HomeMy WebLinkAbout06-21-2016 City Council Packet 2 of 3MAYOR AND COUNCIL COMMUNICATION
DATE: 6/21/16
Consent
ITEM #: 16
MOTION
AGENDA ITEM: Vue Exception to allow accessory structure closer to front lot line than principal
structure.
SUBMITTED BY: Stephen Wensman, Planning Director
REVIEWED BY: Kristina Handt, City Administrator
Emily Becker, City Planner
BACKGROUND:
Mae Vue and Jeerasak Poophakumpanart, the owner of a 40 acre parcel at 2675 Legion Avenue, are
requesting an exemption from the requirement that accessory structures be located no closer to the front
lot line than the principal structure. The City of Lake Elmo Code, Section 154.406, D. prohibits accessory
structures from being located closer to the front lot line than the principal structure unless by Resolution
of City Council, an exception is granted. The owners are requesting such an exemption.
This item was pulled from the 5/17/16 Consent Agenda so Staff could provide additional information to
the Council. Staff has again placed this item on the Consent Agenda and is recommending approval.
ISSUE BEFORE COUNCIL:
Approve Resolution 2016-43 to grant an exemption to allow an accessory structures to be located closer
to the front lot line than the principal structure.
PROPOSAL DETAILS/ANALYSIS:
The owners of 2675 Legion Avenue, recently constructed a home on the northwest corner of their property,
more or less on the high point of the property. Access to their property is from a long driveway that extends
over an unbuilt Legion Avenue right of way, to the south of the property. The City Council recently granted
an encroachment to the Legion Avenue right of way for their driveway in order to allow the construction
of the driveway on the Legion Avenue right of way, providing access to the property. Although the property
access is to the south, the front property line is along the Legion Avenue easement on the west side of the
property. This unbuilt Legion Avenue easement is 41.48 foot wide, at present, too narrow to construct a
street without additional right of way from the property to the west. There are no plans to construct an
extension of Legion Avenue, nor are there any public utilities planned for the easement at this time. The
owners would like to locate an accessory structure to the south and west of their home, closer to the front
property line than the principal structure. The new accessory structure would be located 25’ from the Legion
Avenue easement. The home is located 68.4 feet from Legion Avenue easement (the front property line).
FISCAL IMPACT:
None
OPTIONS:
To deny or approve.
RECOMMENDATION:
Staff recommends the City Council approve Resolution 2016-43 approving an exemption to allow
an accessory structure closer to the front property line than the principal structure. If this item is removed
from the Consent Agenda, Staff recommends the following motion:
“Move to recommend approval of Resolution 2016-43 approving an exemption to allow an
accessory structure closer to the front property line than the principal structure at 2675 Legion
Avenue”. ATTACHMENT:
•Resolution 2016-43
Resolution 2016-43
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2016-43
A RESOLUTION APPROVING AN EXEMPTION FROM CODE SECTION 154.406, D TO
ALLOW AN ACCESSORY STRUCTURE CLOSER TO FRONT PROPERTY LINE THAN
PRINCIPAL STRUCTURE.
WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing
under the laws of the State of Minnesota; and
WHEREAS, the owners of a residential property at 2675 Legion Avenue, Mae Vue and
Jeerasak Poophakumpanart would like to construct an accessory structure to be located closer to the front
property line than the principal structure; and
WHEREAS, the City of Lake Elmo Code of Ordinances, Section 154.406, D prohibits
accessory structures closer to front property lines than the principal structure unless an
exemption is granted by City Council resolution; and
WHEREAS, the City Council considered the said matter at its May 17, 2016 meeting;
and
NOW, THEREFORE, based on the information received, the City Council makes the
following:
FINDINGS
1.The proposed accessory structure will comply with the City’s accessory structure
ordinances and zoning district regulations, with the exception as approved by this
Resolution.
2. The proposed accessory structure location has been reviewed by the City Staff and
the City Engineer and the location appears to poses no threat, nor impact any City
project or plans.
3. The proposed accessory structure will pose no threat to the health, safety and welfare
of the public.
BE IT RESOLVED THAT the City Council does hereby approve the exemption from the front
property setback, complying with Section 154.406, D of the City of Lake Emo’s Code of
Ordinances.
This resolution was adopted by the City Council of the City of Lake Elmo on this 17th day of
May, 2016.
Resolution 2016-43
_____________________________
Mike Pearson, Mayor
ATTEST:
___________________________
Julie Johnson, City Clerk
MAYOR AND COUNCIL COMMUNICATION
DATE: 6/21/16
CONSENT
ITEM #: 17
AGENDA ITEM: Comprehensive Plan Text Amendment to Rural Single Family Land Use
Designation
SUBMITTED BY: Stephen Wensman, Planning Director
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Emily Becker, City Planner
BACKGROUND:
On April 19, 2016, the Lake Elmo City Council approved a Comprehensive Plan Text Amendment to the
City’s Wastewater Facilities Plan by adding three properties to the Village MUSA. The Metropolitan
Council, upon reviewing the amendment, requested that the Rural Single Family land use designation be
amended to be in compliance with areas guided for sewer. The Comprehensive Land Use Plan
designation is defined as being served by private on-site well and septic systems. The proposed new
definition will allow for municipal sanitary sewer where the City Council deems it practical. This
amendment will allow for municipal sanitary sewer without changing the guided density. Presently, there
are two areas where properties guided for Rural Single Family are within a MUSA area; the Old Village
and in the Tri-Lakes area near Oakdale.
