HomeMy WebLinkAbout#18 TKDA Auth 7- Section 34 Water Pressure
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: June 21, 2015
CONSENT
ITEM #18
AGENDA ITEM: Section 34 Water System Pressure Surge Investigation – Approve
Authorization No. 7 for TKDA.
SUBMITTED BY: Jack Griffin, City Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Cathy Bendel, Finance Director
Mike Bouthilet, Public Works
Chad Isakson, Assistant City Engineer
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: $16,500 to be funded through the Section 34 Water & Sewer Utility
Extension project fund which has been fully assessed against the benefitting properties.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to approve an Authorization with TKDA to complete
the Section 34 Water System Pressure Surge Investigation.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
The City water system is experiencing periodic pressure surges in the Savona development in the
transitional area between the high pressure zone (on top of the hill) and the low pressure zone
(townhome units along Keats Avenue at the bottom of the hill). Each time a hydrant or valve is
manipulated within this region the water system creates a surge causing pressures up to 150 PSI
in some homes, exceeding the rated pressure limits for private plumbing fixtures. Engineering
City Council Meeting [Regular Agenda Item 18]
June 21, 2015
-- page 2 --
and Public Works have met on several occasions to discuss and troubleshoot the issues and
causes and have concluded that a detailed investigation will be needed to identify all potential
sources for the pressure surges and to make recommendations (valve settings, operating
procedures, valve manipulation training etc.) to mitigate and manage the surges going forward.
In particular, the investigation will need to include pressure monitoring over an extended time
period and over various operating conditions and locations (tank levels, pumps on/off, varying
water use periods, etc.) to gain a better understanding of the issues. To monitor pressures
engineering and public works are proposing to purchase three pressure logger devices at a cost of
$500 each. Rather than rent them for this study it is believed that these devices will be useful to
the water operating staff as the water system continues to expand.
RECOMMENDATION:
Staff is recommending that the City Council approve, as part of the consent agenda, the Section
34 Water System Pressure Surge Investigation, Authorization No. 7 for TKDA. The
recommended motion for the action is as follows:
“Move to approve the Section 34 Water System Pressure Surge Investigation, Authorization
No. 7 for TKDA in an amount not to exceed $16,500.”
ATTACHMENT(S):
1. TKDA Authorization No. 7.
AUTHORIZATION No. 7 – SECTION 34 WATER PRESSURE INVESTIGATION Page 1 of 2
AUTHORIZATION No. 7
CITY OF LAKE ELMO, MINNESOTA – TKDA, INC.
PROFESSIONAL ENGINEERING SERVICES AGREEMENT
In accordance with GENERAL AGREEMENT between the City of Lake Elmo (“CITY”) and TKDA, Inc.
(“ENGINEER”), dated FEBRUARY 8, 1988 (“AGREEMENT”), the ENGINEER agrees to provide Professional
Engineering Support Services as follows:
SECTION 34 WATER PRESSURE INVESTIGATION
PROJECT OVERVIEW: The Project includes Engineering Services for the Section 34 Water Pressure
Investigation as detailed within this Authorization. The investigation includes identification of the
source of the water pressure surging issues experienced in Lake Elmo’s intermediate pressure zone in
the Section 34 area together corrective recommendations and best practices for ongoing operations.
SERVICES TO BE PROVIDED BY ENGINEER: TKDA, Inc. shall provide the following Professional
Engineering Services:
1. Perform a desktop review of infrastructure in place including irrigation valves, piping, pressure
reduction valve stations, and any additional information requested by TKDA.
2. Complete a field investigation including but not limited to data collection of the existing system
pressure, hydrant/valve operations, and review of the existing pressure reduction valve
settings.
3. Prepare a Technical Memorandum detailing the investigation procedures, preliminary findings
and an engineering opinion on the source(s) of the pressure surging issue, and provide written
recommendations for Best management practices and procedures for future operation of the
system.
4. Purchase the pressure logger devices (3) for the investigation. Provide the City the pressure
loggers after completion of the analysis and invoice the cost of the devices as a part of this
authorization.
CITY RESPONSIBILITIES: The city (or its consultants) will provide the following:
1. Provide data and information requested by TKDA.
2. Field work coordination when operation of hydrants/valves or access to pressure reduction
stations are requested.
AUTHORIZATION No. 7 – SECTION 34 WATER PRESSURE INVESTIGATION Page 2 of 2
TIMES FOR RENDERING SERVICES: ENGINEER shall perform its services and provide deliverables in a
timely manner.
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by ENGINEER under this AUTHORIZATION shall be the Assistant City Engineer.
Project correspondence must be addressed to:
Chad Isakson, P.E., Assistant City Engineer
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4283
Email: Chad.Isakson@FOCUSengineeringinc.com
COMPENSATION: Compensation to the ENGINEER for the Professional Services for the Section 34
Water Pressure Investigation shall be on an hourly rate basis in a not to exceed amount of $15,000
plus an expense reimbursement for 3 pressure logger devices in the estimated amount of $1,500.
Invoices shall be submitted once each month and should be sent to the attention of the Assistant City
Engineer.
ADDITIONAL SERVICES: If authorized by the City, ENGINEER shall furnish or obtain from others
Additional Services which are not considered under this Authorization. Such services shall be
compensated for on an Hourly Rate basis in an amount approved by the City prior to any services being
started or as otherwise mutually agreed. The City is not obligated to compensate ENGINEER for services
completed outside the approved scope of work which are completed prior to ENGINEER submitting a
written request to the City, and receiving written approval of the City.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Authorization, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGINEER is
authorized to begin performance of services upon receipt of a copy of this Authorization signed by CITY.
The Effective Date of this Task Order is June 21, 2016.
TKDA, INC. CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _______________________________ __
(Authorized Principal of the Firm) City Administrator