HomeMy WebLinkAboutInwood Booster Station - CO#1 CONTRACT CHANGE ORDER FORM CITY OF LAKE ELMO, MINNESOTA FOCUS ENGINEERING, inc. INWOOD BOOSTER STATION IMPROVEMENTS PROJECT NO.2014.129 CHANGE ORDER NO. 1 DATE: July 20, 2016 TO: Magney Construction, Inc., 1401 Park Road,Chanhassen, MN 55317 This Document will become a supplement to the Contract and all provisions will apply hereto.The Contract Documents are modified as follows upon execution of this Change Order. CHANGE ORDER DESCRIPTION/JUSTIFICATION: See summary breakdown and supporting doucuments for clarification&cost breakdowns Attachments (list documents supporting change): Attached price quotation(s)&cost proposals) ITEM DESCRIPTION OF PAY ITEM UNIT CITY UNITE PRICE INCREASE/(DECREASE) CO1 Proposal Req.1-3, Field Change 1-2,Substitute 1-2 LS 1 -$5,048.49 ($5,048.49) NET CONTRACT CHANGE ($5,048.49) Amount of Original Contract $ 1,308,404.00 Sum of Additions/Deductions approved to date (CO Nos.0) $ 0.00 Contract Amount to date $ 1,308,404.00 Amount of this Change Order kA&&� (DEDUCT) (NO Ck#ANG9) $ (5,048.49) Revised Contract Amount $ 1,303,355.51 The Contract Period for Completion will be (UN,- 8) (INCREASED) (DECREASED) 2 days APPROVED BY ENGINEER: MSA PROFESSIONAL SERVICES APPROVED BY CONTRACTOR ENGI EER BY DATE DATE APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA BY BY DATE DATE FOCUS Engineering,inc. CHANGE ORDER FORM CHANGE ORDER NO. 1 INWOOD BOOSTER STATION IMPROVEMENTS FOCUSENGINEERING, inn. CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2014.129 CHANGE ORDER ITEM DESCRIPTION OF PAY ITEM UNIT DESCRIPTION/JUSTIFICATION QUANTITY UNIT PRICE AMOUNT C01-1 FC1:Additional Common Excavation @ driveway&ditch CY 185 $20.00 $3,700.00 Adjust plans per Washington Co.comments C01-2 PR1:Relocate Chemical Pump&Remove Chemical Room Floor Drain LS 1 $255.78 $255.78 Adjust plans per MN Department of Health comments C01-3 Sub1:Substitute Main Circuit Breaker&Variable Frequency Drives LS 1 -$3,082.56 -$3,082.56 Value engineering and size considerations C01-4 Sub2:Substitute Booster Pump Manufacturers LS 1 -$3,500.00 -$3,500.00 Value engineering and lead time considerations C01-5 FC2:Water Service&Watermain Connections LS 1 $5,666.18 $5,666.18 Upsize&relocate water service,deeper watermain connection C01-6 PR2:Additional Building Insulation LS 1 $1,047.11 $1,047.11 Adjust plans per MN Department of Labor&Industry comments C01-7 I PR3:Remove Chlorination Actuators LS 1 -$9,135.00 -$9,135.00 lValue engineering and space considerations TOTALS-CHANGE ORDER NO. 1 -$5,048.49 AQNE,YC 0 N S T R U C T 10 N Proposal ('0MMOICIAL b INDUSTRIAL CONTHAC T OR S PR#1 1' ; 1401 Park Road - Chanhassen, MN 55317 vnvw.magneyconstruction.com 952.474.1674 Office 952.474.1679 Fax CO 1-2 SEND TO Company name From MSA Peter Aldritt Attention Date Lucas Jones 6/8/2016 Fax Phone Proposal# PR-1 Urgent ❑ Please comment ❑ Please review X❑ For your information Total pages,including cover. 