HomeMy WebLinkAboutInwood Booster Station - CO#1 CONTRACT CHANGE ORDER FORM
CITY OF LAKE ELMO, MINNESOTA FOCUS ENGINEERING, inc.
INWOOD BOOSTER STATION IMPROVEMENTS
PROJECT NO.2014.129
CHANGE ORDER NO. 1 DATE: July 20, 2016
TO: Magney Construction, Inc., 1401 Park Road,Chanhassen, MN 55317
This Document will become a supplement to the Contract and all provisions will apply hereto.The Contract Documents are
modified as follows upon execution of this Change Order.
CHANGE ORDER DESCRIPTION/JUSTIFICATION:
See summary breakdown and supporting doucuments for clarification&cost breakdowns
Attachments (list documents supporting change): Attached price quotation(s)&cost proposals)
ITEM DESCRIPTION OF PAY ITEM UNIT CITY UNITE PRICE INCREASE/(DECREASE)
CO1 Proposal Req.1-3, Field Change 1-2,Substitute 1-2 LS 1 -$5,048.49 ($5,048.49)
NET CONTRACT CHANGE ($5,048.49)
Amount of Original Contract $ 1,308,404.00
Sum of Additions/Deductions approved to date (CO Nos.0) $ 0.00
Contract Amount to date $ 1,308,404.00
Amount of this Change Order kA&&� (DEDUCT) (NO Ck#ANG9) $ (5,048.49)
Revised Contract Amount $ 1,303,355.51
The Contract Period for Completion will be (UN,- 8) (INCREASED) (DECREASED) 2 days
APPROVED BY ENGINEER: MSA PROFESSIONAL SERVICES APPROVED BY CONTRACTOR
ENGI EER BY
DATE DATE
APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA
BY BY
DATE DATE
FOCUS Engineering,inc. CHANGE ORDER FORM
CHANGE ORDER NO. 1
INWOOD BOOSTER STATION IMPROVEMENTS FOCUSENGINEERING, inn.
CITY OF LAKE ELMO, MINNESOTA
PROJECT NO. 2014.129
CHANGE ORDER
ITEM DESCRIPTION OF PAY ITEM UNIT DESCRIPTION/JUSTIFICATION
QUANTITY UNIT PRICE AMOUNT
C01-1 FC1:Additional Common Excavation @ driveway&ditch CY 185 $20.00 $3,700.00 Adjust plans per Washington Co.comments
C01-2 PR1:Relocate Chemical Pump&Remove Chemical Room Floor Drain LS 1 $255.78 $255.78 Adjust plans per MN Department of Health comments
C01-3 Sub1:Substitute Main Circuit Breaker&Variable Frequency Drives LS 1 -$3,082.56 -$3,082.56 Value engineering and size considerations
C01-4 Sub2:Substitute Booster Pump Manufacturers LS 1 -$3,500.00 -$3,500.00 Value engineering and lead time considerations
C01-5 FC2:Water Service&Watermain Connections LS 1 $5,666.18 $5,666.18 Upsize&relocate water service,deeper watermain connection
C01-6 PR2:Additional Building Insulation LS 1 $1,047.11 $1,047.11 Adjust plans per MN Department of Labor&Industry comments
C01-7 I PR3:Remove Chlorination Actuators LS 1 -$9,135.00 -$9,135.00 lValue engineering and space considerations
TOTALS-CHANGE ORDER NO. 1 -$5,048.49
AQNE,YC 0 N S T R U C T 10 N Proposal
('0MMOICIAL b INDUSTRIAL CONTHAC T OR S PR#1
1' ; 1401 Park Road - Chanhassen, MN 55317
vnvw.magneyconstruction.com 952.474.1674 Office 952.474.1679 Fax CO 1-2
SEND TO
Company name From
MSA Peter Aldritt
Attention Date
Lucas Jones 6/8/2016
Fax Phone Proposal#
PR-1
Urgent ❑ Please comment ❑ Please review X❑ For your information
Total pages,including cover. 1
COMMENTS
RE: Inwood Ave Booster Station Proposal Request 1
Lucas,
We are affering the following price quotation in regards to the MDH review.
