MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM – PRESENTATIONS MOTION - YES
AGENDA ITEM: Promotion of 2 Probationary Members Jeremy Penman and Brandan
Peltier to Firefighter status
SUBMITTED BY: Greg Malmquist, Fire Chief
THROUGH: City Administrator, Kristina Handt
REVIEWED BY: City Administrator, Kristina Handt
SUGGESTED ORDER OF BUSINESS:
- Introduction of Item ............................................................................ Fire Chief
- Report/Presentation…………………………………………………..Fire Chief
- Questions from Council to Staff ............................................. Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECCOMENDER: Hiring process of fire department.
FISCAL IMPACT: Additional members on the payroll at full pay rates.
SUMMARY AND ACTION REQUESTED: Probationary members, Jeremy Penman and Brandan Peltier have successfully completed the requirements of Probation as follows: State
Certified Firefighter I & II, State Certified Haz Mat Operations, First Responder and CPR.
Approximately 200 hours of training. All the while maintaining their response requirements of
Duty Crews, All Calls and Training.
Request motion to promote from Probationary Status to Firefighter.
Following Motion and Approval we will administer their Oath of Office and present them with
their badge and helmet.
City Council Meeting [PRESENTATION]
May 17, 2016
-- page 2 --
LEGISLATIVE HISTORY: Established hiring process of the fire department.
BACKGROUND INFORMATION (SWOT):
Strengths Addition of 2 trained Firefighters to the Department
Weaknesses
Opportunities Long term Firefighter to serve the community. Threats Retention
RECOMMENDATION:
MOTION to approve promotion of Jeremy Penman and Brandan Peltier from Probationary status to Firefighter.
Following approval we will administer the Oath of Office and present the new Firefighters with their helmets and badges.
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM #3 MOTION
AGENDA ITEM: Approve Disbursements in the amount of $733,432.19
SUBMITTED BY: Patty Baker, Accountant
THROUGH: Cathy Bendel, Finance Director
REVIEWED BY: Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS:
- Introduction of Item .............................................................. City Administrator
- Report/Presentation…………………………………………City Administrator
- Questions from Council to Staff ............................................. Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Finance
FISCAL IMPACT: $733,432.19 SUMMARY AND ACTION REQUESTED: As part of its Consent Agenda, the City Council
is asked to approve disbursements in the amount of $733,432.19. No specific motion is needed
as this is recommended to be part of the Consent Agenda.
LEGISLATIVE HISTORY: NA
City Council Meeting [Consent Agenda Item 4]
May 17, 2016
-- page 2 --
BACKGROUND INFORMATION/STAFF REPORT: The City of Lake Elmo has the
fiduciary responsibility to conduct normal business operations. Below is a summary of current
claims to be disbursed and paid in accordance with State law and City policies and procedures.
Claim # Amount Description
ACH $ 15,084.85 Payroll Taxes to IRS & MN Dept of Revenue 05/12/16
ACH $ 7,230.89 Payroll Retirement to PERA 05/12/16
ACH $ 1,200.00 Payroll Retirement to ICMA 05/12/16
DD7159-DD7212 $ 37,547.37 Payroll (Direct Deposits) 05/12/16
44292-44360 $ 672,309.08 Accounts Payable 05/17/16
2759 $ 60.00 Library Card Reimbursement 05/17/16
TOTAL $ 733,432.19
RECOMMENDATION: Based on the aforementioned, the staff recommends the City Council
approve as part of the Consent Agenda the aforementioned disbursements in the amount of
$733,432.19.
ATTACHMENTS: 1. Accounts Payable – check registers
MAYOR AND COUNCIL COMMUNICATION
DATE: 5-17-16
CONSENT
ITEM #: 5
AGENDA ITEM: Mutual Aid Agreement
SUBMITTED BY: Mike Bent, Building Official
THROUGH: Mike Bent, Building Official
REVIEWED BY: Kristina Handt, City Administrator
SUMMARY AND ACTION REQUESTED: As part of its Consent Agenda, the City Council
is asked to accept the mutual aid agreement with the City of Woodbury. No specific motion is
needed, as this is recommended to be part of the overall approval of the Consent Agenda.
STAFF REPORT: The City of Lake Elmo has entered into a delegation agreement with the
Minnesota Department of Labor and Industry to perform plan review and inspections of state
owned facilities, public and charter schools, and state licensed facility projects. The state
recommends a system of back-up be in place to inspect delegation projects. This mutual aid
agreement will provide the recommended two-deep inspection capability for delegation projects.
RECOMMENDATION: Based on the aforementioned, the staff recommends the City Council
accept the Mutual Aid Agreement with the City of Woodbury for inspections of state delegation
projects.
1 | Page
479751v2 SJS LA515-1
MUTUAL AID AGREEMENT
This Mutual Aid Agreement (“Agreement”) is made and entered into this ____ day of _____________, 2016, by and between the City of Lake Elmo, a Minnesota municipal
corporation (“Lake Elmo”) and the City of Woodbury, a Minnesota municipal corporation
(“Woodbury”).
WHEREAS, Lake Elmo employs a full time building official and building inspector for the purpose of performing building plan review and building inspections; and
WHEREAS, Woodbury also employs a full time building official and building
inspectors for these purposes; and
WHEREAS, Minnesota Statutes Section 471.59 authorizes the joint and cooperative
exercise of powers common to contracting parties; and
WHEREAS, both parties are desirous of having their respective building officials and
building inspectors, equipment and other resources available for the purpose of providing assistance for state delegation projects;
NOW, THEREFORE, the parties agree as follows:
1. Definitions
1.1 “Party” means Woodbury or Lake Elmo.
1.2 “Requesting Official” means the person designated by a Party who is responsible for
requesting Assistance from the other Party.
1.3 “Requesting Party” means a party that requests Assistance from other Party.
1.4 “Responding Official” means the person designated by a Party who is responsible to
determine whether and to what extent that Party should provide Assistance to a Requesting Party.
1.5 “Responding Party” means a Party that provides Assistance to a Requesting Party.
1.6 “Assistance” means building inspections personnel and equipment for state delegation projects.
2. Procedure
2.1 Request for Assistance. Whenever, in the opinion of a Requesting Official, there is a need for Assistance from the other Party, the Requesting Official may call upon the
Responding Official of the other Party to furnish Assistance.
2 | Page
479751v2 SJS LA515-1
2.2 Response to request. Upon the request for Assistance from a Requesting Party, the
Responding Official may authorize and direct his or her party’s personnel to provide
Assistance to the Requesting Party. This decision will be made after considering the
needs of the Responding Party and the availability of resources.
2.3 Recall of Assistance. The Responding Official may at any time recall such Assistance
when in his or her best judgment or by an order from the city council of the Responding
Party, it is considered to be in the best interests of the Responding Party to do so.
3. Workers’ compensation. Each Party shall be responsible for injuries or death of its own personnel. Each Party will
maintain workers’ compensation insurance or self-insurance coverage, covering its own
personnel while they are providing Assistance pursuant to this Agreement. Each Party
waives the right to sue the other Party for any workers’ compensation benefits paid to its own employee or volunteer or their dependents, even if the injuries were caused wholly
or partially by the negligence of any other party or its officers, employees, or volunteers.
4. Damage to equipment.
Each Party shall be responsible for damages to or loss of its own equipment. Each Party waives the right to sue the other Party for any damages to or loss of its equipment, even if
the damages or losses were caused wholly or partially by the negligence of the other
Party or its officers, employees, or volunteers.
5. Liability 5.1 For the purposes of the Minnesota Municipal Tort Liability Act (Minn. Stat. 466), the
employees and officers of the Responding Party are deemed to be employees (as defined
in Minn. Stat. 466.01, subdivision 6) of the Requesting Party.
5.2 The Requesting Party agrees to defend and indemnify the Responding Party against any claims brought or actions filed against the Responding Party or any officer, employee, or
volunteer of the Responding Party for injury to, death of, or damage to the property of
any third person or persons, arising from the performance and provision of Assistance in
responding to a request for Assistance by the Requesting Party pursuant to this
Agreement.
5.3 Under no circumstances, however, shall a Party be required to pay on behalf of itself and
other parties, any amounts in excess of the limits on liability established in Minnesota
Statutes Chapter 466 applicable to any one Party. The limits of liability for some or all of
the Parties may not be added together to determine the maximum amount of liability for any Party.
5.4 The intent of this subdivision is to impose on each Requesting Party a limited duty to
defend and indemnify a Responding Party for claims arising within the Requesting
Party’s jurisdiction subject to the limits of liability under Minnesota Statutes Chapter 466. The purpose of creating this duty to defend and indemnify is to simplify the defense
3 | Page
479751v2 SJS LA515-1
of claims by eliminating conflicts among defendants, and to permit liability claims
against multiple defendants from a single occurrence to be defended by a single attorney.