ISSUE BEFORE COUNCIL:
The Council is respectfully being asked to consider a Comprehensive Plan Text Amendment to the Rural
Single Family land use definition to allow municipal sanitary sewer where deemed practical by the City
Council.
PROPOSAL DETAILS/ANALYSIS:
The current Rural Single Family planned land use category definition reads:
RURAL SINGLE FAMILY – This category defines a large portion of the City that was
historically platted for conventional subdivision prior to 2005, but has been and will continue to
be serviced by private on-site well and septic systems. Limited locations within this classification
are allowed to have two-family dwellings based on zoning. [Corresponding Zoning District(s): R-
1, R-2]
The category as defined is served by private on-site well and septic systems. In addition, the definition
references zoning districts that are no longer in existence. The corresponding zoning district is RS - Rural
Single Family. The proposed definition will allow on-site well and septic systems, unless the City
Council considers connection to the sanitary sewer where practical. The corresponding zoning district is
City Council Meeting June 21, 2016 Consent Agenda Item #17
Page 2
RS - Rural Single Family. The proposed Rural Single Family planned land use category reads (inserted
text is underlined):
RURAL SINGLE FAMILY – This category defines a large portion of the City that was
historically platted for conventional subdivision prior to 2005, but has been and will continue to
be serviced by private on-site well and septic systems unless within a Metropolitan Urban Service
Area (MUSA). If within a MUSA, the City Council may consider connection to the sanitary
sewer system where practical. Limited locations within this classification are allowed to have
two-family dwellings based on zoning. [Corresponding Zoning District(s): RS – Rural Single
Family]
This proposed amendment has been reviewed by the Metropolitan Council Staff and will require formal
Metropolitan Council approval.
PUBLIC HEARING:
A public hearing on the Comprehensive Plan Text Amendment was held on June 13, 2016. Nobody from
the public spoke for or against the amendment. During the Planning Commission discussion,
Commissioner Dunn opposed the amendment, stating that residents should have a choice whether or not
to connect to municipal sanitary sewer. The Planning Commission recommended approval of the
Amendment.
FISCAL IMPACT:
None.
OPTIONS:
The City Council should consider whether the amended land use category definition is acceptable or not.
RECOMMENDATION:
Staff and the Planning Commission respectfully request, as part of tonight’s consent agenda, that the City
Council approve the Comprehensive Plan Text Amendment amending the Rural Single Family land use
category definition to allow connection to municipal sanitary sewer where the City Council deems it
practical by consent. Comprehensive Plan Text Amendments require a 4/5 affirmative vote of the City
Council.
If removed from the Consent Agenda, the recommended action can be completed through the following
motion:
“Move to approve Resolution 2016-50 Amending the City of Lake Elmo Comprehensive Land Use
Plan land use designation for Rural Single Family to allow connection to municipal sanitary sewer
where deemed practical by the Lake Elmo City Council. ”
ATTACHMENTS:
1) Resolution 2016-50
2) Planning Commission Report
3) June 13, 2016 Planning Commission Minutes
Resolution 2016-50
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2016- 50
A RESOLUTION APPROVING AN AMENDMENT TO THE CITY OF LAKE ELMO
COMPREHENSIVE LAND USE PLAN RURAL SINGLE FAMILY LAND USE CATEGORY
DEFINITION TO ALLOW CONNECTION TO MUNICIPAL SANITARY SEWER WHERE
DEEMED PRACTICAL BY THE CITY COUNCIL.
WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing
under the laws of the State of Minnesota; and
WHEREAS, The City of Lake Elmo has established a Comprehensive Plan that provides
complication of background data, policy statements, standards, and maps, which help to guide
the future physical, social, and economic development of the City; and
WHEREAS, The City Council has approved the Old Village Phase 2 Street and Utility
Improvement Project which will extend municipal sanitary sewer to some properties within the
Old Village MUSA ; and
WHEREAS, the City has approved projects to connect properties within the Tri-Lakes
Sewer Service Area to sanitary sewer;
WHEREAS, many of the properties within these areas have the land use designation of
Rural Single Family in the City of Lake Elmo Comprehensive Plan; and
WHEREAS, the Rural Single Family land use definition states these properties have
been and will continue to be serviced by private on-site well and septic systems; and
WHEREAS, the Rural Single Family land use definition should be amended to allow for
municipal sanitary sewer connection consistent with the City’s practice; and
NOW, THEREFORE, based on the testimony elicited and the information received, the
City makes the following:
Findings
1. The text amendment will not impact lot density or any other standards for the affected
properties.
2. The Metropolitan Council has administratively reviewed the text amendment has
appeared to have no objection and had waived adjacent jurisdictional review.
3. The expansion of the MUSA is consistent with improving the health, safety and
welfare of the City of Lake Elmo residents.
Resolution 2016-50
4. The text amendment will remove an inconsistency between the MUSA designation
and Land Use category definition in the City’s Comprehensive Plan.