1 COMMENTS RE: Inwood Ave Booster Station Proposal Request 1 Lucas, We are affering the following price quotation in regards to the MDH review. Material: - $ Labor: Install Booster Pump outside of Chlorine Room $ _ Subcontractor. Northern Plumbing Tech $ (260.00) Subcontractor: Taylor Electric $ 500.00 Subtotal $ 240.00 General Contractor's Overhead $ 12.00 Bond & Insurance premiums $ 3.78 Total $ 255.78 Please review this proposal and feel free to contact me with any questions, comments or concerns. Thank you, P z G 'e Peter Aldritt Project Manager Accepted By Date Page 1 of 1 C O N S T R U C T IO N Proposal fOAGNIE Y LUMMf HLIAL Fi lNuun i liIAL SUN I HAL i Win C01-3 �!I` �� 1401 Park Road - Chanhassen, MN 55317 www.magneyconstrur-tion.com 952.474.1674 Office 952.474.1679 Fax SEND TO Company name From MSA Peter Aldritt Attention Date Lucas Jones 7/18/2016 Fax Phone Proposal# MC-P2 Revised ❑ Urgent ❑ Please comment X❑ Please review For your information Total pages,including cover: 1 COMMENTS RE: MCC Modifications Lucas, We are offering the following price quotation in regards to the MCC modifications and substituting the electronic main circuit breaker for the thermal mag breaker. Material: $ _ Labor: $ _ Subcontractor: TPC/Taylor Electric - MCC Modifications $ (3,037.00) Subtotal $ (3,037.00) General Contractor's Overhead $ - Bond & Insurance premiums $ (45.56) Total $ (3,082.56) Please review this proposal and feel free to contact me with any questions, comments or concerns. Thank you, Peter Aldritt Project Manager Accepted By Date Page 1 of 1 NUI ri u tatin AG -E,"', N S ( l i �K]AL Fl li���l��l�fIAL CONTRAf,�h5 c01-4 1401 Park Road-Chanhassen, MN 55317 www.magneyconstruction:com 952.474.1674 Office 952.474.1679 Fax SEND TO Company name From MSA Peter Aldritt Attention Date Lucas Jones 6/3/2016 Fax Phone Proposal# ❑ Urgent Please comment X❑ Please review For your information Total pages,including cover: COMMENTS Lucas, We are offering the following deduct price quotation for the submitted Booster Pumps. Labor: $ - Material: $ (3,500.00) Equipment: $ - Subcontractor: $ - Subtotal $ (3,500.00) General Contractor's Labor Mark Up 15% $ General Contractor's Overhead 5% $ Bond &Insurance premiums $ - Total $ (3,500.00) Additional Working Days Required for this Change: 0.0 Please review this proposal and feel free to contact me with any questions, comments or concerns. Thank you, Peter Aldritt Project Manager r7777pted By Date MAGNEYC 0 N S T R U CT I ON COST PROPOSAL DATE: June 6,2016 WORKSHEET 1401 Park Road-Chanhassen,MN 55317 COR NO: CO 1-5 952.4741674 Office 952 4741679 Fax P.R. NO: R.F.I. NO: St. Croix Lift Station DESCRIPTION OF WORK: ESTIMATED ADDITIONAL CALENDAR DAYS REQUIRED: 2 days Furnish and install 1.5"copper water service,curbstop and wet tap from existing water main. This includes the additional 4'of excavation for the 12"Tie-Ins. Existing 12"was at 994.5' LABOR MAT'L SUB DESCRIPTION QUANTITY UNIT UNIT PRICE LABOR UNIT PRICE MATERIAL EQUIPMENT CONTRACTS