5.5 Neither party to this Agreement nor any officer of any Party shall be liable to any other Party or to any other person for failure of any Party to furnish Assistance to the other
Party, or for recalling Assistance, both as described in this Agreement.
6. Charges to the Requesting Party.
6.1 No charges will be levied by a Responding Party to this Agreement for Assistance
rendered to a Requesting Party under the terms of this Agreement unless that
Assistance continues for a period of more than 48 hours. If Assistance provided
under this Agreement continues for more than 48 hours, the Responding Party
will submit to the Requesting Party an itemized bill for the actual cost of any Assistance provided after the initial 48 hour period, including salaries, overtime,
materials and supplies and other necessary expenses; and the Requesting Party
will reimburse the Party providing the Assistance for that amount.
6.2 Such charges are not contingent upon the availability of federal or state government funds.
7. Duration.
This Agreement will be in force for a period of five years from the date of written above. Either Party may withdraw from this Agreement upon providing 30 days’ written notice to the other
Party.
8. Government Data Practices.
Both Parties must comply with the Minnesota Government Data Practices Act, Minnesota
Statutes Chapter 13, as it applies to all data provided under this Agreement.
9. Governing Law.
This Agreement is to be governed by and construed in accordance with the laws of the State of
Minnesota. The venue for all legal proceedings arising out of this Agreement, or its breach, shall
be in the appropriate state or federal court with competent jurisdiction in Washington County,
Minnesota.
10. Entire Agreement.
This Agreement constitutes the entire agreement between the Parties. There are no other
agreements, either oral or written, between the Parties. Any modification of this Agreement or additional obligation assumed by either party in connection with this Agreement shall be binding
4 | Page
479751v2 SJS LA515-1
only if evidenced in writing signed by each Party’s representatives with signatory authority to
enter into agreements.
.
IN WITNESS WHEREOF, the parties have caused this Agreement to be executed on the date
and year written above.
CITY OF WOODBURY
By: ________________________________
Its: Mayor
By: ________________________________
Its: City Administrator
CITY OF LAKE ELMO
By: ________________________________
Mike Pearson Its: Mayor
By: _______________________________
Kristina Handt Its: City Administrator
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM #6
AGENDA ITEM: Monthly Assessor Report
SUBMITTED BY: Dan Raboin, City Assessor
THROUGH: Cathy Bendel, Finance Director
REVIEWED BY: Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS:
- Introduction of Item .............................................................. City Administrator
- Report/Presentation…………………………………………City Administrator
- Questions from Council to Staff .............................................. Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion ..................................................................... Mayor Facilitates
SUMMARY AND ACTION REQUESTED: As part of its Consent Agenda, the City Council is asked to accept the monthly assessor report for through April 2016 outlining work performed on behalf
of the City of Lake Elmo. No specific motion is needed as this is recommended as part of the Consent
Agenda.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
Property splits/plats – 0
Sales collected and viewed – 16
Taxpayer inquiries – 26 Miscellaneous inquiries - 5 Inspections – Residential – 11; Commercial – 1
Building permit reviews – 31
Pictures taken – 10
Other work performed included:
• Respond to valuation related phone calls
• 2016 LBAE Meeting (Open Book)
City Council Meeting [Consent Agenda Item #6]
May 17, 2016
-- page 2 --
• Monthly meeting with County residential and commercial supervisors
• Input of all inspection and permit work
• Perform sales verifications and land value analysis using MLS and other resources
• Field telephone inquiries
RECOMMENDATION: Based on the aforementioned, the staff recommends the City Council accept the April 2016 monthly assessor report.
MAYOR AND COUNCIL COMMUNICATION
DATE: 05/17/2016
CONSENT
ITEM #: 7
AGENDA ITEM: Building Department Report
SUBMITTED BY: Mike Bent, Building Official
THROUGH: Mike Bent, Building Official
REVIEWED BY: Cathy Bendel, Finance Director
SUMMARY AND ACTION REQUESTED: As part of its Consent Agenda, the City Council
is asked to accept the monthly building department report. No specific motion is needed, as this
is recommended to be part of the overall approval of the Consent Agenda.
STAFF REPORT: Below is a snapshot of the year to date statistics through April 2016.
Comparison data is also include from prior years for new home single family construction and
total permitting activity. Attached are the system summary reports breaking out this information
further, including the statistics related to the inspection activity.
2016 2015 2014
New homes 79 20 6
Total valuation $23,251,774 $7,551,994 $3,912,800
Average home value $294,326 $377,599 $652,133
Total Permit Valuation YTD $35,128,916 $10,760,747 $5,721,971
RECOMMENDATION: Based on the aforementioned, the staff recommends the City Council
accept the April 2016 monthly building permit report.
ATTACHMENTS:
1. Valuation Report
2. Permits Issued & Fees Report
3. Inspection statistic report for April 2016
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM #9
AGENDA ITEM: Approve Valley Branch Watershed District Boundary Update
SUBMITTED BY: Julie Johnson, City Clerk
THROUGH: Julie Johnson, City Clerk
REVIEWED BY: Kristina Handt, City Administrator
POLICY RECOMMENDER: City Clerk
FISCAL IMPACT: None
SUMMARY AND ACTION REQUESTED: As part of its routine review of hydrologic
boundaries, the Valley Branch Watershed District is requesting that the City of Lake Elmo concur with its updated legal boundaries. A letter explaining this process and two maps
illustrating the proposed changes are included with this memo.
RECOMMENDATION: “Motion to adopt Resolution 2016-38 approving the Valley Branch Watershed District Boundary Update.”
CITY OF LAKE ELMO
WASHINGTON COUNTY, MINNESOTA
RESOLUTION NO. 2016 - 38
A RESOLUTION SUPPORTING THE PETITION FROM VALLEY BRANCH WATERSHED DISTRICT TO THE BOARD OF WATER AND SOIL RESOURCES, REQUESTING A BOUNDARY CHANGE FOR THE TRANSFER
OF TERRITORY BETWEEN IT AND ITS ADJACENT WATERSHED
MANAGEMENT ORGANIZATIONS. _____________________________________________________ WHEREAS, the City of Lake Elmo received map figures showing the proposed changes
to the Valley Branch Watershed District, Brown’s Creek Watershed District, and South
Washington Watershed District (“the Districts”) boundaries.
WHEREAS, these boundary changes will make the legal boundaries of the Districts
better aligned with the hydrologic boundaries that exist between the Districts within the
City of Lake Elmo.
NOW THEREFORE BE IT RESOLVED that the City of Lake Elmo City Council
concurs with the proposed legal boundary changes to the Districts.
BY ROLL CALL VOTE OF THE CITY OF LAKE ELMO CITY COUNCIL:
THIS RESOLUTION IS ADOPTED / NOT ADOPTED
THIS _____ DAY OF ________________, 2016.
_______________________________ _______________________________ Attest: Clerk, City of Lake Elmo Mayor, City of Lake Elmo
Ramsey-Washington MetroWatershed District
South WashingtonWatershedDistrict
Valley BranchWatershedDistrict
Oakdale
LakeElmo
WoodburyInwood Ave NHudson RdHudson Ave
9th St N
4th St N
15th St N
Hudson Blvd
W h i s t l in g V a lle y R d
WoodburyLakes Rd Keats Ave N456719
456710456710
456719
456713
456713
§¨¦94 §¨¦94
Eagle PointLake Main
I
2,500 0Feet
Barr Footer: ArcGIS 10.3.1, 2016-02-02 13:19 File: I:\Client\VBWD\District\Work_Orders\Out_of_Scope\Misc\2015_Misc\District_Legal_Boundary_Update\For_Distribution_to_LGUs\Munis\Lake_Elmo_SW_Letter_Map.mxd User: mbs2
Proposed District Legal Boundary
Current District Legal Boundary
Revised Hydrologic Boundary
Proposed Parcel Change
Proposed Parcel into VBWD
No Change
Proposed Parcel out of VBWD
Municipal Boundary
Parcel Boundary Figure 1
PROPOSED PARCEL CHANGESBETWEEN VALLEY BRANCHWATERSHED DISTRICT ANDSURROUNDING DISTRICTSCity of Lake ElmoWashington County, Minnesota
Imagery Source: USDA NAIP, 2015
Browns CreekWatershedDistrict
Valley BranchWatershedDistrict
Oak ParkHeights
Stillwater
LakeElmo
Grant
Manning Ave NStillwater Blvd N62nd St N
50th St N
60th St N
456714
456715
456714
36 36
I
1,000 0 1,000Feet
Barr Footer: ArcGIS 10.3.1, 2016-02-02 13:23 File: I:\Client\VBWD\District\Work_Orders\Out_of_Scope\Misc\2015_Misc\District_Legal_Boundary_Update\For_Distribution_to_LGUs\Munis\Lake_Elmo_NE_Letter_Map.mxd User: mbs2
Proposed District Legal Boundary
Current District Legal Boundary
Revised Hydrologic Boundary
Proposed Parcel Change
Proposed Parcel into VBWD
No Change
Proposed Parcel out of VBWD
Municipal Boundary
Parcel Boundary Figure 2
PROPOSED PARCEL CHANGESBETWEEN VALLEY BRANCHWATERSHED DISTRICT ANDSURROUNDING DISTRICTSCity of Lake ElmoWashington County, Minnesota
Imagery Source: USDA NAIP, 2015
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 10
AGENDA ITEM: Temporary Liquor License for Lake Elmo Jaycees
SUBMITTED BY: Julie Johnson, City Clerk
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Kristina Handt, City Administrator
SUGGESTED ORDER OF BUSINESS:
- Introduction of Item .............................................................. City Administrator
- Report/Presentation…………………………………………City Administrator
- Questions from Council to Staff ............................................. Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Lake Elmo Jaycees, Staff
SUMMARY AND ACTION REQUESTED:
As part of the Consent Agenda, City Council is respectfully requested to consider approval of a temporary on-sale liquor license issued to the Lake Elmo Jaycees for their annual Huff n’ Puff
Days event held August 11 through 14, 2016, subject to approval of the Director of Alcohol and
Gambling Enforcement. In addition, the City Council is requested to waive the $25 liquor license
fee and the fee for the Lion’s Park ball field lighting. As part of the Consent Agenda, no formal
motion is required. If removed from the Consent Agenda, the recommended motion is as follows:
“Move to approve a temporary on-sale liquor license issued to the Lake Elmo Jaycees for their
Huff n’ Puff Days event held August 11 through 14, 2016, subject to approval of the Director of MN Alcohol and Gambling Enforcement Division, and waive both the $25 liquor license fee and the fee for Lion’s Park ball field lighting.”