NOW, THEREFORE, BE IT RESOLVED that based on the foregoing, the Lake Elmo City
Council does hereby approve the Lake Elmo Comprehensive Plan Text Amendment to allow
connection to municipal sanitary sewer where deemed practical by the City Council, subject to
and contingent upon the following:
1. The Metropolitan Council’s approval of the Comprehensive Plan Text Amendment.
This resolution was adopted by the City Council of the City of Lake Elmo on this 21 day of June,
2016.
_____________________________
Mike Pearson, Mayor
ATTEST:
___________________________
Julie Johnson, City Clerk
1
PLANNING COMMISSION
DATE: 6/13/16
AGENDA ITEM: 4D – PUBLIC HEARING
CASE # 2016-19
ITEM: Comprehensive Plan Text Amendment to Rural Single Family Land Use
Designation
SUBMITTED BY: Stephen Wensman, Planning Director
REVIEWED BY: Emily Becker, City Planner
Lisa Barajas, Metropolitan Council
SUMMARY AND ACTION REQUESTED:
The Planning Commission is requested to review a Comprehensive Plan Text Amendment to bring
the planned official land use plan category, Rural Single Family, into compliance with the
Comprehensive Plan’s Wastewater Facilities Plan as recently amended. Staff is recommending the
Planning Commission recommend approval of the Comprehensive Plan Text Amendment.
GENERAL INFORMATION
Applicant: City of Lake Elmo
Location: Areas guided as Rural Single Family
Request: A Comprehensive Plan Text Amendment to bring the planned official land use
plan category, Rural Single Family, into compliance with the Comprehensive
Plan’s Wastewater Facilities Plan as recently amended.
History: On 4/19/16, the City Council approved an amendment to the Village MUSA to
add three properties. The Metropolitan Council requested that the Rural Single
Family land use designation be amended to be in compliance with areas guided
for sewer.
REQUEST DETAILS:
The Lake Elmo City Council, on April 19, 2016, approved a Comprehensive Plan Text Amendment
to the City’s Wastewater Facilities Plan by adding three properties to the Village MUSA. The
Metropolitan Council, upon reviewing the amendment, requested that the Rural Single Family land
use designation be amended to be in compliance with areas guided for sewer. Presently, there are two
areas where properties guided for Rural Single Family are within a MUSA area; the Old Village and
in the Tri-Lakes area near Oakdale.
Planning Commission Meeting June 13, 2016 Public Hearing Item 4d-Action Item
2
The current Rural Single Family planned land use category reads:
RURAL SINGLE FAMILY – This category defines a large portion of the City that was
historically platted for conventional subdivision prior to 2005, but has been and will continue to
be serviced by private on-site well and septic systems. Limited locations within this classification
are allowed to have two-family dwellings based on zoning. [Corresponding Zoning District(s): R-
1, R-2]
The category as defined is served by private on-site well and septic systems. In addition, the
definition references zoning districts that are no longer in existence. The corresponding zoning
district is RS - Rural Single Family. The proposed definition will allow on-site well and septic
systems, unless the City Council considers connection to the sanitary sewer practicable. The
corresponding zoning district is RS - Rural Single Family. The proposed Rural Single Family
planned land use category reads (inserted text is underlined):
RURAL SINGLE FAMILY – This category defines a large portion of the City that was historically
platted for conventional subdivision prior to 2005, but has been and will continue to be serviced
by private on-site well and septic systems unless within a Metropolitan Urban Service Area
(MUSA). If within a MUSA, the City Council may consider connection to the sanitary sewer
system where practical. Limited locations within this classification are allowed to have two-
family dwellings based on zoning. [Corresponding Zoning District(s): RS – Rural Single Family]
ANALYSIS:
The RS-Zoning District as defined in City Code Section 154.400, D. reads:
RS Rural Single Family District. The RS District is established for lands that have
already been platted as conventional residential subdivisions prior to the 2005 adoption of
the Comprehensive Land Use Plan. This district provides an environment of
predominantly single-family detached dwellings on moderately sized lots in areas that
have typically not been provided with public sanitary sewer services.
Staff believes the definition of RS - Rural Single Family suggests on-site septic systems, but does not
preclude them from connecting to public sewer. No change to the RS Rural Single Family definition
is needed and the proposed Comprehensive Plan Text Amendment will bring the Land Use Plan in
compliance with the Wastewater Facilities Plan without changing existing densities, setbacks, etc.
DRAFT FINDINGS:
The City Code does not require specific findings for comprehensive plan amendments, however,
Staff is suggesting the following findings in support of the amendment:
1. The comprehensive plan text amendment will bring the Lake Elmo Comprehensive
Land Use Plan into conformity with the Comprehensive Wastewater Facilities Plan.
2. The comprehensive plan text amendment will not affect underlying density or zoning
code regulations.
Planning Commission Meeting June 13, 2016 Public Hearing Item 4d-Action Item
3
3. The Metropolitan Council has administratively reviewed the amendment, has no
objection, and had waived adjacent jurisdictional review.
