HomeMy WebLinkAbout#12 Inwood Tower No. 4 - Pay Request No 1 AGENDA ITEM
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 12
AGENDA ITEM: Inwood Water Tower (No. 4) – Pay Request No. 1
SUBMITTED BY: Chad Isakson, Project Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer
Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the
project. Payment remains within the authorized scope and budget.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider approving Pay Request No. 1 for the
Inwood Water Tower (No. 4) project.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
CB&I, Inc., the Contractor for the project, has submitted Partial Pay Estimate No. 1 in the
amount of $45,505.00. The request has been reviewed and payment is recommended in the
amount requested. In accordance with the contract documents, the City has retained 5% of the
total work completed. The amount retained is $2,395.00.
City Council Meeting [Consent Agenda Item 12]
May 17, 2016
-- page 2 --
RECOMMENDATION:
Staff is recommending that the City Council consider approving, as part of the Consent Agenda,
Pay Request No. 1 for the Inwood Water Tower (No. 4) project. If removed from the consent
agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 1 to CB&I, Inc. in the amount of $45,505 for the Inwood
Water Tower (No. 4) Project”.
ATTACHMENT(S):
1. Partial Pay Estimate No. 1