MAYOR & COUNCIL COMMUNICATION
-- page 1 --
DATE: August 16, 2016
REGULAR
ITEM # 18
AGENDA ITEM: CSAH 13 Phase 1 Improvements - Authorize Preparation of a Feasibility
Report
SUBMITTED BY: Jack Griffin, City Engineer
THROUGH: Kristina Handt, City Administrator
REVIEWED BY: Chad Isakson, Project Engineer
Cathy Bendel, Finance Director
SUGGESTED ORDER OF BUSINESS:
- Introduction of Item .................................................................................. City Engineer
- Report/Presentation………………………………………… .................. City Engineer
- Questions from Council to Staff ............................................. Mayor Facilitates
- Public Input, if Appropriate………………………………….Mayor Facilitates
- Call for Motion ............................................................... Mayor & City Council
- Discussion ....................................................................... Mayor & City Council
- Action on Motion .................................................................... Mayor Facilitates
POLICY RECOMMENDER: Engineering.
FISCAL IMPACT: $7,000. If the improvements are ordered, the report costs will be charged
against the project fund and become assessable to the benefitting properties. Should the project
not be constructed, the report costs cannot be assessed.
SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to
consider approving Resolution No. 2016-67, Ordering the Preparation of a Feasibility Report
meeting MN State Statute 429 for the CSAH 13 Phase 1 Improvements so that the costs may be
wholly or partially assessed to the benefitting properties.
LEGISLATIVE HISTORY/BACKGROUND INFORMATION: The City of Lake Elmo,
City of Oakdale, and Washington County are working jointly to make improvements along
County State Aid Highway (CSAH) 13 (Ideal Avenue/Olson Lake Trail) with the Phase 1
Improvements to be constructed in 2017. On July 19, 2016 the City of Lake Elmo approved a
Resolution of Municipal Support for the Phase 1 Improvements consisting of pavement
City Council Meeting [Regular Agenda Item 18]
August 16, 2016
-- page 2 --
preservation from CSAH 14 to 44th Street and Street Reconstruction with Trail, Drainage and
Sanitary Sewer Improvements from 44th Street to 50th Street. The project will improve the
roadway corridor, better manage storm water, add a pedestrian facility, and extend Oakdale’s
municipal sanitary sewer system to several Lake Elmo properties.
Washington County intends to require cost participation from the Cities of Lake Elmo and
Oakdale in accordance with the County Cost Participation Policy for County Improvement
Projects. In addition, the improvements include the extension of sanitary sewer service to Lake
Elmo and Oakdale properties at the request of both cities. The current estimate for the local cost
share of the improvements to be shared approximately equally between Lake Elmo and Oakdale
is $1,185,142. A Joint Powers Agreement will be prepared to more specifically allocate those
costs between the County and each City.
Special assessments have been identified as one of the available funding mechanisms for the
improvements where the benefiting properties are specially assessed all or a portion of the cost
of the improvement, pursuant to the City’s Special Assessment Policy and Minnesota Statues,
Chapter 429. In order to maintain special assessments as a viable funding alternative, the City
Council must direct the preparation of a feasibility report meeting the statutory process for public
improvements that are specially assessed.
The report will advise on the improvements being recommended along the corridor, provide
estimated project costs for the City cost participation of the recommended improvements,
including easement and right-of-way, permits, and other requirements needed to implement the
improvements, recommend whether the improvements should be made as proposed or in
connection with some other improvement, and advise if the improvements are ne cessary, cost
effective, and feasible. The Report will also provide a preliminary assessment roll for each of the
benefitting properties. Utility improvements will address sanitary sewer service to replace
individual on-site treatment systems. Project costs will be as provided by Washington County’s
design consultant (SRF Consulting) for the improvements. Additionally, a Cooperate Agreement
will be needed between Lake Elmo and Oakdale to address the respective municipal cost share
along with maintenance responsibilities for the various improvements.