RECOMMENDATION:
Staff is recommending the Planning Commission recommend approval of the Comprehensive Plan
Text Amendment with the following motion:
“Move to recommend the City Council approve the comprehensive plan text amendment to amend
the planned land use category in the Comprehensive Land Use Plan to read:
RURAL SINGLE FAMILY – This category defines a large portion of the City that was historically
platted for conventional subdivision prior to 2005, but has been and will continue to be serviced
by private on-site well and septic systems unless within a Metropolitan Urban Service Area
(MUSA). If within a MUSA, the City Council may consider connection to the sanitary sewer
system where practical. Limited locations within this classification are allowed to have two-
family dwellings based on zoning. [Corresponding Zoning District(s): RS – Rural Single Family]
ATTACHMENTS:
None
ORDER OF BUSINESS:
- Introduction ........................................................................................ Planning Staff
- Report by Staff ................................................................................... Planning Staff
- Questions from the Commission ............................ Chair & Commission Members
- Open the Public Hearing .................................................................................. Chair
- Close the Public Hearing .................................................................................. Chair
- Discussion by the Commission .............................. Chair & Commission Members
- Action by the Commission ..................................... Chair & Commission Members
Lake Elmo Planning Commission Minutes; 6-13-16
City of Lake Elmo
Planning Commission Meeting
Minutes of June 13, 2016
Chairman Williams called to order the meeting of the Lake Elmo Planning Commission at
7:00 p.m.
COMMISSIONERS PRESENT: Dunn, Fields, Larson, Griffin, Dodson, and Williams.
COMMISSIONERS ABSENT: Haggard, Kreimer, & Lundquist
STAFF PRESENT: Planning Director Wensman & City Planner Becker
Approve Agenda:
Agenda is approved as presented.
Approve Minutes: June 23, 2016
M/S/P:Dunn/Fields, move to approve the June 23, 2016 minutes as amended, Vote: 4-0,
motion carried with Griffin and Dodson not voting.
Public Hearing – Easement Vacation 8574 Eagle Point circle
Becker started her presentation regarding the easements related to Auto Owners water
mains and hydrants. The city moved the location of the water mains and hydrants, so
new easements were recorded. Auto Owners is requesting the old easments be
vacated.
Public hearing opened at 7:07 pm
No one spoke
There was written comment from Machine Shed, but once the application was
explained to them, they were fine with the item.
Public hearing closed at 7:08 pm
Dunn stated it was straight forward and she has no issue with it.
M/S/P: Dunn/Griffin, move to recommend approval of the request to vacate the
easement as outlined in Exhibit B-2/2138129 Water Main Easement as recorded, Vote:
6-0, motion carried unanimoulsy.
2
Lake Elmo Planning Commission Minutes; 6-13-16
Public Hearing – Zoning Text Amendment – To amend the fencing regulations to allow
administrative approval of encroachment agreements.
Becker stated that the current code the way it is written requires any easement
encroachment agreement be approved by the City Council. This change would allow for
those agreements to be approved administratively by staff. The current process is time
consuming for staff as well as the resident and delays the issuing of the permit. The fee
for this agreement is $150.00, making a fence permit $225.00. In the future, we might
be able to reduce the fee with the reduced staff time.
Dunn is wondering why this was added in 2011 and how often this happens. Becker
stated that it has happened quite a bit since she has been here. The new developments
all have the utility easements located on the properties.
Larson asked what happens if there is conflicting rules between the City and the HOA.
Becker stated that this change doesn’t in effect change any of the rules other than who
is allowed to make the approval. Wensman stated that the City does not regulate HOA
covenants between property owners.
Public hearing opened at 7:20 pm
No one spoke and there was no written comments received.
Public hearing closed at 7:21 pm
M/S/: Fields/Dunn, would like to add a sentence at the end of the suggested motion to
read that the fee be reduced to $50 when the city Council considers the fee schedule.
M/S/P: Williams/Dunn, would like to make an amendment to the motion that the fee
not be specified, but only that it be reduced. Vote: 6-0, motion carried unanimously.
Oringinal motion as amended to add “that the fee be reduced when the City Council
considers the fee schedule”, Vote: 6-0, motion carried unanimously.
M/S/P: Dodson/Griffin, move to recommend approval of an ordinance to amend
Chapter 154: Zoning Code; Section 205: Fencing Regulation; Subp. (D) (6) to allow
approval of a fence easement encroachment agreement by the Planning Director or
his/her designee after review and approval and furthermore recommends that the fee
be reduced when the City Council considers the fee schedule, Vote: 6-0, motion carried
unanimously.
3
Lake Elmo Planning Commission Minutes; 6-13-16
Public Hearing – Zoning Text Amendment – To amend the accessory Structure
Regulations
Becker stated that staff is bringing forward 3 suggested changes to the accessory
structure ordinance. The first is to exempt fish houses to the requirement that a
primary structure not be required prior to a fish house being located on the lot. The
second is removing the portion of the code that allows an accessory structure to be
located closer to the front lot line by resolution. Staff would like this removed because
it is essentially granting a variance without the requirement to go through the variance
process. The third change is to change the size of a tool shed from a maximum of 160
square feet to 200 square feet and move that to the exempted section with one being
allowed on a residential lot.
Dodson is wondering why a fishhouse would be any different than something like a
camper trailer. Wensman stated that the concern was that there would be storage on
vacant lots if there are not specific standards.
Williams was wondering if the tool shed size is calculated into the overall size of
accessory structure. Becker stated that no it would not be included for size or number.
Dodson thinks it might be beneficial to have the 120 square feet in the definition.
