HomeMy WebLinkAboutInwood trunk WM Change Order No 1 (2) CONTRACT CHANGE ORDER FORM
CITY OF LAKE ELMO, MINNESOTA FOCUS ENGINEERING, inc.
INWOOD TRUNK WATERMAIN IMPROVEMENTS
PROJECT NO. 2014.130
CHANGE ORDER NO. 1 DATE: June 27, 2016
TO: NORTHDALE CONSTRUCTION COMPANY, INC. 9760 71ST STREET NE ALBERTVILLE, MN 55301
This Document will become a supplement to the Contract and all provisions will apply hereto.The Contract Documents are
modified as follows upon execution of this Change Order.
CHANGE ORDER DESCRIPTION/JUSTIFICATION:
This change order is being processed to provide compensation for the time and materials to install offsets on two hydrants.This was
completed to maintain cover over pipe in the County ditches. Additionally this change order provides compensation for the installation of an
18-inch flared end section at 21st Street North.The existing flared end was found to be is poor condition and could not be salvaged as
planned.
Attachments (list documents supporting change): None
ITEM DESCRIPTION OF PAY ITEM UNIT CITY UNIT PRICE INCREASE/(DECREASE)
C01-1 HYDRANT OFFSET EA 2 $500.00 $1,000.00
C01-2 18" FLARED END SECTION EA 1 $1,200.00 $1,200.00
NET CONTRACT CHANGE $2,200.00
Amount of Original Contract $ 1,411,737.31
Sum of Additions/Deductions approved to date (CO Nos. ) $ 0.00
Contract Amount to date $ 1,411,737.31
Amount of this Change Order (ADD) (DEDUCT) (Pig GE) $ 2,200.00
Revised Contract Amount $ 1,413,937.31
The Contract Period for Completion will be (UNCHANGED) ('^'GREASED) (nrr D) 0 days
APPROVED
BY ENGINEER: FOCUS Engineering, inc. APPROVED BY CONTRACTOR
ENGINEER BY
6/27/2016
DATE DATE
APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA
BY BY
DATE DATE
FOCUS Engineering,inc. CHANGE ORDER FORM