Material: - $
Labor: Install Booster Pump outside of Chlorine Room $ _
Subcontractor. Northern Plumbing Tech $ (260.00)
Subcontractor: Taylor Electric $ 500.00
Subtotal $ 240.00
General Contractor's Overhead $ 12.00
Bond & Insurance premiums $ 3.78
Total $ 255.78
Please review this proposal and feel free to contact me with any questions, comments or concerns.
Thank you,
P
z G 'e
Peter Aldritt
Project Manager Accepted By Date
Page 1 of 1
C O N S T R U C T IO N Proposal
fOAGNIE Y
LUMMf HLIAL Fi lNuun i liIAL SUN I HAL i Win C01-3
�!I` �� 1401 Park Road - Chanhassen, MN 55317
www.magneyconstrur-tion.com 952.474.1674 Office 952.474.1679 Fax
SEND TO
Company name From
MSA Peter Aldritt
Attention Date
Lucas Jones 7/18/2016
Fax Phone Proposal#
MC-P2 Revised
❑ Urgent ❑ Please comment X❑ Please review For your information
Total pages,including cover: 1
COMMENTS
RE: MCC Modifications
Lucas,
We are offering the following price quotation in regards to the MCC modifications and substituting the electronic
main circuit breaker for the thermal mag breaker.
Material: $ _
Labor: $ _
Subcontractor: TPC/Taylor Electric - MCC Modifications $ (3,037.00)
Subtotal $ (3,037.00)
General Contractor's Overhead $ -
Bond & Insurance premiums $ (45.56)
Total $ (3,082.56)
Please review this proposal and feel free to contact me with any questions, comments or concerns.
Thank you,
Peter Aldritt
Project Manager Accepted By Date
Page 1 of 1
NUI ri u tatin
AG -E,"', N S
( l i �K]AL Fl li���l��l�fIAL CONTRAf,�h5 c01-4
1401 Park Road-Chanhassen, MN 55317
www.magneyconstruction:com 952.474.1674 Office 952.474.1679 Fax
SEND TO
Company name From
MSA Peter Aldritt
Attention Date
Lucas Jones 6/3/2016
Fax Phone Proposal#
❑ Urgent Please comment X❑ Please review For your information
Total pages,including cover:
COMMENTS
Lucas,
We are offering the following deduct price quotation for the submitted Booster Pumps.
Labor: $ -
Material: $ (3,500.00)
Equipment: $ -
Subcontractor: $ -
Subtotal $ (3,500.00)
General Contractor's Labor Mark Up 15% $
General Contractor's Overhead 5% $
Bond &Insurance premiums $ -
Total $ (3,500.00)
Additional Working Days Required for this Change: 0.0
Please review this proposal and feel free to contact me with any questions, comments or concerns.
