HomeMy WebLinkAbout#12 Inwood Trunk WM - Pay Request No 4 AGENDA ITEM MAYOR & COUNCIL COMMUNICATION -- page 1 -- DATE: August 16, 2016 CONSENT ITEM # 12 AGENDA ITEM: Inwood Trunk Watermain Improvements – Pay Request No. 4 SUBMITTED BY: Chad Isakson, Project Engineer THROUGH: Kristina Handt, City Administrator REVIEWED BY: Jack Griffin, City Engineer Cathy Bendel, Finance Director SUGGESTED ORDER OF BUSINESS if removed from the Consent Agenda): - Questions from Council to Staff ............................................. Mayor Facilitates - Public Input, if Appropriate………………………………….Mayor Facilitates - Call for Motion ............................................................... Mayor & City Council - Discussion ....................................................................... Mayor & City Council - Action on Motion .................................................................... Mayor Facilitates POLICY RECOMMENDER: Engineering. FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project. Payment remains within the authorized scope and budget. SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to consider approving Pay Request No. 4 for the Inwood Trunk Watermain Improvements project. LEGISLATIVE HISTORY/BACKGROUND INFORMATION: Northdale Construction Company, Inc., the Contractor for the project, has submitted Partial Pay Estimate No. 4 in the amount of $248,363.65. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of the total work completed. The amount retained is $69,479.95. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 4 for the Inwood Trunk Watermain Improvements project. If removed from the consent agenda, the recommended motion for the action is as follows: City Council Meeting [Consent Agenda Item 12] August 16, 2016 -- page 2 -- “Move to approve Pay Request No. 4 to Northdale Construction Company, Inc. in the amount of $248,363.65 for the Inwood Trunk Watermain Improvements”. ATTACHMENT(S): 1. Partial Pay Estimate No. 4. PARTIAL PAY ESTIMATE NO. 4 INWOOD AVENUE TRUNK WATERMAIN IMPROVEMENTS CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2014.130 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LS 1                    $64,800.00 $64,800.00 0.00 $0.00 1.00 $64,800.00 2 LS 1                    $22,945.00 $22,945.00 0.20 $4,589.00 0.95 $21,797.75 3 LF 600                $4.13 $2,478.00 0.00 $0.00 200 $826.00 4 EA 6                    $750.00 $4,500.00 0.00 $0.00 0 $0.00 5 EA 10                  $104.50 $1,045.00 0.00 $0.00 0 $0.00 $95,768.00 $4,589.00 $87,423.75 1 EA 1                    $7,483.75 $7,483.75 0 $0.00 0 $0.00 2 EA 2                    $13,187.61 $26,375.22 0 $0.00 1 $13,187.61 3 EA 11                  $4,431.40 $48,745.40 1 $4,431.40 10 $44,314.00 4 LF 6                    $1,628.80 $9,772.80 0 $0.00 3.5 $5,700.80 5 EA 10                  $2,476.08 $24,760.80 1 $2,476.08 10 $24,760.80 6 EA 3                    $2,920.05 $8,760.15 0 $0.00 2 $5,840.10 7 EA 2                  $4,117.60 $8,235.20 0 $0.00 2 $8,235.20 8 EA 19                  $10,711.98 $203,527.62 5 $53,559.90 19 $203,527.62 9 EA 3                  $709.63 $2,128.89 0 $0.00 3 $2,128.89 10 EA 3                    $775.20 $2,325.60 0 $0.00 3 $2,325.60 11 LF 100                $50.97 $5,097.00 0 $0.00 81 $4,128.57 12 LF 75                  $63.87 $4,790.25 19 $1,181.60 141.0 $9,005.67 13 LF 96                  $70.32 $6,750.72 0 $0.00 42 $2,953.44 14 LF 28                  $108.70 $3,043.60 0 $0.00 25.75 $2,799.03 15 LF 25                  $126.98 $3,174.50 20 $2,539.60 55 $6,983.90 16 LF 11,015          $74.75 $823,371.25 2,214 $165,496.50 10,940 $817,765.00 17 LB 5,810            $10.74 $62,399.40 1,773 $19,042.02 8,776 $94,254.24 18 LS 1                    $49,462.20 $49,462.20 0 $7,419.33 0.90 $44,515.98 19 LS 1                    $7,000.00 $7,000.00 0 $700.00 0.95 $6,650.00 20 EA 18                  $156.02 $2,808.36 0 $0.00 0 $0.00 $1,310,012.71 $256,846.43 $1,299,076.45 1 LF 60                  $15.00 $900.00 0 $0.00 14 $210.00 2 LF 60                  $31.11 $1,866.60 0 $0.00 8 $248.88 $2,766.60 $0.00 $458.88 1 EA 2                  $165.00 $330.00 0 $0.00 0 $0.00 2 EA 13                  $220.00 $2,860.00 0 $0.00 2 $440.00 $3,190.00 $0.00 $440.00 TOTALS ‐ BASE CONTRACT $1,411,737.31 $261,435.43 $1,387,399.08 CHANGE ORDER NO. 1 CO1‐1 EA 2 $500.00 $1,000.00 0 $0.00 2 $1,000.00 CO1‐2 EA 1 $1,200.00 $1,200.00 0 $0.00 1 $1,200.00 TOTALS ‐ CHANGE ORDER NO. 1 $2,200.00 $0.00 $2,200.00 TOTALS ‐ REVISED CONTRACT $1,413,937.31 $261,435.43 $1,389,599.08 SALVAGE AND REINSTALL MAILBOX 18" FLARED END SECTION 1" CURB STOP AND CURB BOX CLEAR AND GRUB TREE DITCH CHECK SUBTOTAL ‐ DIVISION 1 DIVISION 2 ‐ WATERMAIN CONNECT TO EXISTING 8" WATERMAIN CONNECT TO EXISTING 16" WATERMAIN 12" GATE VALVE AND BOX 1" CORPORATION STOP WITH FUSIBLE SADDLE HYDRANT 6" GATE VALVE AND BOX 8" GATE VALVE AND BOX 16" BUTTERFLY VALVE AND BOX ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE DIVISION 1 ‐ GENERAL MOBILIZATION TRAFFIC CONTROL SILT FENCE, MACHINE SLICED HYDRANT EXTENSION 1" COPPER WATER SERVICE PIPE 6" DUCTILE IRON WATERMAIN PIPE, CLASS 52 8" DUCTILE IRON WATERMAIN PIPE, CLASS 52 12" DUCTILE IRON WATERMAIN PIPE, CLASS 52 16" DUCTILE IRON WATERMAIN PIPE, CLASS 52 16" HDPE DIPS DR11 WATERMAIN, DIRECTIONAL DRILL DUCTILE IRON FITTINGS HORIZONTAL DIRECTIONAL DRILLING BORE PITS WATER SERVICE CONNECTION PITS TRIVIEW TEST STATION MARKER SUBTOTAL ‐ DIVISION 2 SUBTOTAL ‐ DIVISION 4 DIVISION 4 ‐ STREET CONSTRUCTION DIVISION 3 ‐ STORM SEWER SALVAGE CONCRETE PIPE CULVERT INSTALL SALVAGED PIPE CULVERT SALVAGE AND REINSTALL SIGN SUBTOTAL ‐ DIVISION 3 HYDRANT OFFSET