MAGNEYLABOR Laborer- 14 Hr $ 76.23 $1,067.22 Carpenter- 10 Hr $ 83.02 $830.20 Operator Hr $ 85.93 $0.00 Plumber/Pipe Fitter Hr $ 91.50 $0.00 Foreman Hr $ 86.72 $0.00 Superintendent 12 Hr $ 93.00 $1,116.00 General Su erintedant Hr $ 126.87 $0.00 Project Manager Hr $ 100.00 $0.00 Overtime-Add$30.00/Hr Hr $ 30.00 $0.00 Sunday&Holidays-Add$48.00/Hr Hr $ 48.00 $0.00 MAGNEY Material 1.5"Copper $210.00 1.5"Curbstop $297.00 MAGNEY Equipment Trench Box $350.00 Kamatsu 360 $0.00 Mileage 76 Miles $0.65 $49.40 Pick Up Truck 0 day $90.00 $0.00 SUBCONTRACTORS/SUPPLIERS Fobbe Contracting-Wet Tap $800.00 SUBTOTAL MAGNEY LABOR, MATERIALS, SUBCONTRACTORS $3,013.42 $556.40 $800.00 MAT.HANDLING LABOR:4%OF MAT. $22.26 SMALL TOOLS MAT.:6%OF LABOR 1 1 $180.81 SUBTOTAL $3,035.68 $737.21 1 $350.00 $800.00 MAGNEY OVERHEAD/FEE 15% $455.35 $110.58 1 $0.00 $40.00 SUBTOTAL MAGNEY LABOR $3,491.03 SUBTOTAL EQUIPMENT1 $350.00 $350.00 SUBTOTAL MATERIAL $847.79 $847.79 SUBTOTAL SUBCONTRACT 1 $840.00 $840.00 SUBTOTAL $5,528.81 MATERIAL SALES TAX-7.275% $53.63 BOND/INSURANCE-0.015 $83.74 BUILDERS RISK INSURANCE N/A TOTAL THIS COST PROPOSAL $5,666.18 Page 1 AGNEYC O N S T R U C T 10 N Proposal COMMERCIML U MDUSTRIAL CONTRACTORS PR-2 W-3—z%; 1401 Park Road - Chanhassen, MN 55317 www.mayney�stniction.com 952.474.1674 Office 952.474.1679 Fax C01-6 SEND TO Company name From MSA Peter Aldritt Attention Date Lucas Jones 6/28/2016 Fax Phone Proposal# PR-2 ❑ Urgent ❑ Please comment ❑ Please review X❑ For your information Total pages, including cover: 1 COMMENTS RE: Lake Elmo Booster Station PR-2 Lucas, We are offering the following price quotation to add a continuous layer of 1/2" Rigid Insulation under the siding. Labor: $ 415.00 Material: $ 554.39 Tools & Equipment: $ - Subtotal $ 969.39 General Contractor's Overhead $ 62.25 Bond & Insurance premiums $ 15.47 Total $ 1,047.11 Additional Working Days Required for this Change: 0.0 Please review this proposal and feel free to contact me with any questions, comments or concerns. Thank you, Peter Aldritt Project Manager Accepted By Date Page 1 of 1 N ST R U CT I ON Proposal AGNEYCO �� LUMMERCIAL U iitiUUSTRIAL Luiy i r ACTORS c01-7 �� 1401 Park Road - Chanhassen, MN 55317 www.mag�construction.com 952.474.1674 Office 952.474.1679 Fax SEND TO Company name From MSA Peter Aldritt Attention Date Lucas Jones 7/12/2016 Fax Phone Proposal# MC-P3 Urgent Please comment X❑ Please review For your information Total pages,including cover: 1 COMMENTS RE: Removing Motorized Gas Shut off Actuators Lucas, We are affering the following price quotation in regards to removing the Emergency Gas Shut off Actuators. Material: $ _ Labor: $ _ Subcontractor: Vessco - Removing Actuators $ (9,000.00) Subtotal $ (9,000.00) General Contractor's Overhead $ - Bond & Insurance premiums $ (135.00) Total $ (9,135.00) Please review this proposal and feel free to contact me with any questions, comments or concerns. Thank you, Peter Aldritt Project Manager Accepted By Date Page 1 of 1