LEGISLATIVE HISTORY:
City Council Meeting [Consent Agenda Item 9]
May 17, 2016
-- page 2 --
Pursuant to Lake Elmo City Code Chapter 111.17 Section (B)(3), temporary on-sale licenses
shall be issued only to clubs, charitable, religious, or other non-profit organizations in existence
for at least three years and shall authorize the on-sale of intoxicating liquor in connection with a
social event sponsored by the licensee and subject to the restrictions imposed by MN Statute 340A.
Lake Elmo Jaycees will hold their annual Huff n’ Puff Days event August 11 through 9, 2015
and have requested an on-sale temporary special event liquor license to allow for the safe sale of
alcoholic beverages at the event. RECOMMENDATION:
If removed from the Consent Agenda, Staff recommends the following motion:
“Move to approve a temporary on-sale liquor license issued to the Lake Elmo Jaycees for their Huff n’ Puff Days event held August 11 through 14, 2016, subject to approval of the Director of MN Alcohol and Gambling Enforcement Division, and waive both the $25 liquor license fee
and the fee for Lion’s Park ball field lighting.”
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 11
AGENDA ITEM: Inwood Trunk Watermain Improvements – Pay Request No. 1
SUBMITTED BY: Chad Isakson, Project Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer
Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the
project. Payment remains within the authorized scope and budget.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider approving Pay Request No. 1 for the
Inwood Trunk Watermain Improvements project.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
Northdale Construction Company, Inc., the Contractor for the project, has submitted Partial Pay
Estimate No. 1 in the amount of $349,571.01. The request has been reviewed and payment is
recommended in the amount requested. In accordance with the contract documents, the City has
retained 5% of the total work completed. The amount retained is $18,398.47.
City Council Meeting [Consent Agenda Item 11]
May 17, 2016
-- page 2 --
RECOMMENDATION:
Staff is recommending that the City Council consider approving, as part of the Consent Agenda,
Pay Request No. 1 for the Inwood Trunk Watermain Improvements project. If removed from the
consent agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 1 to Northdale Construction Company, Inc. in the amount
of $349,571.01 for the Inwood Trunk Watermain Improvements”.
ATTACHMENT(S):
1. Partial Pay Estimate No. 1
PARTIAL PAY ESTIMATE NO. 1
INWOOD AVENUE TRUNK WATERMAIN IMPROVEMENTS
CITY OF LAKE ELMO, MINNESOTA
PROJECT NO. 2014.130
QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
1 LS 1 $64,800.00 $64,800.00 1.00 $64,800.00 1.00 $64,800.00
2 LS 1 $22,945.00 $22,945.00 0.25 $5,736.25 0.25 $5,736.25
3 LF 600 $4.13 $2,478.00 105 $433.65 105 $433.65
4 EA 6 $750.00 $4,500.00 0 $0.00 0 $0.00
5 EA 10 $104.50 $1,045.00 0 $0.00 0 $0.00
$95,768.00 $70,969.90 $70,969.90
1 EA 1 $7,483.75 $7,483.75 0 $0.00 0 $0.00
2 EA 2 $13,187.61 $26,375.22 1 $13,187.61 1 $13,187.61
3 EA 11 $4,431.40 $48,745.40 2 $8,862.80 2 $8,862.80
4 LF 6 $1,628.80 $9,772.80 0 $0.00 0 $0.00
5 EA 10 $2,476.08 $24,760.80 2 $4,952.16 2 $4,952.16
6 EA 3 $2,920.05 $8,760.15 0 $0.00 0 $0.00
7 EA 2 $4,117.60 $8,235.20 2 $8,235.20 2 $8,235.20
8 EA 19 $10,711.98 $203,527.62 3 $32,135.94 3 $32,135.94
9 EA 3 $709.63 $2,128.89 2 $1,419.26 2 $1,419.26
10 EA 3 $775.20 $2,325.60 1 $775.20 1 $775.20
11 LF 100 $50.97 $5,097.00 20 $1,019.40 20 $1,019.40
12 LF 75 $63.87 $4,790.25 43 $2,714.48 43 $2,714.48
13 LF 96 $70.32 $6,750.72 0 $0.00 0 $0.00
14 LF 28 $108.70 $3,043.60 25 $2,690.33 25 $2,690.33
15 LF 25 $126.98 $3,174.50 30 $3,809.40 30 $3,809.40
16 LF 11,015 $74.75 $823,371.25 2,466 $184,333.50 2,466 $184,333.50
17 LB 5,810 $10.74 $62,399.40 1,674 $17,978.76 1,674 $17,978.76
18 LS 1 $49,462.20 $49,462.20 0 $12,365.55 0 $12,365.55
19 LS 1 $7,000.00 $7,000.00 0 $2,310.00 0 $2,310.00
20 EA 18 $156.02 $2,808.36 0 $0.00 0 $0.00
$1,310,012.71 $296,789.58 $296,789.58
1 LF 60 $15.00 $900.00 14 $210.00 14 $210.00
2 LF 60 $31.11 $1,866.60 0 $0.00 0 $0.00
$2,766.60 $210.00 $210.00
1 EA 2 $165.00 $330.00 0 $0.00 0 $0.00
2 EA 13 $220.00 $2,860.00 0 $0.00 0 $0.00
$3,190.00 $0.00 $0.00
TOTALS $1,411,737.31 $367,969.48 $367,969.48
SUBTOTAL ‐ DIVISION 2
SUBTOTAL ‐ DIVISION 4
DIVISION 4 ‐ STREET CONSTRUCTION
DIVISION 3 ‐ STORM SEWER
SALVAGE CONCRETE PIPE CULVERT
INSTALL SALVAGED PIPE CULVERT
SALVAGE AND REINSTALL SIGN
SUBTOTAL ‐ DIVISION 3
16" HDPE DIPS DR11 WATERMAIN, DIRECTIONAL DRILL
DUCTILE IRON FITTINGS
HORIZONTAL DIRECTIONAL DRILLING BORE PITS
WATER SERVICE CONNECTION PITS
TRIVIEW TEST STATION MARKER
1" COPPER WATER SERVICE PIPE
6" DUCTILE IRON WATERMAIN PIPE, CLASS 52
8" DUCTILE IRON WATERMAIN PIPE, CLASS 52
12" DUCTILE IRON WATERMAIN PIPE, CLASS 52
16" DUCTILE IRON WATERMAIN PIPE, CLASS 52
DIVISION 1 ‐ GENERAL
MOBILIZATION
TRAFFIC CONTROL
SILT FENCE, MACHINE SLICED
HYDRANT EXTENSION
ITEM DESCRIPTION OF PAY ITEM UNIT
CONTRACT THIS PERIOD TOTAL TO DATE
1" CURB STOP AND CURB BOX
CLEAR AND GRUB TREE
DITCH CHECK
SUBTOTAL ‐ DIVISION 1
DIVISION 2 ‐ WATERMAIN
CONNECT TO EXISTING 8" WATERMAIN
CONNECT TO EXISTING 16" WATERMAIN
12" GATE VALVE AND BOX
1" CORPORATION STOP WITH FUSIBLE SADDLE
HYDRANT
6" GATE VALVE AND BOX
8" GATE VALVE AND BOX
16" BUTTERFLY VALVE AND BOX
SALVAGE AND REINSTALL MAILBOX
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 12
AGENDA ITEM: Inwood Water Tower (No. 4) – Pay Request No. 1
SUBMITTED BY: Chad Isakson, Project Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer
Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the
project. Payment remains within the authorized scope and budget.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider approving Pay Request No. 1 for the
Inwood Water Tower (No. 4) project.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
CB&I, Inc., the Contractor for the project, has submitted Partial Pay Estimate No. 1 in the
amount of $45,505.00. The request has been reviewed and payment is recommended in the
amount requested. In accordance with the contract documents, the City has retained 5% of the
total work completed. The amount retained is $2,395.00.