RECOMMENDATION: Staff is recommending that the City Council authorize FOCUS
Engineering, Inc. to prepare a Feasibility Report meeting MN State Statute 429 for the CSAH 13
Phase 1 Improvements in the not to exceed amount of $7,000. The recommended motion for this
action is as follows:
“Move to approve Resolution No. 2016-67, Ordering preparation of a Feasibility Report by
FOCUS Engineering for the CSAH 13 Phase 1 Improvements in a not to exceed amount of
$7,000.”
ATTACHMENT(S):
1. Resolution No. 2016-67, Ordering Preparation of a Feasibility Report.
2. CSAH 13 Location Map and Typical Section.
3. Project Schedule.
Resolution No. 2016-67 1
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2016-67
A RESOLUTION ORDERING PREPARATION OF A FEASIBILITY REPORT
FOR THE CSAH 13 PHASE 1 IMPROVEMENTS
WHEREAS, on July 19, 2016 the City of Lake Elmo approved a Resolution of Municipal Support for the
County State Aid Highway 13 (Ideal Avenue/Olson Lake Trail) Roadway, Trail, Drainage and Sanitary Sewer
Improvements for CSAH 13 from CSAH 14 to 50th Street; and
WHEREAS, the CSAH 13 Phase 1 Improvements, including pavement preservation from CSAH 14 to 44th
Street and Street Reconstruction with Trail, Drainage and Sanitary Sewer Improvements from 44th Street to 50th
Street, are proposed for construction beginning in 2017; and
WHEREAS, Washington County, the City of Oakdale and the City of Lake Elmo are each responsible for
sharing in the project costs per the Washington County cost participation policy; and
WHEREAS, it is proposed to assess the benefiting properties for all or a portion of the cost of the
improvement, pursuant to the City’s Special Assessment Policy and Minnesota Statues, Chapter 429.
NOW, THEREFORE, IT IS HEREBY RESOLVED,
That the proposed improvement, called the CSAH 13 Phase 1 Improvements, be referred to the City Engineer
and FOCUS Engineering, and that FOCUS Engineering is instructed to complete a feasibility report in
accordance with Minnesota Statues, Chapter 429 for the proposed improvements, and to report to the council
with all convenient speed advising the council in a preliminary way as to whether the proposed improvement
is necessary, cost-effective, and feasible; whether it should be best made as proposed or in connection with
some other improvement; using estimated costs for the recommended improvements as determined by the
County’s design consultant; and a description of the methodology used to calculate individual assessments for
affected parcels.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE SIXTEENTH DAY OF AUGUST 2016.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
Mayor
(Seal)
ATTEST:
________________________________
Julie Johnson
City Clerk
7/11/2016
1
Preferred Alternative
Oakdale
Lake
Elmo
PROJECT SCHEDULE
CITY OF LAKE ELMO
CSAH 13 PHASE 1 IMPROVEMENTS
PROJECT NO. 2015.125
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
AUGUST 2016
JULY 19, 2016 Council approves Phase 1 Municipal Consent. County proceeds with Final Design.
AUGUST 16, 2016 Council authorizes the preparation of the CSAH 13 Phase 1 Feasibility Report.
FEBRUARY 21, 2017 County presents final plans and specifications. Council accepts Report and adopts
project assessment policy. Calls Public Improvement and Final Assessment
Hearing.
FEBRUARY 22, 2017 Notice of Public Improvement and Final Assessment Hearing (Publish March 1 and
March 8, 2017).
FEBRUARY 27, 2017 County posts advertisement for bid.
MARCH 21, 2016 Public Improvement and Final Assessment Hearing. Council Orders the
Improvement for the CSAH 13 Phase 1 Improvements (Requires 4/5th vote).
APRIL 4, 2017 County Accepts Contractor Bids.
APRIL 18, 2017 Council approves “Concurrence” to award contract.
MAY, 2017 Start of Phase 1 Construction.
NOVEMBER, 2017 Substantial Completion.
JULY, 2018 Final Completion.