sanitary sewer as-built inverts have been verified, and the utilities are
considered ready for use by the City Engineer.
d. Construction Categories 4 and 5: The amount of $115,945 may be released when
all streets, and storm sewer have been installed and tested, and have been found to be complete to the
satisfaction of the City Engineer including all corrective work for any identified punch list items and
including verification of storm sewer as-built inverts, but not including the final wear course.
e. Construction Categories 6-18: The amount of $153,188 may be released when all
remaining Developer’s obligations under this Agreement have been completed including: (1) bituminous
wear course, (2) street lighting and private utilities, (3) sidewalks and trails, (4) bio retention facilities, (5)
iron monuments for lot corners have been installed, (3) all financial obligations to the City satisfied, (4)
the required "record" plans in the form of the City standards have been received and approved by the
City, and (5) the public improvements are accepted by the City Engineer and City Council.
f. At no point may the Security be reduced below twenty-five percent (25%) of the
original security amount until: (1) the warranty period has expired, (2) all improvements have been fully
completed and excepted by the City, including all corrective work and identified punch list items, and (3)
all financial obligations to the City have been satisfied.
g. In addition to the above project milestone based security reductions, the Developer
may submit written request to the City Engineer and upon receipt of proof satisfactory to the City
Engineer that work is progressing in accordance with the approved plans and specifications,
REV2: 04/18/2016 19
and terms of this Agreement, and that all financial obligations to the City have been satisfied, the
City Engineer may approve a one-time reduction in the security for Construction Categories 2-5 in an amount
not to exceed fifty percent (50%) of the initial security amounts.
h. It is the intention of the parties that the City at all times have available to it a Letter
of Credit in an amount adequate to ensure completion of all elements of the Subdivision Improvements
and other obligations of the Developer under this Agreement, including fees or costs due to the City by
the Developer. To that end and notwithstanding anything herein to the contrary, all requests by the
Developer for a reduction or release of the Letter of Credit shall be evaluated by the City in light of that
principle.
36. SUMMARY OF CASH REQUIREMENTS. The following is a summary of the cash
requirements under this Contract which must be furnished to the City at the time of final plat approval:
Sewer Availability Charge (SAC) $54,000 Water Availability Charge (WAC) $54,000 Park Dedication N/A Street Light Operating Fee $258 City Base Map Upgrading ($25.00 per REU) $450
City Engineering Administration Escrow $50,000 TOTAL CASH REQUIREMENTS $158,708
37. NOTICES. Required notices to the Developer shall be in writing, and shall be either hand
delivered to the Developer, its employees or agents, or mailed to the Developer by certified mail at the
following address:1660 Highway 100 South, Suite 400, St. Louis Park, MN 55416. Notices to the City shall
be in writing and shall be either hand delivered to the City Administrator, or mailed to the City by certified
mail in care of the City Administrator at the following address: Lake Elmo City Hall, 3800 Laverne Avenue
N. Lake Elmo, Minnesota 55042.
38. EVIDENCE OF TITLE. Developer shall furnish the City with evidence of fee ownership of
the property being platted by way of an attorney’s title opinion or title insurance policy dated not earlier than
thirty (30) days prior to the execution of the plat.
REV2: 04/18/2016 20
CITY OF LAKE ELMO (SEAL)
BY:
Mike Pearson, Mayor
REV2: 04/18/2016 21
AND Julie Johnson, City Clerk DEVELOPER:
BY: Its
STATE OF MINNESOTA ) ( ss. COUNTY OF WASHINGTON ) The foregoing instrument was acknowledged before me this day of ,
2016, by Mike Pearson and by Julie Johnson, the Mayor and City Clerk of the City of Lake Elmo, a Minnesota municipal corporation, on behalf of the corporation and pursuant to the authority granted by its City Council.
NOTARY PUBLIC DEVELOPER:
BY: Its
STATE OF MINNESOTA )
( ss. COUNTY OF )
The foregoing instrument was acknowledged before me this day of , 2016, by the of
.