City Council Meeting [Consent Agenda Item 12]
May 17, 2016
-- page 2 --
RECOMMENDATION:
Staff is recommending that the City Council consider approving, as part of the Consent Agenda,
Pay Request No. 1 for the Inwood Water Tower (No. 4) project. If removed from the consent
agenda, the recommended motion for the action is as follows:
“Move to approve Pay Request No. 1 to CB&I, Inc. in the amount of $45,505 for the Inwood
Water Tower (No. 4) Project”.
ATTACHMENT(S):
1. Partial Pay Estimate No. 1
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 13
AGENDA ITEM: Eagle Point Boulevard Street and Utility Improvements – Change Order
No. 3
SUBMITTED BY: Ryan Stempski, Project Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Cathy Bendel, Finance Director
Jack Griffin, City Engineer
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: None. This change order only impacts the Contract Final Completion Date
for the project.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider approving Change Order No. 3 for the
Eagle Point Boulevard Street & Utility Improvements.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
This change order extends the contract times for final completion by 107 days from June 15,
2016 to September 30, 2016. The time extension for final completion is being requested by the
City to minimize scarring and damage to the new pavement from construction work on adjacent
property. More specifically, this time extension allows the placement of the final wear course of
bituminous until after substantial construction activity on the ISD 916 Pankalo School has been
City Council Meeting [Consent Agenda Item 13]
May 17, 2016
-- page 2 --
completed this summer. The Contractor has agreed to defer the placement of the final wear
course without requesting additional payment.
With approval of Change Order No. 3, the revised Final Completion date will be September 30,
2016.
RECOMMENDATION:
Staff is recommending that the City Council approve, as part of the consent agenda, Change
Order No. 3 for the Eagle Point Boulevard Street & Utility Improvements, thereby extending the
Contract Times for Final Completion until September 30, 2016. If removed from the consent
agenda, the recommended motion for the action is as follows:
“Move to approve Change Order No. 3 for the Eagle Point Boulevard Street & Utility
Improvements Project”.
ATTACHMENT(S):
1. Change Order No. 3.
CONTRACT CHANGE ORDER FORM
CHANGE ORDER NO. DATE:
TO:
UNIT
Amount of Original Contract $
Sum of Additions/Deductions approved to date $
Contract Amount to date $
Amount of this Change Order (ADD) (DEDUCT) (NO CHANGE)$
Revised Contract Amount $
The Contract Period for Final Completion will be (UNCHANGED) (INCREASED) (DECREASED)days
APPROVED BY ENGINEER: FOCUS Engineering, inc. APPROVED BY CONTRACTOR
DATE DATE
APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA
DATE DATE
$0.00
CITY OF LAKE ELMO, MINNESOTA
BYBY
CHANGE ORDER DESCRIPTION / JUSTIFICATION:
This change order extends the contract time for Final Completion by 107 days from June 15, 2016 to September 30, 2016. The
time extension is being requested by the City to mimize surface damage to the new pavement from construction activities on the
adjacent ISD 196 Pankalo School site. Furthermore it is recommended to pave the final lift of asphalt after both concrete
driveway entrances have been completed by the school for their project. This sequence of events would minimize the need to
cut into the new street to match the driveways to the street edge. Ultimately, the City will receive a better street finish at no
additional cost by delaying the placement of the final street layer to September 30, 2016.
Attachments (list documents supporting change):
DESCRIPTION OF PAY ITEM QTY UNITE PRICE
NET CONTRACT CHANGE
ITEM
MILLER EXCAVATING, INC. , 3636 STAGECOACH TRAIL N, STILLWATER, MN 55082
EAGLE POINT BLVD STREET & UTILITY IMPROVEMENTS
PROJECT NO. 2015.120
3May 2, 2016
107
This Document will become a supplement to the Contract and all provisions will apply hereto. The Contract Documents are
modified as follows upon execution of this Change Order.
BYENGINEER
1,249,494.09
(28,500.00)
1,220,994.09
0.00
1,220,994.09
INCREASE/(DECREASE)
FOCUS Engineering, inc.CHANGE ORDER FORM
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 14
AGENDA ITEM: 2016 Seal Coat Project – West Lakeland Township Joint Services
Agreement
SUBMITTED BY: Ryan Stempski, Assistant City Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer
Cathy Bendel, Finance Director
Mike Bouthilet, Public Works
SUGGESTED ORDER OF BUSINESS (if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering and Public Works.
FISCAL IMPACT: Cost savings of $3,000 in engineering and administration services. Seal coat unit
price reduction also anticipated based on economy of scale at the time of construction.
Through a joint project effort, the City of Lake Elmo, West Lakeland Township and, at times, Baytown
Township, have been realizing project cost savings through an economy of scale and sharing in project
expenses for preparation of plans and specifications, bidding, and construction administration. In
addition, staff believes that by combining the project work for multiple communities, we can continue to
promote a more favorable bidding environment that may result in lower overall construction costs.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider approving the West Lakeland Township Joint
Services Agreement for the 2016 Seal Coat Project.
City Council Meeting [Consent Agenda Item 14]
May 17, 2016
-- page 2 --
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
Since 2012, Lake Elmo and West Lakeland Township have successfully contracted jointly for
the annual street seal coat projects to share and reduce overall project costs. Staff has reviewed
and updated the Joint Services Agreement with West Lakeland Township in preparation of the
2016 Seal Coat Project. Staff is recommending that the city continue to work jointly with West
Lakeland Township to perform seal coating for routine maintenance of city and township streets.
The agreement identifies the terms and conditions upon which the City of Lake Elmo prepares
and administers a contract for the 2016 Seal Coat Project to be completed on streets within both
the city and township. Each jurisdiction pays its portion of the construction costs and shares in
the engineering design, bidding and construction administration costs. The construction
observation services would be contracted directly by each jurisdiction.
The City of Lake Elmo is defined as the lead entity and prepares the plans and specifications
with input from the township. The city bids the project and enters into a contract with the
selected contractor for all the work. West Lakeland will pay a fee to the city in the amount of
$3,000 to reimburse the city for the design, bidding and construction administration services
related to the project. The township will reimburse the city within 30 days of receiving contractor
invoices for the work performed on West Lakeland streets.
RECOMMENDATION:
Staff is recommending that the City Council consider approving, as part of the consent agenda, the
West Lakeland Township Joint Services Agreement for the 2016 Seal Coat Project. If removed from the
consent agenda, the recommended motion for this action is as follows:
“Move to approve the West Lakeland Township Joint Services Agreement
for the 2016 Seal Coat Project.”
ATTACHMENT(S):
1. West Lakeland Township Joint Services Agreement for the 2016 Seal Coat Project.
JOINT SERVICES AGREEMENT FOR THE 2016 SEAL COAT PROJECT
This Agreement is made this ___ day of ________2016, by and between the West Lakeland
Township (hereinafter referred to as “West Lakeland”) and the City of Lake Elmo (hereinafter
referred to as “Lake Elmo”).
WHEREAS, it is the desire of the parties, and it is the purpose of this Agreement, that
certain road-related services be performed or contracted by Lake Elmo on behalf of West Lakeland
for the purpose of seal coating certain street segments as designated by West Lakeland;
NOW, THEREFORE, in consideration of the mutual covenants and conditions set forth
below, the above parties hereto agree as follows:
1. Term: The term of this Agreement shall commence upon the date of execution and
shall be for the duration of the one year warranty period for the 2016 Seal Coat Project.