Becker stated that there are fish houses that are larger. The size limit only applies if
there is no primary structure.
Public hearing opened at 7:47 pm
No one spoke and there was no written comments received.
Public hearing closed at 7:48 pm
Williams is not in favor of exempting the tool shed from size and number in all districts
and thinks it should adhere to the limitations of the district. Wensman stated that if
that is the direction the Planning Commission wants to go, there should be some
language added in the old “F” and would specify one.
M/S/P: Williams/Fields, move to change the wording of the definition for storage or tool
sheds to be: Storage or Tool sheds: One storage or tool shed as defined in this section
may be placed on any lot in addition to the permited number of accessory buildings,
provided it complies with the maximum area requirements of the zoning district,
providing a principal structure exists on the lot. Vote: 6-0, motion carried unanimously.
Williams is wondering about separate lots of record owned by the person who lives next
door. This might open up the door for someone to have a fishhouse on both lots.
4
Lake Elmo Planning Commission Minutes; 6-13-16
Becker stated as it is written, that could happen. Williams is uncomfortable with this
possibility because it could create a lot of clutter for the neighbors.
Dodson thinks that this seems like a really small problem and that there is n ot a lot of
lots this would pertain to. Dodson wants the 3 proposals to be separate motions.
Williams would like to separate out the fishhouse portion and know how many parcels
this would apply to.
M/S/P:Dodson/Williams, Move to recommend approval of Ordinance 08- the exception
to 154.406, subd D, and the definition of “storage or tool shed” as amended, Vote: 6-0,
motion carried unanimously.
Becker stated that there is roughly 50 parcels that are adjacent to the lake and could
potentially put a fishhouse on the lot without a primary structure. Fields is comfortable
with the language written as this is not a permanent structure.
M/S/P:Williams/Dodson, move to recommend the following finding of fact that there is
some concern that if every one of these lots had a fishhouse, it may lead to complaints
by the neighbors. Vote: 6-0, motion carried unanimously.
M/S/P: Dunn/Griffin, Move to recommend approval of the accessory structure
ordinance as it pertains to fishhouses as amended, Vote: 6-0, motion carried
unanimously.
Public Hearing – Comprehensive Plan Text Amendment to allow connection to
sanitary sewer in Rural Single Family zoning where practical.
Wensman stated that the Met Council suggested that we amend the definition of the
rural single family definition in the Comprehensive Plan so that it would allow
connections to sanitary sewer where reasonable.
Dodson would like it to also read to municipal water where practical. Wensman stated
that we are really just talking about areas in the MUSA and the water system extends
outside the MUSA.
Williams is wondering about the term practical. Wensman stated that it was what was
suggested by Lisa Barajas at the Met Council. Williams asked what if the resident did
not want to connect. Wensman stated that the connection would be determined by the
City Council.
Dunn would like the “when practical” changed to “when requested”, which gives the
resident much more control. Wensman stated that the MUSA dictates where the sewer
can go, but this basically allows for Rural Single Family to connect.
5
Lake Elmo Planning Commission Minutes; 6-13-16
Public hearing opened at 8:34 pm
No one spoke and there was no written comments received.
Public hearing closed at 8:35 pm
Dunn would like to see the option of sewer or private septic. She doesn’t think that
they should be forced to connect to sewer. Wensman stated that the comprehensive
Plan is not in compliance with the projects that we are doing. If we don’t do this
amendment, the land use designation would need to be changed.
M/S/P: Fields/Dodson, Move to recommend the City Council approve the
comprehensive plan text amendment to amend the planned land use category in the
Comprehensive Land Use Plan to read as written, Vote: 5-1, motion carried. Dunn
voted no because she feels it is important that people have an option regarding
connection.
Business Item – Zoning Text Amendment to discuss the VMX Zoning Text .
Wensman began his presentation by showing the areas that are zoned as general
business, but guided as VMX in the Comprehensive Plan. To bring the zoning into
compliance with the Comprehensive Plan, Wensman would like to see these properties
rezoned. Wensman believes by rezoning, it would actually eliminate some non
conformities. The area that would change the most, would be in the Northern area by
39th Street. Wensman stated that this was intended to bring the district more in
conformance than it is now and should be done as a district vs. one at a time. If there
are things about the district that the Commission does not like, then changes should be
made to the district.
Dunn feels that the premise is based on the Village Master Plan. Where is the master
plan? Wensman stated that the plan was based on transfer of density and he is not sure
what happened to that plan. Dunn did a rough calculation on what could be done if the
maximum densities were used. With her calculation, there is potential for upwards of
3000 people. She feels it is quite intense without a lot of restrictions. She would like to
see more work done on the reductions for the comprehensive plan and possibly look at
form based code. She thinks we should take our time and do this r ight.
Dunn pointed out some of the differences between GB and VMX. She feels one of the
biggest differences is the impervious surface coverage maximum goes from 40% based
on acreage in GB to 75% in VMX.
Fields is confused because if the comprehensive plan is guided the way we want it, the
rezoning should happen. If we are considering if the guiding is correct, then it should
not be rezoned, but should be discussed what the guiding should be.
