HomeMy WebLinkAbout3-Project SchedulePROJECT SCHEDULE
CITY OF LAKE ELMO
CSAH 13 PHASE 1 IMPROVEMENTS
PROJECT NO. 2015.125
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
AUGUST 2016
JULY 19, 2016 Council approves Phase 1 Municipal Consent. County proceeds with Final Design.
AUGUST 16, 2016 Council authorizes the preparation of the CSAH 13 Phase 1 Feasibility Report.
FEBRUARY 21, 2017 County presents final plans and specifications. Council accepts Report and adopts
project assessment policy. Calls Public Improvement and Final Assessment
Hearing.
FEBRUARY 22, 2017 Notice of Public Improvement and Final Assessment Hearing (Publish March 1 and
March 8, 2017).
FEBRUARY 27, 2017 County posts advertisement for bid.
MARCH 21, 2016 Public Improvement and Final Assessment Hearing. Council Orders the
Improvement for the CSAH 13 Phase 1 Improvements (Requires 4/5th vote).
APRIL 4, 2017 County Accepts Contractor Bids.
APRIL 18, 2017 Council approves “Concurrence” to award contract.
MAY, 2017 Start of Phase 1 Construction.
NOVEMBER, 2017 Substantial Completion.
JULY, 2018 Final Completion.