2. Services. For the term of this Agreement, Lake Elmo shall provide West Lakeland
with the following services in and on behalf of West Lakeland and at the direction of West
Lakeland’s Engineer:
a. Lake Elmo will provide professional engineering services to prepare Plans and
Specifications and Contract documents for the 2016 Seal Coat Project. The
project will include seal coating of street segments located in West Lakeland, in
addition to the street segments located in Lake Elmo for which Lake Elmo is
otherwise contracting.
b. Prior to March 15, 2016, West Lakeland will provide Lake Elmo with a plan,
designating and depicting the street segments to be seal coated in West
Lakeland, said plan to be suitable for inclusion in the Plan documents, along
with a tabulation of the estimated quantities (in square yards) showing the seal
coating work to be performed in West Lakeland as a part of the project.
c. Lake Elmo will advertise the 2016 Seal Coat Project for contractor bids and
may award a contract for seal coating, or a portion of thereof, as deemed in the
best interests of Lake Elmo. If Lake Elmo awards a contract for the 2016 Seal
Coat Project and West Lakeland agrees, the award shall include that portion of
streets within West Lakeland.
d. Lake Elmo will provide professional engineering services for the construction
administration of the contract.
e. At its sole cost and expense, West Lakeland will provide a construction
observer to inspect the seal coat work performed on West Lakeland streets.
3. Payments. West Lakeland shall make payments to Lake Elmo for services related to
the project or directly for services as follows:
2
a. West Lakeland will pay Lake Elmo a fee in the amount of $3,000 for
engineering and administration fees performed by Lake Elmo for the seal coat
project. Lake Elmo will invoice this amount to West Lakeland once the Lake
Elmo City Council accepts the bids and awards the construction contract.
b. Lake Elmo will make Contractor payments for all work completed in
accordance with the Contract. West Lakeland will reimburse Lake Elmo for the
work completed and paid to the contractor in accordance with the contract for
the actual quantities of work performed on West Lakeland streets.
c. Lake Elmo will invoice West Lakeland for services to be reimbursed by West
Lakeland as outlined above and West Lakeland will pay all invoices within 30
days after receipt of the invoice. Lake Elmo shall include with its invoices
copies of the contractor’s claims showing the amount charged for the work
performed and materials used in West Lakeland.
4. Insurance. Lake Elmo shall require its contractor(s) to provide insurance as
specified below, and West Lakeland shall be named as an additional insured on such insurance:
Comprehensive General Liability $1,000,000 per occurrence, $2,000,000 aggregate
Auto Liability $1,200,000 per occurrence
Workers compensation Statutory amount
5. Indemnification. Lake Elmo agrees to defend, indemnify and hold harmless West
Lakeland, and its officials, agents and employees from and against all claims, actions, damages,
losses and expenses, including attorneys fees, arising out of or resulting from Lake Elmo's
performance of the duties required under this Agreement, provided that any such claim, action,
damage, loss or expense is caused in whole or in part by an alleged negligent act, omission, or
willful misconduct (including, but not limited to, a claimed breach of contract made by the
contractor) of Lake Elmo. Lake Elmo agrees to require, as part of its contract with the contractor
used to provide the seal coating, to include West Lakeland in the contractor’s indemnification
obligation under the contract. West Lakeland agrees to defend, indemnify and hold harmless Lake
Elmo, and its officials, agents and employees from and against all claims, actions, damages, losses
and expenses, including attorneys’ fees, arising out of or resulting from West Lakeland’s
performance of the duties required of it under this Agreement, provided that any such claim, action,
damage, loss or expense is caused in whole or in part by an alleged negligent act or omission or
willful misconduct of West Lakeland. This provision shall not be construed as a waiver by either
party of any defenses, immunities or limitations on liability to which they are entitled, under
Minnesota Statutes, Chapter 466 or otherwise. Under no circumstances shall a party be required to
pay on behalf of itself and other parties, any amounts in excess of the limits of liability established
in Minnesota Statutes, Chapter 466, applicable to any one party. The limits of liability for some or
all of the parties may not be added together to determine the maximum amount of liability for any
party.
6. Service Contract. This is a service contract. The parties do not intend to create, and
nothing herein shall be construed as creating, a joint powers agreement, joint venture, or joint
enterprise. However, to the extent a court of competent jurisdiction may find such a relationship
exists, Lake Elmo and West Lakeland shall be considered a single governmental entity as provided
3
in Minnesota Statutes, section 471.59, subdivision 1a for the purposes of determining total liability.
The limits of liability for Lake Elmo and West Lakeland shall not be added together to determine
the maximum amount of liability for either party or for any occurrence.
7. Contracting Procedure and Oversight. Lake Elmo shall be solely responsible for
letting the contracts for the services to be provided hereunder in accordance with all applicable
laws, rules, and regulations. The bonds obtained from the contractor for the work shall include the
work to be performed in West Lakeland. Lake Elmo shall, to the extent reasonably necessary, assist
West Lakeland to draw upon the performance bond as needed to complete or correct any work the
contractor fails to perform in West Lakeland in accordance with the contract. West Lakeland will
be responsible for inspecting the work to be performed in West Lakeland, but Lake Elmo shall be
responsible for generally overseeing the contractor’s performance of services in accordance with
the contract.
8. Miscellaneous. This Agreement is solely for the benefit of the parties hereto and no
other person shall have any right, claim, or interest in it.
9. Legal Compliance. Both parties agree to comply with all applicable state, federal
and local laws, rules and regulations in carrying out their respective obligations under this
Agreement.
10. Entire Agreement. This Agreement represents the entire agreement between Lake
Elmo and West Lakeland and supersedes and cancels any and all prior agreements or proposals,
written or oral, between the parties relating to the subject matter hereof. No amendments, addenda,
alterations, or modifications to the terms and conditions of this Agreement shall be effective unless
in writing and signed by both parties.
IN WITNESS WHEREOF, the parties have set forth their hands on the day and year first
written above.
CITY OF LAKE ELMO TOWN OF WEST LAKELAND
By: ___________________________ By: ___________________________
Its Mayor Its Town Chairperson
______________________________ ______________________________
Date Date
By: ___________________________ By: ___________________________
Its City Administrator Its Town Clerk-Treasurer
______________________________ ______________________________
Date Date
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 15
AGENDA ITEM: 2016 Seal Coat Project – Accept Bids and Award Contract
SUBMITTED BY: Ryan Stempski, Assistant City Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director Mike Bouthilet, Public Works
SUGGESTED ORDER OF BUSINESS (if removed from the Consent Agenda):
- Questions from Council to Staff ......................................................... Mayor Facilitates
- Public Input, if Appropriate………………………………………… Mayor Facilitates
- Call for Motion ........................................................................... Mayor & City Council
- Discussion…………………………………. .............................. Mayor & City Council
- Action on Motion ............................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: $152,875.00.
As itemized in this report below the total post-bid project cost for the 2016 Seal Coat Project is $158,375.00 to be paid through the General Fund (Fund No. 101-430-3120-42250).
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider accepting contractor bids and awarding a contract for the 2016 Seal Coat Project.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
Bids were received, publicly opened, and read aloud on May 5, 2016. FOCUS Engineering, Inc. has
prepared and attached the Tabulation of Bids and a Letter of Recommendation for the award of the contract. The City received three (3) bids for this project, with Pearson Bros., Inc. providing the lowest
bid amount of $1.19 per square yard for the base bid and $1.25 per square yard for the alternate bid. The
Engineer’s post-design construction cost estimate for the base bid was $1.23 per square yard and $1.33 per square yard for the alternate bid.
City Council Meeting [Consent Agenda Item 15]
May 17, 2016
-- page 2 --
This project will be completed jointly with West Lakeland Township with the Township reimbursing
Lake Elmo their portion of the construction cost; with West Lakeland at $56,028.00 (26.8%). West
Lakeland will also pay Lake Elmo $3,000 for engineering and administration fees once the Lake Elmo City Council accepts the bids and awards the construction contract. Construction observation services
will be contracted directly by each jurisdiction for the work performed on their streets.
The post-bid construction estimate for Lake Elmo is $152,875.00 (73.2%) for the alternate bid, which
includes higher performing asphalt (CRS-2P) to provide a better product and to reduce resident complaints. The total engineering design, bidding and construction services is estimated to be $8,500 less $3,000 to be reimbursed by West Lakeland Township. The Lake Elmo total project cost is therefore
estimated to be $158,375.00. RECOMMENDATION:
Staff is recommending that the City Council approve Resolution No. 2016-40, thereby accepting the bids and awarding a Contract to Pearson Bros., Inc. If removed from consent, the recommended motion for
this action is as follows:
“Move to approve Resolution No. 2016-40 Accepting the Bids and Awarding a Contract to Pearson
Bros., Inc. in the amount of $208,903.00 for the 2016 Seal Coat Project; which includes the alternate bid for Lake Elmo in the amount of $152,875.00 and the alternate bid for West Lakeland in the amount of $56,028.00.”