6
Lake Elmo Planning Commission Minutes; 6-13-16
Larson thinks that what brings the guiding for VMX into question is that the density of
this area is in transition. Larson understands the feeling of discomfort as this zone is
less restrictive. There are still a lot of questions that make it uncomfortable for peo ple
to buy into this zone.
Williams thinks it would be good to ask the City Council if past projections of population
in this area are still valid.
Dodson is wondering how big a project form based code is. Wensman stated that it is
something that takes some technical skill to do and it would need to be contracted out.
Williams thinks it would help facilitate the vision, but would not be necessary to do the
rezone.
M/:Dunn/, Move to recommend not rezoning the parcels to VMX until the City Council
can review the target numbers and there is a form based code, motion dies for lack of
second.
M/S/P: Williams/Dunn, Move to ask the City Council to give the Planning Commission
guidance on updated population and development projections for the area s guided for
VMX in the Old Village, Vote: 6-0, motion carried unanimously.
Fields would like to know what the driving force was for the VMX. If it was to bring
more people to the downtown to make it more vibrant, or if it was to meet the Met
Council mandates for housing population. Williams recollection was that it was for both
of those reasons in addition to form based code to make it a more picturesque
downtown and to incorporate business and residential in the same building, which
general business does not do.
M/S/P: Williams/Dodson, Move to ask the City Council to approve funds for a consultant
to work on a form based code for the downtown Old Village, Vote: 6-0, motion carried
unanimously.
Fields would like any information that he could get on form based code. Williams
believes that the City has a couple of videos on this topic.
Staff Updates
1. Upcoming Meetings
a. June 27, 2016
b. July 11, 2016
Commission Concerns
7
Lake Elmo Planning Commission Minutes; 6-13-16
Dunn asked about the AUAR. Wensman stated that the City is overdue for the update
and it is in the City Engineers hands right now.
Meeting adjourned at 9:28 pm
Respectfully submitted,
Joan Ziertman
Planning Program Assistant
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: June 21, 2015
CONSENT
ITEM #18
AGENDA ITEM: Section 34 Water System Pressure Surge Investigation – Approve
Authorization No. 7 for TKDA.
SUBMITTED BY: Jack Griffin, City Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Cathy Bendel, Finance Director
Mike Bouthilet, Public Works
Chad Isakson, Assistant City Engineer
SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda):
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: $16,500 to be funded through the Section 34 Water & Sewer Utility
Extension project fund which has been fully assessed against the benefitting properties.
SUMMARY AND ACTION REQUESTED:
The City Council is respectfully requested to approve an Authorization with TKDA to complete
the Section 34 Water System Pressure Surge Investigation.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION:
The City water system is experiencing periodic pressure surges in the Savona development in the
transitional area between the high pressure zone (on top of the hill) and the low pressure zone
(townhome units along Keats Avenue at the bottom of the hill). Each time a hydrant or valve is
manipulated within this region the water system creates a surge causing pressures up to 150 PSI
in some homes, exceeding the rated pressure limits for private plumbing fixtures. Engineering
City Council Meeting [Regular Agenda Item 18]
June 21, 2015
-- page 2 --
and Public Works have met on several occasions to discuss and troubleshoot the issues and
causes and have concluded that a detailed investigation will be needed to identify all potential
sources for the pressure surges and to make recommendations (valve settings, operating
procedures, valve manipulation training etc.) to mitigate and manage the surges going forward.
In particular, the investigation will need to include pressure monitoring over an extended time
period and over various operating conditions and locations (tank levels, pumps on/off, varying
water use periods, etc.) to gain a better understanding of the issues. To monitor pressures
engineering and public works are proposing to purchase three pressure logger devices at a cost of
$500 each. Rather than rent them for this study it is believed that these devices will be useful to
the water operating staff as the water system continues to expand.
RECOMMENDATION:
Staff is recommending that the City Council approve, as part of the consent agenda, the Section
34 Water System Pressure Surge Investigation, Authorization No. 7 for TKDA. The
recommended motion for the action is as follows:
“Move to approve the Section 34 Water System Pressure Surge Investigation, Authorization
No. 7 for TKDA in an amount not to exceed $16,500.”
ATTACHMENT(S):
1. TKDA Authorization No. 7.
AUTHORIZATION No. 7 – SECTION 34 WATER PRESSURE INVESTIGATION Page 1 of 2
AUTHORIZATION No. 7
CITY OF LAKE ELMO, MINNESOTA – TKDA, INC.
PROFESSIONAL ENGINEERING SERVICES AGREEMENT
In accordance with GENERAL AGREEMENT between the City of Lake Elmo (“CITY”) and TKDA, Inc.
(“ENGINEER”), dated FEBRUARY 8, 1988 (“AGREEMENT”), the ENGINEER agrees to provide Professional
Engineering Support Services as follows:
SECTION 34 WATER PRESSURE INVESTIGATION
PROJECT OVERVIEW: The Project includes Engineering Services for the Section 34 Water Pressure
Investigation as detailed within this Authorization. The investigation includes identification of the
source of the water pressure surging issues experienced in Lake Elmo’s intermediate pressure zone in
the Section 34 area together corrective recommendations and best practices for ongoing operations.
SERVICES TO BE PROVIDED BY ENGINEER: TKDA, Inc. shall provide the following Professional
Engineering Services:
1. Perform a desktop review of infrastructure in place including irrigation valves, piping, pressure
reduction valve stations, and any additional information requested by TKDA.