REV2: 04/18/2016 22
NOTARY PUBLIC
DRAFTED BY: City of Lake Elmo 3800 Laverne Avenue North Lake Elmo, MN 55042 (651) 747-3901
REV2: 04/18/2016 23
FEE OWNER CONSENT
TO DEVELOPMENT CONTRACT
, fee owners of all or part of the subject property, the development of which is governed by the foregoing Development Contract, affirm and consent to the provisions thereof and agree to be bound by the provisions as the same may apply to
that portion of the subject property owned by them. Dated this day of , 2016.
STATE OF MINNESOTA ) ( ss. COUNTY OF )
The foregoing instrument was acknowledged before me this day of , 2016, by .
NOTARY PUBLIC
DRAFTED BY: City of Lake Elmo 3800 Laverne Avenue North Lake Elmo, MN 55042 (651) 747-3901
REV2: 04/18/2016 24
MORTGAGE CONSENT
TO DEVELOPMENT CONTRACT
, which holds a mortgage on the subject property, the development of which is governed by the foregoing Development Contract, agrees that the Development Contract shall remain in full force and effect even if it forecloses on its mortgage. Dated this day of , 2016.
STATE OF MINNESOTA ) ( ss. COUNTY OF )
The foregoing instrument was acknowledged before me this day of _, 2016, by .
NOTARY PUBLIC
DRAFTED BY: City of Lake Elmo 3800 Laverne Avenue North Lake Elmo, MN 55042 (651) 747-3901
REV2: 04/18/2016 25
CONTRACT PURCHASER CONSENT
TO DEVELOPMENT CONTRACT
, which/who has a contract purchaser's interest in all or part of the subject property, the development of which is governed by the foregoing Development Contract, hereby affirms and consents to the provisions thereof and agrees to be bound by the provisions as the same may apply to that portion of the subject property in which there is a contract purchaser's interest. Dated this day of , 2016.
STATE OF MINNESOTA )
( ss. COUNTY OF )
The foregoing instrument was acknowledged before me this day of _, 2016, by .
NOTARY PUBLIC
DRAFTED BY: City of Lake Elmo
3800 Laverne Avenue North Lake Elmo, MN 55042 (651) 747-3901
REV2: 04/18/2016 26
EXHIBIT “A”
TO DEVELOPMENT CONTRACT Legal Description of Property Being Final Platted as
Outlot H, Boulder Ponds
REV2: 04/18/2016 27
IRREVOCABLE LETTER OF CREDIT
No. Date:
TO: City of Lake Elmo
Dear Sir or Madam:
We hereby issue, for the account of OP4 Boulder Ponds, LLC and in your favor, our Irrevocable Letter of Credit in the amount of $533,844.00, available to you by your draft drawn on sight on the undersigned bank. The draft must: a) Bear the clause, "Drawn under Letter of Credit No. , dated , 2 , of
(Name of Bank) ";
b) Be signed by the Mayor or City Administrator of the City of Lake Elmo. c) Be presented for payment at (Address of Bank) , on or before 4:00 p.m. on November 30, 2_ _. This Letter of Credit shall automatically renew for successive one-year terms unless, at least forty-five (45) days prior to the next annual renewal date (which shall be November 30 of each year), the Bank delivers written notice to the Lake Elmo City Administrator that it intends to modify the terms of, or cancel, this Letter of Credit. Written notice is effective if sent by certified mail, postage prepaid, and deposited in the U.S. Mail, at least forty-five (45) days prior to the next annual renewal date addressed as follows: City Administrator, City Hall, 3800 Laverne Ave. N. Lake Elmo Minnesota 55042 and is actually received by the City Administrator at least thirty (30) days prior to the renewal date. This Letter of Credit sets forth in full our understanding which shall not in any way be modified, amended, amplified, or limited by reference to any document, instrument, or agreement, whether or not referred to herein. This Letter of Credit is not assignable. This is not a Notation Letter of Credit. More than one draw may be made under this Letter of Credit. This Letter of Credit shall be governed by the most recent revision of the Uniform Customs and Practice for Documentary Credits, International Chamber of Commerce Publication No. 500. We hereby agree that a draft drawn under and in compliance with this Letter of Credit shall be duly honored upon presentation. BY:
Its