ATTACHMENT(S):
1. Resolution 2016-40 2. Engineer’s Letter of Award Recommendation and Tabulation of Bids.
3. Project Schedule.
Resolution No. 2016-40 1
CITY OF LAKE ELMO
WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2016-40
A RESOLUTION ACCEPTING THE BIDS AND AWARDING A
CONTRACT FOR THE 2016 SEAL COAT PROJECT
WHEREAS, pursuant to an advertisement for bids for the 2016 Seal Coat Project, bids were
received, opened, and tabulated according to law, and bids were received complying with the
advertisement; and WHEREAS, bids were tabulated, checked and summarized to verify that all requirements of the
submittals were met; and
WHEREAS, the project engineer reviewed the bids and has provided a letter recommending the award of the contract to the lowest responsible bidder, Pearson Brothers, Inc., in the amount of $208,903.00.
NOW, THEREFORE, IT IS HEREBY RESOLVED,
1. That the Mayor and City Clerk are hereby authorized and directed to enter into a Contract in the accordance with the above ordered Project, in the amount of the Contractor’s
lowest responsible bid, and according to the plans and specifications thereof approved by
the City Council.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits made with their bids, except that the deposits of the successful bidder and the
next two lowest bidders shall be retained until a contract has been signed.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE SEVENTEENTH DAY OF
MAY 2016.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
Mayor (Seal)
ATTEST:
________________________________ Julie Johnson
City Clerk
May 9, 2016
Honorable Mayor and City Council
City of Lake Elmo, Minnesota
2016 Seal Coat Project
City of Lake Elmo, Minnesota
FOCUS Project No. 2016.118
Dear Mayor and City Council:
Bids for the 2016 Seal Coat Project were received on May 5, 2016, at 3:00 PM with the following results:
Contractor Base Bid Alternate Bid
Pearson Bros., Inc.
City of Lake Elmo $145,537.00 $152,875.00
West Lakeland Township $53,130.00 $56,028.00
TOTAL: $198,667.00 $208,903.00
Allied Blacktop Co.
City of Lake Elmo $147,983.00 $154,098.00
West Lakeland Township $59,409.00 $61,824.00
TOTAL: $207,392.00 $215,922.00
Fahrner Asphalt
City of Lake Elmo $188,342.00 $203,018
West Lakeland Township $74,382.00 $80,178.00
TOTAL: $262,724.00 $283,196.00
A complete Tabulation of Bids is enclosed for your information. We recommend that you award the Contract
to the lowest responsible bidder, Pearson Brothers, Inc. in the total amount of $208,903.00 for their
alternate bid to Lake Elmo in the amount of $152,875.00; and alternate bid for West Lakeland in the amount
of $56,028.00.
Please contact me with any questions you may have.
Sincerely,
Ryan W. Stempski, P.E.
Project Engineer
Enclosure
cc: Jack Griffin, City Engineer
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
TABULATION OF BIDS2016 SEAL COAT PROJECTCITY OF LAKE ELMO & WEST LAKELAND TWPPROJECT NO. 2016.118 BIDS OPENED: MAY 5, 2016, AT 3:00 PMBASE BID (CRS‐2 EMULSIFIED ASPHALT)ITEMUNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTALNO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNTCITY OF LAKE ELMO1 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 122,300 SY 1.23$ 150,429.00$ 1.19$ 145,537.00$ 1.21$ 147,983.00$ 1.54$ 188,342.00$ CITY OF WEST LAKELAND2 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 48,300 SY 1.23$ 59,409.00$ 1.10$ 53,130.00$ 1.23$ 59,409.00$ 1.54$ 74,382.00$ TOTAL209,838.00$ 198,667.00$ 207,392.00$ 262,724.00$ ALTERNATE BID NO. 1 (CRS‐2P EMULSIFIED ASPHALT)ITEMUNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTALNO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNTCITY OF LAKE ELMO1 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 122,300 SY 1.33$ 162,659.00$ 1.25$ 152,875.00$ 1.26$ 154,098.00$ 1.66$ 203,018.00$ CITY OF WEST LAKELAND2 BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK 48,300 SY 1.33$ 64,239.00$ 1.16$ 56,028.00$ 1.28$ 61,824.00$ 1.66$ 80,178.00$ TOTAL226,898.00$ 208,903.00$ 215,922.00$ 283,196.00$ ENGINEER'S ESTIMATE Pearson Bros., Inc. Allied Blacktop CompanyENGINEER'S ESTIMATE Pearson Bros, Inc. Allied Blacktop Company Fahrner AsphaltAstech Corp.Astech Corp.Did Not SubmitDid Not SubmitDid Not SubmitDid Not SubmitFahrner Asphalt
CITY OF LAKE ELMO
2016 SEAL COAT PROJECT
PROJECT NO. 2016.118
PROJECT SCHEDULE
April 7, 2016 Placement of Advertisement for Bids.
–Oakdale‐Lake Elmo Review. Publication on April 13
– Quest CDN. Publication on April 13
May 5, 2016 Receive Contractor bids.
May 17, 2016 City Council accepts bids and awards Contract.
May 20, 2016 Process and send out Contract Documents.
June 9, 2016 Receipt of Contractor’s Bonds/Legal Review.
June 14, 2016 Conduct Pre‐Construction Meeting and Issue Notice to
Proceed.
June 15, 2016 Contractor begins Work.
July 15, 2016 Substantial Completion of Work (including sweeping of excess
aggregate).
August 31, 2016 Final Completion of Work (including Punchlist and final
documentation).
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 16
AGENDA ITEM: 2016 Street Full Depth Patching – Accept Quotes and Award Contract
SUBMITTED BY: Ryan Stempski, Assistant City Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director Mike Bouthilet, Public Works
SUGGESTED ORDER OF BUSINESS (if removed from the Consent Agenda):
- Questions from Council to Staff ......................................................... Mayor Facilitates
- Public Input, if Appropriate………………………………………… Mayor Facilitates
- Call for Motion ........................................................................... Mayor & City Council
- Discussion…………………………………. .............................. Mayor & City Council
- Action on Motion ............................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: $55,820.00.
The 2016 Street Full Depth Patching work would be paid from the Street Budget under the General Fund. With this cost the street maintenance work, including crack seal, seal coat, overlay and full depth patching
would be completed within the total 2016 budget amount. SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider accepting contractor quotes and awarding a
contract for the 2016 Street Full Depth Patching project.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
In addition to the City’s annual street maintenance work completed by Public Works staff, the City contracts out street maintenance for crack sealing, seal coating, occasional mill and overlay work and full
depth patch repairs. This work is part of the City annual street maintenance budget. To date, contractor
bids or quotes have been received for the 2016 Crack Seal Project, the 2016 Seal Coat Project and the 2016 Overlay Project. In each case, the bids or quotes have been favorable, coming in well under budget.
City Council Meeting [Consent Agenda Item X]
May 17, 2016
-- page 2 --
On May 11, 2016, staff received two contractor quotes to complete full depth street patching work along
14th Street North within the Homestead neighborhood. The work will repair localized areas of pavement
distress near the entrance of the neighborhood where the street is in significant disrepair. The work will serve to extend the useful life of this roadway and will help defer the neighborhood streets from a more
significant street improvement project. It is recommended to have this work completed in 2016. In 2017,
all streets in the neighborhood are scheduled to be seal coated.
To comply with competitive bidding law for contracts between $25,000 and $100,000, the City may use direct negotiation. When direct negotiation is used, two quotes must be obtained and kept on file for the period of one year. Contractor quotes were obtained from local, reputable paving contractors with the
following results: Hardrives, Inc. = $55,820.00.
T.A. Schifsky & Sons, Inc. = $68,040.00. The breakdown of these quote totals can be seen in the attached Contracts, with staff recommending the
low quote of $55,820.00 from Hardrives, Inc.
RECOMMENDATION:
Staff is recommending that the City Council accept the quotes and award a Contract to Hardrives, Inc. If
removed from consent, the recommended motion for this action is as follows:
“Move to accept the quotes and award a Contract to Hardrives, Inc. in the amount of $55,820.00 for the 2016 Street Full Depth Patching Project.” ATTACHMENT(S): 1. Hardrives, Inc. Construction Contract for the 2016 Street Full Depth Patching Project. 2. T.A. Schifsky & Sons, Inc. Construction Contract for the 2016 Street Full Depth Patching
Project.
Project No. 2016.115 General Conditions for 2016 Patching Project Page 1 of 2
State of Minnesota
Washington County
CONSTRUCTION CONTRACT FOR THE
2016 STREET FULL DEPTH PATCHING PROJECT
LAKE ELMO, MINNESOTA
This Contract, made this 17th day of May 2016, by the City of Lake Elmo, Minnesota (herinafter called the “Owner”) and Hardrives,
Inc. (hereinafter called the “Contractor”).
WITNESSETH that the parties hereto agree as follows:
The Contractor shall provide all labor, services, materials, equipment and machinery, transportation, tools, fuel, power, light, heat,
telephone, water, sanitary facilities, traffic control, temporary facilities, and all other facilities and incidentals, including profit and
overhead, necessary for the performance, testing, start‐up, and completion of the work as described herein:
IN WITNESS WHEREOF, the parties hereto have executed this contract as of the date first above written.