2. Complete a field investigation including but not limited to data collection of the existing system
pressure, hydrant/valve operations, and review of the existing pressure reduction valve
settings.
3. Prepare a Technical Memorandum detailing the investigation procedures, preliminary findings
and an engineering opinion on the source(s) of the pressure surging issue, and provide written
recommendations for Best management practices and procedures for future operation of the
system.
4. Purchase the pressure logger devices (3) for the investigation. Provide the City the pressure
loggers after completion of the analysis and invoice the cost of the devices as a part of this
authorization.
CITY RESPONSIBILITIES: The city (or its consultants) will provide the following:
1. Provide data and information requested by TKDA.
2. Field work coordination when operation of hydrants/valves or access to pressure reduction
stations are requested.
AUTHORIZATION No. 7 – SECTION 34 WATER PRESSURE INVESTIGATION Page 2 of 2
TIMES FOR RENDERING SERVICES: ENGINEER shall perform its services and provide deliverables in a
timely manner.
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by ENGINEER under this AUTHORIZATION shall be the Assistant City Engineer.
Project correspondence must be addressed to:
Chad Isakson, P.E., Assistant City Engineer
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4283
Email: Chad.Isakson@FOCUSengineeringinc.com
COMPENSATION: Compensation to the ENGINEER for the Professional Services for the Section 34
Water Pressure Investigation shall be on an hourly rate basis in a not to exceed amount of $15,000
plus an expense reimbursement for 3 pressure logger devices in the estimated amount of $1,500.
Invoices shall be submitted once each month and should be sent to the attention of the Assistant City
Engineer.
ADDITIONAL SERVICES: If authorized by the City, ENGINEER shall furnish or obtain from others
Additional Services which are not considered under this Authorization. Such services shall be
compensated for on an Hourly Rate basis in an amount approved by the City prior to any services being
started or as otherwise mutually agreed. The City is not obligated to compensate ENGINEER for services
completed outside the approved scope of work which are completed prior to ENGINEER submitting a
written request to the City, and receiving written approval of the City.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Authorization, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGINEER is
authorized to begin performance of services upon receipt of a copy of this Authorization signed by CITY.
The Effective Date of this Task Order is June 21, 2016.
TKDA, INC. CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _______________________________ __
(Authorized Principal of the Firm) City Administrator
MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: June 21, 2016
CONSENT
ITEM #21
MOTION
AGENDA ITEM: Authorize RFP for Information Technology Services
SUBMITTED BY: Cathy Bendel, Finance Director
THROUGH: Cathy Bendel, Finance Director
REVIEWED BY: Kristina Handt, City Administrator
SUGGESTED ORDER OF BUSINESS:
- Introduction of Item .............................................................. City Administrator
- Report/Presentation…………………………………………City Administrator
- Questions from Council to Staff ............................................. Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Finance
FISCAL IMPACT: None
SUMMARY AND ACTION REQUESTED: As part of its Consent Agenda, the City Council
is asked to approve issuance of an RFP seeking quotes for comparable Information Technology
services from vendors other than the City of Roseville (already have their quote for 2017
services). No specific motion is needed as this is recommended to be part of the Consent
Agenda.
BACKGROUND INFORMATION: The City of Lake Elmo recently received the projected
2017 budgeted costs for Information Services to be provided by the City of Roseville. The
quoted rate increase was an increase of 25% over 2016. As shown in the attachment, the
cumulative rate increase since 2012 is 216%.
RECOMMENDATION: Staff brought this suggestion to the City Finance Committee on June
14th and it was unanimously agreed to recommend to the City Council that an RFP should be
issued to obtain quotes for comparable services from other vendors.
City Council Meeting [Consent Agenda Item 21]
June 21, 2016
-- page 2 --
ATTACHMENT:
1. Recap of Roseville historical costs
MAYOR AND COUNCIL COMMUNICATION
DATE: 06/21/2016
CONSENT
ITEM: #22
AGENDA ITEM: Amend 2017 Budget Schedule
SUBMITTED BY: Cathy Bendel, Finance Director
REVIEWED BY: Kristina Handt, City Administrator
SUMMARY AND ACTION REQUESTED: As part of its Consent Agenda, the City Council
was asked in May to accept the proposed 2017 budget key dates for planning purposes. This
item is being brought back to the City Council due to the July Finance Committee meeting
needing to be rescheduled due to two members being unavailable on July 12th. No specific
motion is needed, as this is recommended to be part of the overall approval of the Consent
Agenda.
STAFF REPORT: Below are key dates to note for the 2017 budget preparation calendar:
5/12/16, 6/14/16, 6/20/16 – 5 year proposed CIP plan under review by the Finance Committee
7/19/16 – Proposed 2017 budgets (all funds) to be presented to the Finance Committee at Joint
meeting with CC. Finance Committee meeting scheduled from 5:00 – 7:00 pm (prior to CC
meeting)
8/10/16 – Finance Committee meeting; 5:00 – 6:30 (2nd Budget workshop if needed)
9/6/16 – Proposed budget to City Council for adoption for preliminary certification of the
General Fund Budget to the County
9/30/16 – Preliminary Certification due to Washington County
12/6/16 – Final Budget and Levy determination (Public Hearing); also referred to as “TNT
hearing”
12/28/16 – Final Levy Certification due to Washington County
RECOMMENDATION: Based on the aforementioned, the staff recommends the City Council
accept the proposed amended schedule related to the 2017 Budget process.