Thank you,
Peter Aldritt
Project Manager r7777pted By Date
MAGNEYC 0 N S T R U CT I ON COST PROPOSAL DATE: June 6,2016
WORKSHEET
1401 Park Road-Chanhassen,MN 55317 COR NO: CO 1-5
952.4741674 Office 952 4741679 Fax P.R. NO:
R.F.I. NO:
St. Croix Lift Station
DESCRIPTION OF WORK: ESTIMATED ADDITIONAL CALENDAR DAYS REQUIRED: 2 days
Furnish and install 1.5"copper water service,curbstop and wet
tap from existing water main. This includes the additional 4'of
excavation for the 12"Tie-Ins. Existing 12"was at 994.5'
LABOR MAT'L SUB
DESCRIPTION QUANTITY UNIT UNIT PRICE LABOR UNIT PRICE MATERIAL EQUIPMENT CONTRACTS
MAGNEYLABOR
Laborer- 14 Hr $ 76.23 $1,067.22
Carpenter- 10 Hr $ 83.02 $830.20
Operator Hr $ 85.93 $0.00
Plumber/Pipe Fitter Hr $ 91.50 $0.00
Foreman Hr $ 86.72 $0.00
Superintendent 12 Hr $ 93.00 $1,116.00
General Su erintedant Hr $ 126.87 $0.00
Project Manager Hr $ 100.00 $0.00
Overtime-Add$30.00/Hr Hr $ 30.00 $0.00
Sunday&Holidays-Add$48.00/Hr Hr $ 48.00 $0.00
MAGNEY Material
1.5"Copper $210.00
1.5"Curbstop $297.00
MAGNEY Equipment
Trench Box $350.00
Kamatsu 360 $0.00
Mileage 76 Miles $0.65 $49.40
Pick Up Truck 0 day $90.00 $0.00
SUBCONTRACTORS/SUPPLIERS
Fobbe Contracting-Wet Tap $800.00
SUBTOTAL MAGNEY LABOR, MATERIALS,
SUBCONTRACTORS $3,013.42 $556.40 $800.00
MAT.HANDLING LABOR:4%OF MAT. $22.26
SMALL TOOLS MAT.:6%OF LABOR 1 1 $180.81
SUBTOTAL $3,035.68 $737.21 1 $350.00 $800.00
MAGNEY OVERHEAD/FEE 15% $455.35 $110.58 1 $0.00 $40.00
SUBTOTAL MAGNEY LABOR $3,491.03
SUBTOTAL EQUIPMENT1 $350.00 $350.00
SUBTOTAL MATERIAL $847.79 $847.79
SUBTOTAL SUBCONTRACT 1 $840.00 $840.00
SUBTOTAL $5,528.81
MATERIAL SALES TAX-7.275% $53.63
BOND/INSURANCE-0.015 $83.74
BUILDERS RISK INSURANCE N/A
TOTAL THIS COST PROPOSAL $5,666.18
Page 1
AGNEYC O N S T R U C T 10 N Proposal
COMMERCIML U MDUSTRIAL CONTRACTORS PR-2
W-3—z%; 1401 Park Road - Chanhassen, MN 55317
www.mayney�stniction.com 952.474.1674 Office 952.474.1679 Fax C01-6
SEND TO
Company name From
MSA Peter Aldritt
Attention Date
Lucas Jones 6/28/2016
Fax Phone Proposal#
PR-2
❑ Urgent ❑ Please comment ❑ Please review X❑ For your information
Total pages, including cover: 1
COMMENTS
RE: Lake Elmo Booster Station PR-2
Lucas,
We are offering the following price quotation to add a continuous layer of 1/2" Rigid Insulation under the siding.
Labor: $ 415.00
Material: $ 554.39
Tools & Equipment: $ -
Subtotal $ 969.39
General Contractor's Overhead $ 62.25
Bond & Insurance premiums $ 15.47
Total $ 1,047.11
Additional Working Days Required for this Change: 0.0
Please review this proposal and feel free to contact me with any questions, comments or concerns.
Thank you,
Peter Aldritt
Project Manager Accepted By Date
Page 1 of 1
N ST R U CT I ON Proposal
AGNEYCO
�� LUMMERCIAL U iitiUUSTRIAL Luiy i r ACTORS c01-7
�� 1401 Park Road - Chanhassen, MN 55317
www.mag�construction.com 952.474.1674 Office 952.474.1679 Fax
SEND TO
Company name From
MSA Peter Aldritt
Attention Date
Lucas Jones 7/12/2016
Fax Phone Proposal#
MC-P3
Urgent Please comment X❑ Please review For your information
Total pages,including cover: 1
COMMENTS
RE: Removing Motorized Gas Shut off Actuators
Lucas,
We are affering the following price quotation in regards to removing the Emergency Gas Shut off Actuators.
Material: $ _
Labor: $ _
Subcontractor: Vessco - Removing Actuators $ (9,000.00)
Subtotal $ (9,000.00)
General Contractor's Overhead $ -
Bond & Insurance premiums $ (135.00)
Total $ (9,135.00)
Please review this proposal and feel free to contact me with any questions, comments or concerns.
Thank you,
Peter Aldritt
Project Manager Accepted By Date