(Contractor) (City of Lake Elmo)
DESCRIPTION OF WORK: The Contractor shall complete full-depth pavement patch repairs along 14th Street North in Lake
Elmo, MN at the direction and in the locations specified by the City. All work shall be completed within the specified time frame
and under the terms and conditions provided within this Construction Contract, and in accordance with the “General Conditions”
shown in this contract. The contractor shall complete the proposed work by SEPTEMBER 30, 2016.
The extents of the patch excavation area shall be marked in the field by the City and must be sawcut perpendicular across the entire
street section from lip of curb to lip of curb. Sawcutting is incidental to the patching work.
Full-depth patching shall include the removal of the entire pavement surface layer, regardless of its thickness, over the patching
area. A Test Roll shall be completed with a fully loaded aggregate truck over the street and is incidental to the patching work. The
existing aggregate base areas that pass a Test Roll, as determined by the City inspector, shall be toleranced and re-compacted prior
to paving. The areas that do not pass a Test Roll, as determined by the City inspector, shall receive new Class 6 aggregate base
material to a depth specified by the City. Each excavation shall be inspected by the City to determine if additional base material
removal is needed to provide for a firm support. The aggregate base shall be toleranced to meet a minimum 2% crown to facilitate
drainage. The bituminous surface shall be replaced using two compacted layers and shall include tack coat between them. The
Bituminous Base Course (SPNWB230B) shall be a minimum 1.5” thick and the Bituminous Wear Course (SPWEA240B) shall be
a minimum 1.5” thick.
All bituminous testing shall be in accordance with MnDOT 2360 and is incidental to the patching work. The test procedure shall be
the Ordinary Compaction Method. Aggregate gradation testing shall be as specified in MnDOT 2211 and MnDOT 3138. Water
shall be applied at such times and in such amounts as necessary for proper aggregate compaction.
The City will make payment for the whole contract upon acceptance by the City of all work required hereunder and in compliance
with all the terms and conditions of this contract. Payment to the Contractor will be made for only the actual quantities of work
performed using the unit prices provided within this Contract and listed below, except that the total amount cannot exceed $55,820
without prior written authorization by the City Engineer. All materials, labor, tools and equipment needed to complete full-depth
pavement repair work that is not specifically itemized below with a unit price and estimated quantity shall be incidental to the
work. The City may add or reduce the project quantities in the best interest of the City.
Mobilization 1 LS - $3,000.00
Remove Bituminous and Tolerance – 3,700 SY x $2.85/SY = $10,545.00
1.5” SPNWB230B – 350 Tons x $52.00/Ton = $18,200.00
1.5” SPWEA240B – 350 Tons x $54.50/Ton = $19,075.00
Remove & Replace Class 6 Aggregate Base – 500 SY x $10.00/SY = $5,000.00
TOTAL ESTIMATED AMOUNT: $55,820.00
Project No. 2016.115 General Conditions for 2016 Patching Project Page 2 of 2
GENERAL CONDITIONS
I. CHANGES IN WORK. ‐ The Owner may at any time, make changes in the drawings and specifications, within the general scope thereof. If
such changes cause an increase or decrease in the amount due under this contract or in the time required for its performance, an
equitable adjustment will be made, and this contract will be modified accordingly by a “Contract Change Order”. No charge for any extra
work or material will be allowed unless the same has been ordered on such contract change order by the Owner and the price therefore
stated in the order.
II. INSPECTION OF WORK. ‐ All materials and workmanship will be subject to inspection, examination, and test, by the Owner, who will have
the right to reject defective material and workmanship or require its correction.
III. COMPLETION OF WORK. ‐ If the Contractor refuses or fails to complete the work within the time specified in this contract, or any
extension thereof, the Owner may terminate the Contractor’s rights to proceed. In such event the Owner may take over the work and
prosecute the same to completion by contract or otherwise, and the Contractor will be liable for any excess cost occasioned the Owner
thereby; and the Owner may take possession of and utilize in completing the work such materials and equipment as may be on the site of
the work and necessary therefore. If the Owner does not terminate the right of the Contract to proceed, the Contractor will continue the
work, in which event, actual damages for delay will be impossible to determine, and in lieu thereof, the Contractor may be required to
pay to the Owner the sum of $100 as liquidated damages for each calendar day of delay, and the Contractor will be liable for the amount
thereof: Provided, however, that the right of the Contractor to proceed will not be terminated because of delays in the completion of the
completion of the work due to unforeseeable causes beyond the Contractor’s control and without Contractor’s fault or negligence.
IV. RELEASES. ‐ Prior to final payment, the Contractor will submit evidence that all payrolls, material bills, and other indebtedness connected
with the work have been paid as required by the Owner.
V. OBLIGATION TO DISCHARGE LIENS. ‐ Acceptance by the Owner of the completed work performed by the Contractor and payment
therefore by the Owner will not relieve the Contractor of obligation to the Owner (which obligation is hereby acknowledged) to discharge
any and all liens for the benefit of subcontractors, laborers, material‐person, or any other persons performing labor upon the work or
furnishing material or machinery for the work covered by this contract, which have attached to or may subsequently attach to the
property, or interest of the Owner.
VI. NOTICES AND APPROVAL IN WRITING. ‐ Any notice, consent, or other act to be given or done hereunder will be valid only if in writing.
VII. CLEANING UP. ‐ The Contractor shall keep the premises free from accumulation of waste material and rubbish and at the completion of
the work shall remove from the premises all rubbish, implements and surplus materials.
VIII. WARRANTY. ‐ Contractor warrants and guarantees that title to all work, materials, and equipment covered by any Application for
Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of payment free and clear of all Liens. If
within one year after completion of the work, any work is found to be defective, Contractor shall promptly, without cost to the Owner,
correct such defective work as approved by the Owner.
IX. IDEMNIFICATION. ‐ Contractor shall defend and indemnify the city against claims brought or actions filed against the city or any of its
officers, employees or agents for property damage, bodily injury or death to third persons, arising out of or relating to contractors work
under the contract.
X. WORKERS’ COMPENSATION INSURANCE. ‐ Contractor shall provide a certificate of insurance showing evidence of workers’ compensation
coverage or provide evidence of qualification as a self‐insurer of workers’ compensation.
XI. LIABILITY INSURANCE REQUIREMENTS. – A certificate of insurance acceptable to the City shall be filed with the City prior to the
commencement of the work. The certificate and the required insurance policies shall contain a provision that the coverage afforded
under the contract will not be canceled or allowed to expire until at least 30 days prior written notice has been given to the city.
Contractor shall maintain commercial general liability (CGL) insurance with a limit of not less than $1,000,000 each occurrence and an
aggregate limit of not less than $2,000,000. The CGL insurance shall cover liability arising from premises, operations, independent
contractors, subcontractors, products‐completed operations, personal injury and advertising injury, and contractually‐assumed liability.
The city shall be named as an additional insured under the CGL. Contractor shall maintain automobile liability insurance, and if necessary,
umbrella liability insurance with a limit of not less than $1,000,000 each accident and an aggregate limit of not less than $2,000,000. The
insurance shall cover liability arising out of any auto, including owned, hired, and non‐owned autos.
Project No. 2016.115 General Conditions for 2016 Patching Project Page 1 of 2
State of Minnesota
Washington County
CONSTRUCTION CONTRACT FOR THE
2016 STREET FULL DEPTH PATCHING PROJECT
LAKE ELMO, MINNESOTA
This Contract, made this 17th day of May 2016, by the City of Lake Elmo, Minnesota (herinafter called the “Owner”) and T.A. Schifsky
& Sons, Inc. (hereinafter called the “Contractor”).
WITNESSETH that the parties hereto agree as follows:
The Contractor shall provide all labor, services, materials, equipment and machinery, transportation, tools, fuel, power, light, heat,
telephone, water, sanitary facilities, traffic control, temporary facilities, and all other facilities and incidentals, including profit and
overhead, necessary for the performance, testing, start‐up, and completion of the work as described herein:
IN WITNESS WHEREOF, the parties hereto have executed this contract as of the date first above written.
(Contractor) (City of Lake Elmo)
DESCRIPTION OF WORK: The Contractor shall complete full-depth pavement patch repairs along 14th Street North in Lake
Elmo, MN at the direction and in the locations specified by the City. All work shall be completed within the specified time frame
and under the terms and conditions provided within this Construction Contract, and in accordance with the “General Conditions”
shown in this contract. The contractor shall complete the proposed work by SEPTEMBER 30, 2016.
The extents of the patch excavation area shall be marked in the field by the City and must be sawcut perpendicular across the entire
street section from lip of curb to lip of curb. Sawcutting is incidental to the patching work.