MAYOR AND COUNCIL COMMUNICATION
DATE: June 21, 2016
CONSENT
ITEM #: 23
MOTION
AGENDA ITEM: Requests from Finance Related to Old Village Downtown Improvement Project
SUBMITTED BY: Kristina Handt, City Administrator
_____________________________________________________________________________________
BACKGROUND:
At the June 14th Finance Committee meeting, staff mentioned there were a number of ways to influence
the financial impact to property owners effected by the Old Village Downtown Improvement Project.
These included lowering the assessments and fees, deferring costs over a period of years through special
assessments or the Met Council deferral program, city financing contractor costs related to individual
hook ups on a project basis rather than individual property owners, and lowering the interest rate to name
a few. The committee made a recommendation regarding connection and SAC charges (see later agenda
item) but other items were put off to another meeting.
ISSUE BEFORE COUNCIL:
Should the Council direct the Finance Director and Finance Committee to provide recommendations
within 45 days regarding the financial options related to the Old Village Downtown Improvement
Project?
PROPOSAL DETAILS/ANALYSIS:
Mayor Pearson and Council member Bloyer would like a recommendation from the Finance Director in
conjunction with the Finance Committee regarding all the possible ways to reduce the financial impact to
property owners downtown.
Some specific items they’d like discussed and a recommendation made on include:
1) commercial properties in the village are to be assessed their street / landscaping improvements at the
residential equivalency rate of 30%, yet are not to be lower than any residential property within phase
1&2 (IE: 30% v 100%).
2) city allows carrying the debt for private internal sanitary sewer hookup costs to an amount not to
exceed 5k
3) for those transitioning to city sewer, a lowered interest rate shall be provided for aggregate city
assessments totaling higher than 14k
4) consideration of a universally lowered assessment amount, in anticipation of future growth for the
phase 1 and 2 properties. I.E. existing properties are subsidizing future growth potential. Existing
assessment policy takes little if any consideration of future hook ups for the phase 1 and 2 projects.
5) with regards to phase 1 and 2, for those properties being charged 3 or more RECs, prior to any
assessments being levied, a cost benefit appraisal is to be performed in order to ascertain a more exacting
incremental value increase for those properties. That appraisal shall be the actual assessed amount.
FISCAL IMPACT:
NA-will be determined with recommendations
OPTIONS:
1) Request a summary of all recommendations within 45 days from the finance director in
conjunction with the finance committee related to the Old Village Downtown Improvement
Project
2) Don’t request this information from finance
RECOMMENDATION:
If removed from the consent agenda:
Motion to request a summary of all recommendations within 45 days from the finance director in
conjunction with the finance committee related to the Old Village Downtown Improvement Project.
MAYOR AND COUNCIL COMMUNICATION
DATE: June 21, 2016
CONSENT
ITEM #:
MOTION
AGENDA ITEM: Amending Wastewater Treatment Systems Ordinance to Extend Time for
Connection
SUBMITTED BY: Kristina Handt, City Administrator
BACKGROUND:
Current City Code 51.022 (A) requires a building to connect to municipal sewer within one year from the
time a connection is available to the building.
Met Council Rules allow for 24 months for the connection to happen from the time a connection is
available.
ISSUE BEFORE COUNCIL:
Should the Council amend City Code to be consistent with Met Council Rules and allow 24 months for a
building to connect to municipal sewer from the time a connection is available?
PROPOSAL DETAILS/ANALYSIS:
The proposal would simple change the connection time from 1 year to 2 years.
FISCAL IMPACT:
This change would impact the sewer fund balance by possibly delaying the $1,000 connection fee by an
additional year. Net result over time would have no impact.
OPTIONS:
1) Approve Ordinance No. 08-139
2) Amend and then Approve Ordinance No. 08-139
3) Do not adopt Ordinance No. 08-139
RECOMMENDATION:
Motion to adopt Ordinance No. 08-139
1
CITY OF LAKE ELMO
COUNTY OF WASHINGTON
STATE OF MINNESOTA
ORDINANCE NO. 08-139
AN ORDINANCE AMENDING CHAPTER 51: WASTEWATER TREATMENT SYSTEMS
The City Council of the City of Lake Elmo hereby ordains that Chapter 51, Section 51.022 (A) is hereby
amended to read as follows:
51.022 CONNECTIONS WITH SEWER REQUIRED.
(A) Any building used for human habitation or in which a toilet or other plumbing facility for the
disposal of human waste is installed and located on property adjacent to a sewer main, or in a platted
block through which the system extends, shall be connected to the municipal sanitary sewer system
within 1 year2 years from the date on which a connection is available to the building.
Effective Date
This ordinance shall become effective immediately upon adoptin and publication in the official
newspaper of the City of Lake Elmo.
Adoption Date
This Ordinance No. 08-139 was adopted on this 21st day of May, 2016 by a vote of ____ Ayes and
____Nays.
________________________________________________
Mayor Mike Pearson
ATTEST:
_________________________________
Julie Johnson
City Clerk