Full-depth patching shall include the removal of the entire pavement surface layer, regardless of its thickness, over the patching
area. A Test Roll shall be completed with a fully loaded aggregate truck over the street and is incidental to the patching work. The
existing aggregate base areas that pass a Test Roll, as determined by the City inspector, shall be toleranced and re-compacted prior
to paving. The areas that do not pass a Test Roll, as determined by the City inspector, shall receive new Class 6 aggregate base
material to a depth specified by the City. Each excavation shall be inspected by the City to determine if additional base material
removal is needed to provide for a firm support. The aggregate base shall be toleranced to meet a minimum 2% crown to facilitate
drainage. The bituminous surface shall be replaced using two compacted layers and shall include tack coat between them. The
Bituminous Base Course (SPNWB230B) shall be a minimum 1.5” thick and the Bituminous Wear Course (SPWEA240B) shall be
a minimum 1.5” thick.
All bituminous testing shall be in accordance with MnDOT 2360 and is incidental to the patching work. The test procedure shall be
the Ordinary Compaction Method. Aggregate gradation testing shall be as specified in MnDOT 2211 and MnDOT 3138. Water
shall be applied at such times and in such amounts as necessary for proper aggregate compaction.
The City will make payment for the whole contract upon acceptance by the City of all work required hereunder and in compliance
with all the terms and conditions of this contract. Payment to the Contractor will be made for only the actual quantities of work
performed using the unit prices provided within this Contract and listed below, except that the total amount cannot exceed $55,820
without prior written authorization by the City Engineer. All materials, labor, tools and equipment needed to complete full-depth
pavement repair work that is not specifically itemized below with a unit price and estimated quantity shall be incidental to the
work. The City may add or reduce the project quantities in the best interest of the City.
Mobilization 1 LS – Included at no charge.
Remove Bituminous and Tolerance – 3,700 SY x $3.70/SY = $13,690.00
1.5” SPNWB230B – 350 Tons x $70.00/Ton = $24,500.00
1.5” SPWEA240B – 350 Tons x $71.00/Ton = $24,850.00
Remove & Replace Class 6 Aggregate Base – 500 SY x $10.00/SY = $5,000.00
TOTAL ESTIMATED AMOUNT: $68,040.00
Project No. 2016.115 General Conditions for 2016 Patching Project Page 2 of 2
GENERAL CONDITIONS
I. CHANGES IN WORK. ‐ The Owner may at any time, make changes in the drawings and specifications, within the general scope thereof. If
such changes cause an increase or decrease in the amount due under this contract or in the time required for its performance, an
equitable adjustment will be made, and this contract will be modified accordingly by a “Contract Change Order”. No charge for any extra
work or material will be allowed unless the same has been ordered on such contract change order by the Owner and the price therefore
stated in the order.
II. INSPECTION OF WORK. ‐ All materials and workmanship will be subject to inspection, examination, and test, by the Owner, who will have
the right to reject defective material and workmanship or require its correction.
III. COMPLETION OF WORK. ‐ If the Contractor refuses or fails to complete the work within the time specified in this contract, or any
extension thereof, the Owner may terminate the Contractor’s rights to proceed. In such event the Owner may take over the work and
prosecute the same to completion by contract or otherwise, and the Contractor will be liable for any excess cost occasioned the Owner
thereby; and the Owner may take possession of and utilize in completing the work such materials and equipment as may be on the site of
the work and necessary therefore. If the Owner does not terminate the right of the Contract to proceed, the Contractor will continue the
work, in which event, actual damages for delay will be impossible to determine, and in lieu thereof, the Contractor may be required to
pay to the Owner the sum of $100 as liquidated damages for each calendar day of delay, and the Contractor will be liable for the amount
thereof: Provided, however, that the right of the Contractor to proceed will not be terminated because of delays in the completion of the
completion of the work due to unforeseeable causes beyond the Contractor’s control and without Contractor’s fault or negligence.
IV. RELEASES. ‐ Prior to final payment, the Contractor will submit evidence that all payrolls, material bills, and other indebtedness connected
with the work have been paid as required by the Owner.
V. OBLIGATION TO DISCHARGE LIENS. ‐ Acceptance by the Owner of the completed work performed by the Contractor and payment
therefore by the Owner will not relieve the Contractor of obligation to the Owner (which obligation is hereby acknowledged) to discharge
any and all liens for the benefit of subcontractors, laborers, material‐person, or any other persons performing labor upon the work or
furnishing material or machinery for the work covered by this contract, which have attached to or may subsequently attach to the
property, or interest of the Owner.
VI. NOTICES AND APPROVAL IN WRITING. ‐ Any notice, consent, or other act to be given or done hereunder will be valid only if in writing.
VII. CLEANING UP. ‐ The Contractor shall keep the premises free from accumulation of waste material and rubbish and at the completion of
the work shall remove from the premises all rubbish, implements and surplus materials.
VIII. WARRANTY. ‐ Contractor warrants and guarantees that title to all work, materials, and equipment covered by any Application for
Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of payment free and clear of all Liens. If
within one year after completion of the work, any work is found to be defective, Contractor shall promptly, without cost to the Owner,
correct such defective work as approved by the Owner.
IX. IDEMNIFICATION. ‐ Contractor shall defend and indemnify the city against claims brought or actions filed against the city or any of its
officers, employees or agents for property damage, bodily injury or death to third persons, arising out of or relating to contractors work
under the contract.
X. WORKERS’ COMPENSATION INSURANCE. ‐ Contractor shall provide a certificate of insurance showing evidence of workers’ compensation
coverage or provide evidence of qualification as a self‐insurer of workers’ compensation.
XI. LIABILITY INSURANCE REQUIREMENTS. – A certificate of insurance acceptable to the City shall be filed with the City prior to the
commencement of the work. The certificate and the required insurance policies shall contain a provision that the coverage afforded
under the contract will not be canceled or allowed to expire until at least 30 days prior written notice has been given to the city.
Contractor shall maintain commercial general liability (CGL) insurance with a limit of not less than $1,000,000 each occurrence and an
aggregate limit of not less than $2,000,000. The CGL insurance shall cover liability arising from premises, operations, independent
contractors, subcontractors, products‐completed operations, personal injury and advertising injury, and contractually‐assumed liability.
The city shall be named as an additional insured under the CGL. Contractor shall maintain automobile liability insurance, and if necessary,
umbrella liability insurance with a limit of not less than $1,000,000 each accident and an aggregate limit of not less than $2,000,000. The
insurance shall cover liability arising out of any auto, including owned, hired, and non‐owned autos.
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: May 17, 2016
CONSENT
ITEM # 17
AGENDA ITEM: 2016 Crack Seal Project – Pay Request No. 1 (FINAL)
SUBMITTED BY: Ryan Stempski, Project Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer
Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: None. Final payment is proposed in accordance with the Contract for the
project.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to consider approving Pay Request No. 1 for the 2016
Crack Seal Project.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
The 2016 Crack Seal Project has been fully completed. The Project Engineer has prepared a
Certificate of Completion and is recommending acceptance of the improvements and release of
payment in full. The one year warranty period will begin on May 17, 2016, and will extend to
May 17, 2017.
City Council Meeting [Consent Agenda Item 17]
May 17, 2016
-- page 2 --
RECOMMENDATION:
Staff is recommending that the City Council consider approving, as part of the Consent Agenda,
Pay Request No. 1 to Gopher State Sealcoat, Inc. in the amount of $29,828.00 for the 2016
Crack Seal Project. If removed from the consent agenda, the recommended motion for the action
is as follows:
“Move to approve Pay Request No. 1 to Gopher State Sealcoat, Inc. in the amount of
$29,828.00 for the 2016 Crack Seal Project”.
ATTACHMENT(S):
1. Engineer’s Certificate of Completion dated May 17, 2016.
2. Gopher State Sealcoat Invoice dated April 27, 2016.
3. Lien Waiver dated May 5, 2016.
CITY OF LAKE ELMO, MN 2016 CRACK SEAL PROJECT PROJECT NO. 2016.119
CERTIFICATE OF COMPLETION
DATE OF ISSUANCE: May 17, 2016
OWNER: CITY OF LAKE ELMO, MN
CONTRACTOR: GOPHER STATE SEALCOAT, INC.
PROJECT NAME: 2016 CRACK SEAL PROJECT
PROJECT NO.: 2016.119
This Certification of Completion applies to all work under the Contract Documents
This Certification of Completion applies to the following specified parts of the Contract Documents
I do hereby certify that the work to which this Certificate applies has been constructed in
accordance with the Contract dated April 19, 2016. The above-mentioned improvement is hereby
declared to be complete and acceptance of this work is recommended.
DATE OF COMPLETION: May 17, 2016
Ryan Stempski Reg. No. 45395
FOCUS Engineering, Inc.
THE WARRANTY PERIOD BEGINS May 17, 2016 AND ENDS May 17, 2017